|
"Microturbines fit into the overall distributed-generation
mix," says Jeffrey Pierce, vice president of SCS Energy
in Long Beach, CA, but the qualifier is the fuel. Although
originally designed to be fired by natural gas, propane, or
diesel, Pierce thinks where such "free fuel" as
landfill or digester gas is available, microturbines might
be just the ticket for beating high power costs. Buying natural
gas at inflated prices in places like Ohio and trying to compete
against coal-fired electricity, however, isn't an attractive
economic proposition, even if you can manage to utilize the
heat from the turbines in a combined heat and power (cogeneration)
system.
 |
| A wastewater treatment plant
in Lancaster, CA |
Microturbines are smaller versions of the megawatt machines
widely used in large distributed-energy installations. Some
designs use the turbine to drive an off-the-shelf generator
through a gearbox. A more unconventional approach is to use
a single-shaft turbine with a high-speed, permanent magnet
generator to produce variable-voltage, variable-frequency
AC power. The NOx emissions targetoften a major factor
in deciding on turbine-generated poweris less than 9
ppm in practical operating ranges. Recuperated microturbines
recover heat from the exhaust gas to boost the temperature
of combustion and increase efficiency. Unrecuperated units
have lower efficiency but higher exhaust temperatures, which
makes them better suited to applications that can recycle
the heat. Microturbines are low-maintenance and run basically
unattended. On a 24/7, 365-day basis, the typical useful life
of a commercially available unit ranges from 40,000 to 80,000
hoursapproximately 10 yearswith overhauls. Installed
cost (without incentives) is typically from $1,500 to $3,000/kW,
depending on the difficulty of the fuel and site integration.
Given its current high electrical rates and strict air-quality
standards, California has become a hotbed of early-adopter
microturbine activity. At Bentley Simonson Inc. (BSI), an
independent oil and gas producer based in Ventura, CA, that
operates seven oil fields in Los Angeles and Ventura Counties,
President and CEO Clif Simonson was on the lookout for a way
to rescue what appeared to be a nonpayout project. Faced at
one oil field with having to install a new gas-production
plant to meet changing gas standards, Simonson's problem
was how to dispose of what typically is considered wastewhat
the industry calls overhead vapor. "This is very challenging
in a tight urban environment," says Simonson. "You
can sell it to a company that fractionates it to make propane,
but there's not a good margin in that, or you can flare
it, which is not legal in Los Angeles. Then we got to thinking:
What if we were able to offset our cost of electricity on
that site by using overhead vapors to generate electricity?
Suddenly we had a project that would pay offand [pay
off] fairly quickly."
Working first with Honeywell before it withdrew from the
microturbine market and then with Ingersoll-Rand Energy Systems,
BSI installed a 70-kW microturbine fueled by overhead vapors
from its gas plant to generate electricity that runs lift
systems, pumps, and gas-plant compressors at the oil field.
At Ingersoll-Rand, George Wiltsee confirms that the 70-kW
recuperated microturbine BSI first installed and the 250-kW
unit it has on order have an efficiency of 29% and 32%, respectively.
Electrical output is at 480 V and 60 cps.
BSI's initial installation included one 70-kW microturbine,
which is configured to burn 1,200- to 1,600-Btu fuel and switchgear.
"Regarding the fuel supply, it's rare that associated
gases are pure straight from the wellalthough if conditions
are right, you may be able to operate a turbine on that raw'
gas," says Simonson. "The fuel characteristics most
important for microturbine operation include the combined
Btu content of the various constituent gases, the types and
quantities of various contaminants, and the flow rate and
the gas pressure in the collection systems. You can purchase
an integrated fuel conditioner from Ingersoll-Rand that protects
the turbine from performance losses or damage by providing
levels of purity and pressure that are within the specific
engine tolerances. Our gas processing provides the correct
type of fuel as a byproduct." As Simonson describes it,
"once separated from the crude oil pumped at the field,
the vapor flows through the LTS [low temperature separator];
the liquids are removed from the raw feed gas, compressed,
and chilled; and unwanted contaminants are eliminated. The
natural-gas liquids are stabilized, and the byproducts of
this heating process, overhead vapors, are then compressed
to approximately 80 psig and then flow through a small receiver
tank and into the microturbine. Software controls the flow
rate." (Conditioning is typically required for other
opportunity fuels, both high-Btu and low-methane, such as
biogas. Manufacturer Ingersoll-Rand can provide a fuel conditioner
as part of its microturbine package.)
BSI's first 70-kW unit was installed in February 2003
and so far has logged approximately 3,600 hours and generated
216,000 kWh of electricity, and the company has gone on to
plan the installation of microturbines in three other oil
fields. Simonson estimates his initial $75,000 investment
has resulted in a monthly savings on electricity of just more
than $3,000 at the field where it's operating.
"I was pretty shocked by the numbers," says Simonson.
"But a project like this has to be analyzed very thoroughly.
People get fooled into thinking it's as simple as putting
in a turbine and buying gas from the gas company. We looked
at reciprocating engines for this project, but they require
catalytic converters, fuel-air ratio controllers, and a host
of other equipment that make the project much more challenging
and hard to permit. Plus, the cost of maintenance is higher.
These considerations, coupled with a 42% DG [distributed-generation]
incentive from the California Energy Commission, helped offset
the capital cost, and a one-time microturbine exemption from
the SCAQMD [South Coast Air Quality Management District] clinched
the decision."
Like any distributed-energy system, coupling power with load
is crucial. BSI evaluated running parallel with the grid,
which would mean covering base load with the turbine and peak
load with electricity from the utility, and running independent
of the grid, which would require a steady state load (not
the case with BSI facilities) and gearing up to cover the
peak and exporting the excess. Simonson opted for a parallel
grid system in all of the company's four microturbine
installations and to size the turbines to pick up 6095%
of the base load.
 |
| A BSI site in East Los Angeles |
Not long after the first turbine was installed, the company
again found itself faced with having to alter its production
process to meet shifting regulations at another of its Los
Angeles County fields. "To meet the new regulations, we will
be generating even more of these overhead vapors at this site,"
says Simonson, "and once again we went to a microturbine solution,
which we now consider an important tool for meeting changing
regulations. In this case, five 70-kilowatt microturbines
will be installed for a combined capacity of 350 kilowatts."
Although Ingersoll-Rand also offers a 250-kW unit, Simonson
says the choice of the five smaller turbines was deliberate.
"Typically the utility bills you for how much electricity
you use; for your VARS, which is your power factor; and for
your demand charge, which reflects spikes in demand for power
off the grid. We got to thinking about how much it would cost
us at this facility when our turbines went down for their
monthly air-filter change and minor maintenance, and although
we had originally specified one 250-kilowatt unit and one
70-kilowatt unit for that site, we went back and modeled the
system assuming [it would have] all 70-kilowatt units with
only one or two going down at a time, which would reduce our
exposure to utility demand charges. The multiunit scenario
resulted in a major savings in demand charges. You've got
to know all of this information: the demand charges, the tariffs,
the disconnect charges, the difference between your summer
and winter bill."
Although most of its oil field operations don't avoid
the chance to use heat for cogeneration, BSI eventually found
an opportunity to take advantage of combined heat and power
(CHP) incentives. "At our Sansinena Field, we will be
operating a diethanol amine [carbon dioxide extraction] unit
that normally uses a gas-fired burner as part of the process.
We looked at all that hot air coming off of our microturbines
and asked our process engineering firm to come up with a heat-transfer
solution that would allow us to take the heat from the turbine
exhaust and heat our DEA plant. Capturing the CHP incentive
was a huge driver for that installation." Plans at this
Saninena Field (which is served by a different utility and
is not subject to excessive demand charges) call for installing
one 250-kW microturbine, which will be combined with the waste
heat recovery unit, and two 70-kW units for a combined capacity
of 390 kW. Anaheim, CAbased Vanson Engineering's
Projects Manager Dick Scott, who designed the Saninena CHP
fix, estimates the field's power-generating facility
will recover about 700,000 Btu or about 3032% of the
waste heat and then run it back through the DEA unit. Based
on last year's electrical expenses, BSI believes that
this equipment should help reduce electrical costs by $250,000/yr.
over the entire project.
"In a turbine, you have air at about 10 times the volume
of gas going into it," says Scott.
With a 250-kilowatt turbine, you'd have about 14,000
pounds per hour of a 500° gas; with a reciprocating engine
of the same size, it would be 1,000 pounds. So in one sense,
the turbine is less efficient than the internal combustion
engine, but overall the turbine is more efficient because
you're taking advantage of all the air you're heating
up, which is another thing to consider in CHP applications.
You wouldn't even attempt to recover the heat off of
a corresponding-size reciprocating enginethere's
just not enough available to make it worthwhile, whereas on
a microturbine equivalent to 300 horsepower, you can recover
maybe 800,000 Btu an hour." Scott also points out that
microturbines weigh less than reciprocating engines, which
gives them a leg up in applications where weight is a factor,
such as on offshore oil rigs where turbines will also produce
less vibration than reciprocating engines.
Lessons learned? "Front-load all of your critical paths,
such as permitting, applications for incentives, and your
interconnect agreement with your utility," says Simonson.
"Do that the day you make the decision to go with microturbines.
Use an integrated approach. Consult an electrical engineer
andif applicablea process engineer. Keep your
eye out for incentives, but be aware that sometimes the cost
of capturing an incentive can be a wash with respect to the
time you have to invest and the capital costs you have to
endure to meet the special requirements that many incentive
programs impose. Most of all, plan, plan, plan, then execute.
I bet we've been through 50 economic models on these
projects, reengineering them, looking at them again, then
reengineering [them] again."
 |
| San Diego County's Jamacha
Landfill microturbine system |
Elsewhere in southern California, conditions were right for
installing microturbines at a closed landfill operated by
Monterey Parkbased New Cure Inc. In July 2001, the California
Public Utility Commission OK'd a hike in Southern California
Edison's retail electrical rate from $0.10/kWh to $0.14/kWh
(average numbers that take into account the complicated rate
structure), which increased annual power costs at the landfill
to $440,000. Anaerobic decomposition of organic solid waste
in landfills produces landfill gas (LFG) consisting mainly
of methane, carbon dioxide, and trace constituents. Because
LFG can migrate through soil into structures located on or
near landfills and because methane presents a fire hazard
or explosive threat, LFG at both operating and closed sites
must be controlled to protect property and public health and
safety. Additionally in many jurisdictions, landfill operators
are required to reduce reactive organic gas emissions to improve
regional air quality.
Given the increased cost of electrical power at the New Cure
facility, SCS Energy, which specializes in landfill systems,
suggested that the company consider a feasibility study for
an onsite power-generation facility. The landfill operator
agreed but responded with a list of caveats. First the facility
would be sized for the onsite load because Southern California
Edison wasn't buying power at the time and because a
retail deferral installation was considered to have a lower
capital cost and a higher return on investment, even if the
utility had been buying. Whatever power plant was recommended
would have to be fueled exclusively by LFG, and the technology
was to be limited to microturbines because the LFG at the
site had a low methane content and low NOx emissions were
a high priority with regulators. (The United States Environmental
Protection Agency [EPA] estimates that one million tons of
landfill are capable of producing 800 kW of microturbine power
and that a 70-kW microturbine consumes as little as 1,200
m3/day of LFG.)
"It's a pretty select set of circumstances to which
microturbines are applicable in this industry," says
Pierce. "Primarily you have to have a site that has a
significant enough load, and then you have to have that load
aggregated at one point for a project to be economically viable.
Typically on a landfill, the load is spread out, and you can't
connect it economically to get to a central point."
At the New Cure landfill, loads were distributed between
four operations: the landfill gas treatment system (LFGTS),
a leachate treatment plant (LTP), an office building, and
a booster blower. The LFGTS and the LTP were adjacent to each
other, but the office building was across the eight-lane Pomona
Freeway, and the booster blower was another 580 m away. SCS
recommended that the adjacent LFGTS and LTP loads be combined
and served by a 350-kW microturbine power plant (five 70-kW
units), the office building by a 70-kW facility, and the booster
blower by a 30-kW unit, all installations considered economically
feasible by the company. The SCS study was submitted to EPA
for funding approval in September 2001, at which time the
agency decided that a 99.99% destruction and removal efficiency
(DRE) of trace compounds would be required for the LFG generated
at the site regardless of whether it was flared or used as
fuel. At the time, the facility was producing an LFG treated
with a thermal oxidizer capable of a DRE of 99.95%, which
the microturbines were not expected to achieve.
At Ingersoll-Rand, Wiltsee observed that although microturbines
are efficient combustors of methane, they are not designed
to completely eliminate trace amounts of contaminants, such
as the nonmethane organic compounds (NMOCs) in LFG. Most landfills
must meet a 98% destruction-efficiency requirement for NMOCs,
which microturbines can meet. The problem was that the New
Cure landfill is a Superfund site with strict requirements
closely monitored by EPA.
SCS came back with a solution that directed the microturbine
exhaust into the LFGTE (the microturbine units were expected
to use only 5% of the gas produced on-site). Because the oxygen
content of the microturbine exhaust is so high, it would not
impact mixing and combustion in the flare, nor would it affect
the operation of the LFGTS; nonetheless, there were problems.
The requirement to route the exhaust to the LFGTS effectively
thwarted the plan to use microturbines at the office building
and the booster blower on the opposite side of the freeway.
Furthermore, to overcome the problem whereby Ingersoll-Rand's
factory-installed onboard compressor could not be upgraded
to raise the required quantity of LFG to the 5.5-atm gas required
by microturbines, a positive displacement blower was used
to prepressurize the LFG, and a chiller and heat exchanger
were provided for moisture removal. This pretreatment equipment,
including all nonutility electrical and control equipment,
was designed and constructed on one skid, which allowed for
offsite assembly and testing.
The LFGTS was equipped with combustion air fans to enhance
the fuel mixing and combustion, and finally control of the
microturbines was interlocked with the operation of the LFGTS
to avoid backflowing the microturbines' exhaust out of
the combustion air inlets, which could occur if the LFG system
was off-line while the microturbines were on. The challenge
of matching power generation to the onsite load was solved
by generating more power than needed and through an agreement
with the utility to "inadvertently" export excess
to the grid. Inadvertent export turned out to be the most
workable option, given that the power demands of the site
had significant swings and that there was notable diurnal
variation in power plant output based on ambient air temperature,
which affected the density of the combustion air. Since turbine
power output increases as ambient air temperature decreases,
the power demand was arranged to be greater at night, thereby
matching maximum load with maximum power output. The export
decision required negotiating an agreement with Southern California
Edison for an export limitation of 150 kW. The utility eventually
charged New Cure $105,000 for upgrades to its side of the
meter, including a new main transformer, a ground bank, and
wiring modifications.
Like BSI, New Cure signed a five-year, fixed-price maintenance
contract with Ingersoll-Rand, wherein the manufacturer will
supply all scheduled and unscheduled maintenance at a fixed
cost per year, an expense expected by the company to account
for 70% of the power plant's overall operation. SCS also
secured a $105,000 grant under the California Energy Commission's
innovative peak loadreduction program and a $450,000
grant under California's Self-Generation Incentive Program
(modified to add noncogeneration-based projects to the eligibility
criteria), which helped offset the cost of facility installation.
The New Cure microturbine plant first produced electrical
power in late August 2002, six months after signing a contract
for SCS to provide a turnkey operation. Between October 2002
and January 2003, the plant was on-line 86% of the available
hours; by the end of January, the plant was on-line 95% of
the available hours, and the microturbines, designed for a
methane content of 35% or greater, have demonstrated the ability
to run on contents as low as 29% methane. Savings in "avoided
electrical costs" recently have approached $30,000 a
month.
"This is not something you do to get rid of your landfill
gas," says Pierce. "This is a value-added proposition
at a site. When designing a project, we typically run multiple
proformas to look at different sizes of projects, bouncing
off the distribution to power demand to come up with an optimal
size. Invariably it's some point between the average
demand and the peak load. It's never economical to actually
cover the whole peak, but you would be surprised how many
people start out their projects by sizing them based on their
peak demand."
 |
 |
| The Calabasas Landfill microturbine
power plant and pretreatment skid |
Where does Pierce see microturbines going? "Certainly when
you get up to a megawatt, I don't think you're going to see
microturbines replacing reciprocating engines as the technology
of choice. I think the battleground is in the lower capacity
range, and it's really on a case-by-case basis. The advantage
that microturbines have is they can tolerate a lower methane
content in the fuel. That's important in this industry because
some of our older landfills out here in dry climates don't
have 40%-plus methane, which is the minimum a reciprocating
engine can operate at. Also if you have an air district that
places a high priority on NOx emissions, the microturbines
are much lower than reciprocating engines. Another factor
is that Ingersoll-Rand is willing to guarantee maintenance
costs for over five years at a favorably fixed price; for
these smaller engines, reciprocating engine manufacturers
are not generally willing to provide that kind of agreement.
On the negative side, on a dollar-per-kilowatt basis installed,
microturbines are a lot more expensive. But if you have a
40% capital-cost grant like those available here in California,
that mitigates the sting of the additional capital costs."
Biogas of another sort has long been used to generate electricity
by the County Sanitation Districts of Los Angeles, where Division
Engineer Ed Wheless says the agency has been in the business
of producing its own power since 1938. "We have a long
history of using renewable fuels," says Wheless. "We
generate something like 133 megawatts from all of our different
landfills and treatment plants. As of now, none of this is
done by reciprocating engines." The challenge at the
agency's Lancaster wastewater treatment facility was
to find a turbine that would fit the amount of biogas produced.
When the Ingersoll-Rand 250-kW unit came on-line, Wheless
jumped, also taking advantage of a California self-generation
capital-improvement grant. "Assuming this project works,"
says Wheless, "it's almost the perfect application
for the smaller wastewater treatment plants that are just
about everywhere in every town and city in America. This is
something our districts here in Los Angeles strive to do every
day: to find uses for our waste and reduce the cost to our
ratepayers.
"The big thing for us is that we require something that
operates at a lower gas quality and also with low emissions.
Internal combustion engines are cheaper, but it doesn't
matter what they cost if you're not allowed to install
them." Asked whether the microturbine would have been
viable without the 40% capital-cost incentive, Wheless said
that even without the incentive, the microturbine the agency
purchased is "extremely cost-effective and would be viable"although
it probably would take longer than the one and a half to two
years now projected to pay for themselves. The districts'
system will involve cogeneration with heat from the turbine
exhaust generating hot water that will be routed to the facility's
digesters. Like LFG, digester gas requires conditioning, and
the county's 250-kW microturbine will come factory-equipped
with Ingersoll-Rand's new fuel conditioning system.
Across the county at the districts' Calabasas Landfill,
10 Capstone microturbines have been producing electricity
to run the onsite gas blowers for more than a year. Wheless
says the beauty of microturbines is the fact that they run
unattended. "I can tell you from the Calabasas installation
that it's a real eye-opener that you can have a system
operating on your site, and you don't have to know anything
about it. We don't have an operator; we don't have
to train our mechanics on how to maintain it. These are very
complicated factors for a larger organization to deal with.
With microturbines, all you have to do is walk by, take a
look, and see whether they're burning."
Journalist PENELOPE GRENOBLE O'MALLEY is
a frequent contributor to Forester Communications publications.
DE - Jan/Feb 2004
|