|
Reliability has taken on a new prominence in recent years.
An aging and increasingly complex transmission-and-distribution
infrastructure has added reliability risks to equipment failure
and random system collapse. Users must deal with the operational
impacts, and many are reevaluating the reliability of the
systems as well as potential replacements for them, including
distributed energy. This article discusses how a typical reliability
study can unfold to support a business case for distributed
energy.
 |
Reliability
Studies
A complete power-reliability study should examine the power
system both inside and outside a facility. Outside, reliability
can be determined by utility "rolling blackouts,"
outages caused by power shortages rather than equipment failures;
equipment redundancy; feeder routing; automatic sectionalizing
schemes; utility testing; preventative maintenance practices;
and tree-trimming schedules. Reliability of the internal power
system might be affected by physical protection of feeders,
power-supply redundancy, equipment testing schedules, and
preventative maintenance practices.
Required Levels of Reliability
The total money and effort needed to improve power reliability
depends on the possible consequences of power outages. The
highest level of power reliability is required for "life-safety
systems," such as emergency lighting or ventilation,
which must operate properly to prevent the loss of human life.
The National Fire Protection Association's codes and
standards describe life-safety systems and the design criteria
and maintenance practices required to provide those systems
with reliable power.
The second-highest level of power reliability is required
for systems that prevent damage to plant infrastructure (e.g.,
sump pumps at a wastewater treatment plant), allow monitoring
of other systems (e.g., supervisory control and data acquisition,
or SCADA, systems), or prevent the loss of vital data during
power failures (e.g., at bank data centers) or whose failure
to operate could significantly impact public health.
The third-highest level of power reliability is required
for processes that would cause sizeable financial losses if
power outages occurred. Power outages cause loss of quality
control in batch processesfound at microelectronic component
manufacturing, food processing, chemical processing, and oil
refining facilitiesand force owners to discard entire
batches. In addition, power losses to processes that operate
24 hours per day, seven days per weekwith no openings
to recover lost production timecan lead to cancelled
orders.
The lowest level of power reliability is adequate for equipment
and processes for which operation is not time-critical. Operating
this type of equipment, such as a cooling system with a large,
cool storage tank, can be deferred to off-peak times; switched
to an alternate source, such as an engine generator; or switched
to an alternate fuel, such as an electric heating system with
fuel-oil backup.
Redundancy
Redundant power supplies do not always improve reliability.
If two redundant feeders supply power to an industrial facility
but originate at the same utility substation and are carried
on the same set of power poles, reliability will be lower
than if they originate at separate substations and travel
to the site on different sets of power poles. The problem
with redundant feeders carried on the same set of poles is
that a single-point failure (e.g., a weather-related event,
pole fire, or traffic accident) could cause simultaneous outages
on both sources.
Assessing
Existing Power Reliability
Assessing power
reliability at an existing facility requires examination of
three or four years of feeder-outage history provided by the
serving utility. Causes of outages must be identified, durations
of outages must be quantified, and equipment testing schedules
and preventive maintenance records must be examined. Written
maintenance and testing records provide useful data for determining
how reliably power systems can be expected to perform.
Improving Utility Power-System Reliability
Regular tree-trimming will improve the reliability of overhead
feeders. Routing overhead feeders away from roads and highways
can reduce damage from motor vehicles. Underground feeders
might provide higher levels of power reliability in areas
with high winds, frequent lightning strikes, heavy forestation,
and ice storms.
Most utilities schedule regular testing of power-delivery
equipment to ensure a high level of reliability. Testing includes
analysis of transformer insulating oil for the presence of
water or gases that would indicate pending failures. Power
circuit breakers and protective relays should be tested on
a regular basis for proper operation and correct calibration.
Substation batteries must be tested for proper voltage and
capacity. Some utilities now perform nondestructive testing
on underground feeder cables to anticipate pending cable failures
and proactively replace the cables before faults cause unscheduled
outages.
Recently in California, utilities have resorted to rolling
blackouts. Previous shortages were very rare or very localized
but lately have increased as a result of utility deregulation.
Inspired by media coverage of rolling blackouts and dramatic
spikes in natural-gas prices, other regions with tight power
supplies are evaluating capacity requirements and scrambling
to install new generation-energy systems to prevent similar
scenarios.
Improving
Industrial-Facility Power-System Reliability
Inside an industrial facility, reliability can be improved
by protecting electrical equipment from physical damagefor
example, by placing underground feeders in concrete-encased
duct banks. Redundant feeders and automatic transfer schemes
often are used to improve reliability. To minimize the chances
of single-point failures causing simultaneous outages, redundant
feeders should be routed along different paths within the
plant but should not pass through common manholes.
In addition to the regular maintenance performed by utilities,
owners need to plan for regular inspection, testing, and maintenance
of their breakers, protective relays, and automatic transfer
schemes to ensure power reliability. For example, automatic
transfer switches should be tested periodically to verify
that mechanisms operate freely.
Looking to
Distributed Energy
At this point, the owner should decide if the reliability
risk has been mitigated sufficiently through the discussed
delivery and protection assessments and the potential improvements.
This step allows a strong business case to be developed in
support of distributed energy.
Some owners opt to improve power reliability by installing
standby generation, uninterruptible power supplies (UPS),
flywheels, or fuel cells. The chosen system depends on the
length of outage the owner can tolerate. Diesel engine generators
require about 10 seconds to start, reach rated speed, develop
rated voltage, and begin powering loads. Where even momentary
outages are unacceptable, owners must install UPS or flywheels.
Fuel cells have become commercially available and have performed
as highly reliable power sources. A bank data center in Omaha,
NE, recently installed fuel cells as its primary power source
to maximize reliability and minimize data loss.
Peak Shaving
With Onsite Generators
With proper interconnection to an industrial-facility power
system, onsite generators can be used for both standby and
peak shaving purposes. Taking advantage of peak shaving rates
helps justify the capital, operating, and maintenance costs
of onsite generators. Owners should be aware, however, that
standby and peak shaving requirements are often quite different.
Loads requiring emergency power are usually very small and
might not be running continuously, whereas ideal loads transferring
generator power for peak shaving will be relatively large
and will operate continuously.
To determine whether existing standby generators can be used
for peak shaving purposes, follow these guidelines:
1. Determine the generator rating (kW capacity).
2. Determine the condition of the prime mover from maintenance
records and by completing a physical inspection (i.e., determine
whether operating the generator for peak shaving purposes
will require an overhaul of the prime mover).
3. Develop a spreadsheet to inventory all existing connected
loads.
4. Sort through the connected-loads list to determine which
loads are no longer in service.
5. Measure the actual load(s) on the generator(s) to determine
whether capacity is available to power additional loads.
6. Review utility peak shaving rates to determine peak shaving
benefits.
7. Calculate peak shaving costs from generator fuel-consumption
data and maintenance requirements.
If an existing standby generator appears to have capacity
available beyond the current requirements for emergency loads,
loads should be added with caution to avoid overloading. To
ensure that power is always available for critical loads,
either standby generators must be oversized or load-shedding
equipment must be installed. If load-shedding equipment is
installed, loads must be grouped by priority. During utility
power failures, the load-shedding equipment always connects
the highest-priority loads to the generator first, the second-highest-priority
loads next, and so on. If the load-shedding equipment detects
loads with kilowatts in excess of the generator rating or
decreasing frequency (also indicating generator overload),
it quickly sheds loads (starting with the lowest priority)
to ensure that reliable power reaches critical loads.
Conclusion
Every facility operator should understand the level of power
reliability required for operations. Power-supply reliability
is no longer affected only by equipment failure. As is the
case in California, power reliability also can be reduced
by power shortages. If a facility experiences a utility outage,
do the critical processes have backup power to avoid a catastrophic
event? Are the existing onsite generators being used to full
capacity? Is it possible to maximize onsite generation to
its full capability and satisfy the required level of power
reliability? From the experiences in California and the Northeast,
it is evident that power outages are no longer caused only
by equipment failure and that measures need to be taken to
assess power reliability at industrial facilities. Consideration
of these questions can provide a solid business case for distributed
energy as the best option to quickly resolve reliability risks.
MATT CLARK, P.E., BOB THAYER, P.E.,
and JOHN SPANHAKE, members of HDR Engineering's
Power & Energy Group, work nationally in the power industry,
providing services in the areas of energy studies, generation
system design, transmission and distribution, and the environment.
DE - Jan/Feb 2004
|