| More than ever, with hundreds of megawatts
built and hundreds of megawatts more planned, wind power has
been tapped to generate electricity to help replace fossil
and nuclear fuels and provide customers with the option of
using "green power."
Although wind power is not a new concept, the viability of
selling the electricity produced from these turbines has improved
in recent years due to technological advancements, as well
as government mandates and incentives.
One wind power project located in southeastern Minnesota,
about 20 mi. west of Rochester, has gone through the required
development hurdles and is now producing and delivering its
green power to the utility grid.
The utility interconnection and collection grid, developed
by Garwin McNeilus's GM Transmission LLC in Dodge Center,
MN, came together through a carefully orchestrated plan.
Numerous 1.5- to 2-MW wind power projects have been connected
to the collection grid. To date, the interconnection can accommodate
50 MW of wind capacity with a total of 70 MW expected after
future transmission upgrades. If so, it will be among the
largest wind farms owned by an individual.
McNeilus, the owner, used to own a large manufacturing company
that supplied more than 90% of the concrete trucks in North
America but sold it in 1998 to pursue other interests, such
as developing wind power and building orphanages, churches,
and schools around the world.
Technical
Togetherness
The wind turbines, manufactured by NEG Micon, a Danish company,
have capacity ratings of 950 kW and 1,500 kW and have been
installed on 300-ft. towers on the selected, rural site near
Dodge Center. Though they appear small from a distance, the
generators that sit on top of the towers are taller than an
average-size person.
The turbine blades have a 75-ft. radius, and when lying down,
the hub of the blades is also towering.
The wind farm started with 10 turbine generators and expanded
by adding 15 more in the first phase. The second phase added
21 more turbine generators, bringing the total to 46. With
the total capacity at 50 MW, the farm will produce enough
energy for more than 13,000 typical homes.
Green: The
Name of the Game
Green power is the term being used most often for
environmentally friendly renewable energy. It applies to all
types of energy produced from renewable sources in nature
instead of from fossil fuels or nuclear power. There are five
principal sources of renewable energy: sunlight (solar), wind,
moving water (hydroelectric), organic plant and waste material
(biomass), and Earth's heat (geothermal).
Green power is seen as a way to reduce carbon dioxide and
particulate emissions associated with coal burning and reduce
radioactive waste associated with nuclear power generation.
With many states taking proactive stances to increase the
amount of green power produced and used, the Minnesota wind
farm is positioned to help meet those requirements.
Complicated
Course
A key component that made the Minnesota wind farm project
a challenge, however, was the climate that was unfolding in
the power and transmission market. At the same time that the
technology advances were making wind power economically viable,
the restructuring of the electric utility industry has complicated
the procedures required for a wind generator to interconnect
with and deliver power to an electric utility.
Navigating the procedural path can be a confusingbut
crucialproject component. The wind farm project, however,
was able to map a course for success with some key steps.
At this particular wind farm, the developer needed to identify
interconnection requirements and develop a transmission interconnection
agreement with Xcel Energy of Denver/Minneapolis, the owner
of the transmission grid, and with the Midwest ISO (Independent
System Operator) in Indiana, which oversees the interconnections
to and operation of the transmission system. The interconnection
agreement was needed as quickly as possible to get the power
generated into the market. It also was important to initiate
the procedures providing for the delivery of the power because,
under the new regulatory scheme, the delivery process is separate
from the interconnection process.
R.W. Beck was employed to dual-track both an interconnection
study and the design/construction phases of the project and
to monitor the delivery process.
Some of the key project details included:
- collecting technical information for an interconnection
study;
- coordinating the interconnection study scope/assumptions
and monitoring progress;
- modifying agreements to reflect the project specifics;
- coordinating interconnection designs with substation
designs;
- providing technical support for the interconnection design;
- reviewing the substation design;
- preparing relay settings for substation protection devices;
- specifying, procuring, and coordinating the installation,
programming, and testing of metering, meter interface, supervisory
control and data acquisition, and telephone protection and
relay equipment for a transfer trip scheme;
- monitoring the progress of all project participants to
alleviate any bottlenecks;
- specifying, receiving, and evaluating bids and preparing
contract documents for procuring a larger interconnection
transformer for later phases.
The main project goal was to help GM Transmission LLC navigate
through the maze to meet the interconnection and delivery
requirements of Xcel Energy and the Midwest ISO and to keep
the process moving so the wind turbines could be connected
and begin generating power (and producing revenue) as soon
as possible.
Time Is of
the Essence
With the utility industry still uncertain and undergoing possible
regulatory changes, project developers should make their requests
for interconnection as soon as possible once the project has
been given the go-ahead by investors. One of the aspects considered
in the interconnection studies is the effect of the proposed
generating project on the stability of the transmission system.
With the widespread power outage that recently occurred in
the Northeast United States and parts of Canada, this aspect
of interconnection is likely to received increased scrutiny,
which can only increase the time needed for approvals. The
time required for study, design, equipment procurement, and
construction should be identified as early as possible. As
the interconnection process develops, everyone involved should
be encouraged to remain focused on the project at hand: getting
the wind farm producing clean green power for customers.
Guest author KEVIN FAVERO is a senior director
in R.W. Beck's Minneapolis office.
DE - Nov/Dec 2003
|