|
The winds blowing across eastern New Mexico will soon fuel
the nation's third-largest wind-powered generator. Because
of the wind farm's remote location and the nearly 25 out-of-state
contractors who traveled there to build it, rental equipment
played a crucial role.
The $200 million wind farm stretches along 15 mi.2 (9,600
ac.) of land northeast of Fort Sumner on the Taiban Mesa.
It is composed of 136 turbine towers, each more than 20 stories
high and topped by 110-ft. propeller-like blades. The rotating
blades cause a generator at the top of each tower to produce
electricity, which feeds into a nearby high-voltage power
line owned by the Public Service Company of New Mexico (PNM).
The farm will produce enough power to supply more than 90,000
homes.
 |
PNM and Florida Power Light and Energy LLC (FPL Energy),
which leads the United States in wind energy production with
28 wind facilities in 10 states, signed an agreement for the
204-MW wind farm in a major step to diversify New Mexico's
energy sources.
The development stage of the project started in 2001 with
negotiations between PNM and landowners. Rusty Hurt, project
superintendent for FPL Energy, says, "There were also
extensive engineering studies that had to be performed to
prove that this plant would interact properly with the electric
grid."
Herling Construction crews began to construct a series of
dirt roads on the Taiban Mesa, near the small town of House,
NM, in March 2003. The crew rented 10-ton rollers and 4,000-gal.
water trucks from Rental Service Corporation (RSC) during
this phase. It was a critical first step in transforming a
portion of the mesa into an energy production facility that
produces no air emissions and uses no water to generate electricity.
"And only four and a half months later, in late July
2003, we were on-line," Hurt says.
According to Hurt, the most challenging aspect of the job
was the remoteness of the site. "It made preplanning
for tasks especially crucial. Being short just one bolt for
a component causes a major delay. It was an hour to the nearest
hardware storeand the same goes for equipment. For such
a short-duration job, it is agonizing to wait on equipment
to be delivered to a remote site." He says crews used
rental equipment and the RSC equipment storage sheds to overcome
this challenge.
Nearly all of the equipment on-site was rented, according
to FPL Energy, the general contractor.
Hurt adds, "Because of the remote location, it was often
more economical to rent the equipment locallyeven though
the contractor may have owned the same piece of equipment
four states away."
At the job site RSC filled two storage boxes with equipment
that Hurt and RSC Sales Representative Valerie Wheatstine
anticipated contractors would need.
"This site was literally out in the middle of nowhere,"
Wheatstine says, "and when the contractors needed equipment,
they needed it nownot in four hours. So we decided to
set up two 'convenience stores' that had everything from light
towers and generators to pressure washers and light compaction
equipment. In addition, the storage bins contained retail
items like safety vests, lanyards, earplugs, and hardhats.
Whenever contractors needed something, they just checked it
out and let an [FPL Energy] administrator know."
Hurt says FPL Energy decided to rent from RSC because of its
"service, service, service."
"RSC was extremely flexible in setting up the onsite
warehouse of equipment that all contractors could access,"
he says. "Since we didn't have to wait for equipment
delivery, we didn't have any work delays."
 |
Contractors rented everything from boom lifts to power tools
from RSC. several fuel and water trucks were also on-site
to keep equipment moving and the dust still, Wheatstine says.
The following companies offered additional pieces of equipment:
- Beard Industries Inc. rented dozens of generators and
compressors.
- Great Southwestern Construction rented skid-steer loaders,
loader attachments, and articulating boom lifts.
- Herling Construction rented large excavators, several
4,000-gal. water trucks, three 84-in. rollers, compressors,
light-compaction equipment, and generators.
- Kemco Corporation rented a rough-terrain forklift.
- J&J Powerline rented compressors, air breakers, generators,
light compaction equipment, and light towers.
- Milco Constructors Inc. rented post drivers, water trucks,
pressure washers, generators, air compressors, a laser level,
several 10,000-lb. variable-reach forklifts, pickup trucks,
equipment trailers, a 500-gal. water trailer, and two containers.
- Power Line Constructors Inc. rented a backhoe breaker,
ride-on padfoot rollers, and air compressors.
Hurt thinks the most impressive technique used during construction
of the wind farm was the way in which materials were transferred
to construction teams. "Assuming that each turbine requires
seven oversized truckloads of components, we had to flow over
1,000 truckloads into their assigned locations in about a
60-day window of time," he says. "We built that
temporary road system, which allowed a smooth, one-way flow
of traffic through the site."
The New Mexico Wind Energy Center was fully operational in
July 2003, and now that construction is complete, 95% of the
land leased for the wind center is still available for other
uses, such as grazing and crop production. FPL Energy will
own and operate the facility, and PNM will purchase all of
its output for the next 25 years.
APRIL GOODWIN is a technical writer based
in Des Moines, IA.
DE - Nov/Dec 2003
|