|
Twentynine Palms, CA, is home to more than
10,000 military personnel and their families who reside within
a sprawling facility called the Marine Air-Ground Task Force
Training Command. In relation to the Southern California Edison
(SCE) power grid, it's literally "at the end of the
line." Winters are mild, but summertime heat can hit
120°F and wreak havoc on the Marine Corps' electric bills.
Combat units here receive training in combined
air and ground maneuvers. Early in 2003, as United States
forces were preparing for war abroad, Twentynine Palms'
utility managers were commissioning a Solar Turbines Taurus
model for combined cooling, heating and power (CCHP). The
key objective was to slice the facility's reliance on
grid power by about two-thirds. In short order, the Marines'
new minigrid would be tying together the output from this
7.2-MW dual-fueled turbine genset [making it "one of
the largest cogen turbines" in the Department of Defense
(DOD), notes energy manager Gary Morrissett], with the electricity
produced by an onsite 1.2-MW solar photovoltaic (PV) array,
together with two incoming grid lines from SCE. As payback,
the Marines would be guaranteed savings in the range of several
million dollars annually for the next 19 years.
During 2003,
the first year of operation, Morrissett was able to scrutinize
the turbine's fuel consumption and power output on this
highly automated system, using its built-in advanced computer
controls. He found its efficiency could leap to "as
high as 75%," depending on the seasonal load - a
figure about two and a half times more efficient than conventional
power-company generation. In the low-load wintertime, Twentynine
Palms draws from 6 to 9 MW of power, but in the roasting heat
of summer, the figures virtually double, soaring to 15 or
20 MW - "mostly for air conditioning, of course,"
Morrissett says.
The good news
is that, as of early 2004, latter-stage extensions of the
cogen project were on target for routing the searing exhaust
of the big Taurus not only for the usual water heating but
also for cooling power, by linking
to three new and/or upgraded thermally activated absorption-chiller
plants.
Energy-Reliability
Concerns, Gas-Company Stake, Prodded Initiative
One key strategic
rationale behind this CCHP enterprise, at least initially,
was the fact of Twentynine Palms' remoteness relative
to utility-company generating and pumping stations. The base's
commanders have long had concerns about energy security. Backup
generators are in place, but they're not sufficient
to handle the consequences of an earthquake or some other
major interruption. Energy security "was a primary consideration
to us," Morrissett recalls. Another was the region's
notoriously high power rates, which probably made an investment
in cogen not only attractive but almost inevitable, even for
a public-sector site, given the potential for saving tens
of millions of dollars, long-term.
The turbine
idea had been kicked around since 2000, when Southern California
Gas offered to install a genset for the military under a utility-service-provider
(USP) arrangement. This would have been administered by the
Marine Corps' Southwest Division based in San Diego,
CA. An initial feasibility study and design then were commissioned
by the US Department of Energy's (DOE) Office of Distributed
Energy Resources (very keen on cogen). SCE then produced the
requested detailed rate and tariff data. Out of all the number-crunching
emerged an extremely attractive payback curve, along with
a few challenges, such as natural-gas supply and even the
adequacy of line pressure to pump it into the base.
Contractor Offers
the Corps a No-Lose Deal
As the assessment
went on, the concept of doing the project under a government-designed
Energy Performance Savings Contract (ESPC) emerged. ESPCs
basically enable federal agencies to hire contractors to help
them reduce their energy bills and then share in the net savings.
Such contracts are often more cost-effective and easier to
administer for government managers than a USP relationship.
With an ESPC, says Morrissett, "you're guaranteed
savings," and, should they not materialize, "the
difference is made up from the contractor's portion.
So there's very little risk on the government end."
Too, contracts can put the burden for maintenance, repair,
and replacement on the vendor, providing a strong incentive
not only for correctly assessing the potential savings, designing
and building the system, but also for its continued high efficiency.
The Marines solicited an ESPC contractor
and in September 2001 inked a deal with Johnson Controls Inc.
(JCI). For the next 19 years, the base would be guaranteed
the production of about 55 million kWh/yr. of cogen power,
thereby reducing its electric bill by $5.8 million/yr. All
in all, Morrissett's department would be looking at
"something like $57 million in total that we could work
with," during the contract's duration. All
of that money could readily fund more energy projects
under the same ESPC plan - and additional savings also
would be guaranteed.
Another attractive
provision was that JCI would handle the technically complex
challenges of reliably projecting the savings goals, specifying
appropriate products and soliciting bids, and completing and
implementing the final design, always keeping Morrissett in
the loop.
Funding was
arranged through the US Army Corps of Engineers and the Naval
Facilities Engineering Service Center.
"One
of the most interesting aspects is how the project came together,"
says BP Solar's Mac Moore. "Solar energy is of
course our specialty, but here it is just one of a suite of
onsite generating and efficiency measures that the project
manager, Johnson Controls, had to work with in developing
a total solution for the base." Moore believes that
this approach in conjunction with the use of ESPCs paves the
way for innovative financing of future projects.
Groundbreaking
took place in May 2002. West Coast Air did the major installation
and was joined by Walsh Engineering for the design and Baker
Electric for the wiring. A 3-mi.-long high-pressure natural-gas
line was laid to ensure the turbine's fuel supply. Stage
one - installation of the big Taurus inside a 7,200-ft.2
turbine hall - then was completed within about half a
year, and the new system was fully commissioned in early February
2003. The total cost, including all fittings and a grid connection,
was $16.2 million.
Performance:
Real Time, Real Good
 |
| CHP plant under construction: lowering the turbine into
the turbine hall |
Running 24/7 (except for two weeks yearly of maintenance
downtime) the turbine burns about 50,000 therms of natural
gas monthly. Although rated for 7.3 MW, the output actually
comes to around 7 MW, due to combustion inefficiencies at
higher elevations. Fuel consumption and power output also
are turned down slightly in the lowest-load winter periods,
in order to maximize efficiency.
After
yielding up its electricity, the turbine's hot exhaust
is captured in a heat-recovery generator to supply heat for
roughly a third of the base's central heating plant;
this consists of three International boilers outputting 40
million Btu/hr. apiece. The Taurus actually was sized "in
order to supply heat for one of those boilers," says
Morrissett, since boiler load is a prime scaling factor in
many cogen projects. "Whatever amount of [exhaust] heat
you can use, and not waste your gas producing it," he
says, will tend to determine the appropriate turbine. During
high desert winters, which are sometimes mild and short, two
boilers typically might be running, but in summertime, their
gas valves are closed because the base's hot-water needs
can be supplied largely by the Taurus' exhaust - to
the tune of 30–35 MBtu/hr. - as planned.
This hot-water
output then is pumped through about 40 or 50 mi. of piping,
at up to 2,400 gal./min., to supply 80% of Marine-base buildings
"with very-high-temperature hot water for domestic use,
some steam applications, and building heating," notes
Morrissett.
All of the
boilers and the Taurus genset can be fired with either natural
gas or diesel as a backup.
In sum, the
system easily is attaining its originally targeted efficiencies
and ensuring greater energy security. "We're very
happy with the cogen unit," Morrissett says. For 2003,
it reduced the wattage formerly being purchased from SCE by
two-thirds. Natural-gas purchases shot up from the preinstallation
rate of 150,000 therms to more than 500,000 and will remain
high indefinitely. If this setup were running in certain private-sector
locales, this huge surge in projected consumption might have
been a deal-killer due to volatile natural-gas prices, but
the feds can buy anything they need in bulk through aggressive
purchasing: The fuel-cost impact isn't quite so critical.
Even with
higher-priced natural gas, and with the cost of system maintenance
added, the first-year savings will come to an estimated $5.8
million - which again is being divvied up by the Marines
and JCI.
To ensure that
these enormous savings keep rolling in, an elaborate monitoring
and verification system integrates and logs the natural-gas
input and electrical output meters, together with 10 other
critical variables. Operators can access all of this data
in real time via a fiber-optic communication cabling, which
connects the plant with monitoring and control at a nearby
substation where the power enters the base.
Spending All
That Money
 |
| View of turbine hall with black-start
generator outside building. The CHP system is on-line. |
The entire $16.2 million total outlay easily could be paid
off at the present "income" rate in less than four years,
but instead of doing so, Morrissett and other base managers
decided at the outset to begin plowing their share of the
dollars into buying more energy upgrades and assorted other
related goodies, such as several hundred four-by-four daylighting
and skylighting panels so far. Tops on the Marine Corps' wish
list of fully funded major investments were the following:
A Photovoltaic
Array
PV was a natural choice for a desert
facility; the Mojave enjoys 320-plus sunny days a year, and
what better way to offset the peak-rate charges from SCE?
Too, both DOE and DOD want to see government facilities converting
to more renewable energy sources and in fact are hoping to
achieve a shift of 10% or so by the decade's end. "This
is not an order but a recommendation," Morrissett points
out. Also enticing the Marines were generous incentive
funds - amounting to $0.045/W of PV power production - offered
by the California Public Utilities Commission. This, combined
with the preapproved funding the Marines were getting through
the ESPC savings, made the PV investment a no-brainer. Managers
at Twentynine Palms opted to build "the largest system
we could" with these funds, he recalls. Two firms, BP
Solar and Powerlight, were selected as contractors; groundbreaking
occurred in January 2003, and the system was operational by
September. The resulting array includes 8,706 solar panels,
each capable of yielding 150 W, or 1.2 MW total. The system
uses single-axis tracking, which feeds into five inverters
and then into five transformers and into a main line that
carries it into the cogen plant.
Overall, Morrissett
says, the PV is performing "fairly well," although
"there are times when one of the 15 separate tracking
systems misaligns. But this is an easy fix." Due to
assorted limiting factors, the actual PV yield has averaged
around 900 kW. During its first summer, this amounted to about
5% of Twentynine Palms' total electric needs, with the
Taurus contributing nearly half and the SCE grid contributing
all of the rest.
Thermally
Activated Absorption Chillers
This wasn't
part
of the original cogen blueprint in 2001, but the idea of installing
big, high-performance air conditioners (AC) sprang to mind
very quickly when Morrissett was eyeing the base's rather
shaky 15-year-old chillers and wondering how to spend the
Marine Corps' share of the ESPC dollars. Moreover, he
adds, "Once we got the cogen in place and saw exactly
what the loads were going to be, we knew that we wanted to
go to a central chilling plant - so we ended up incorporating
the absorbers in there." New chillers, running full-blast
in the summertime, also could utilize much of the turbine
exhaust and thereby achieve even higher efficiencies.
In the summer of 2003, the turbine exhaust began powering
one 200-ton absorption chiller for turbine inlet air cooling
(which makes it run more efficiently), in addition to providing
all of the base's piped hot water. Ambitious plans are already
well underway for much more chilling. As of the winter of
2003-2004, one big new chiller plant was nearly finished;
construction of two more to house multiple high-efficiency
Trane R123 chillers was also on the near-term horizon. When
upgrades to the four centralized plants are finished in mid-2004,
they'll be capable of yielding a combined 2,600 tons of cooling.
A chilled-water loop will circulate to output to around 40
or so buildings on the base, thereby replacing 80% or more
of the aging package units.
Chilled-water
lines also are being laid out with an eye to servicing future
base structures so when the latter eventually are built, Morrissett
says, "we're just going to be tying into those
lines so we won't have all of the complex mechanical
AC systems going in, with those buildings," thus saving
even more on up-front and operational costs.
Yet another
application comes from this trigen coolant: A small chilled-water
loop now is icing down the refrigeration condensers in the
newest mess halls. Using water-cooled condenser coils "hasn't
been done before to my knowledge," he believes, but
at least in concept, it should afford the coils higher cooling
efficiency and longer life. Come winter, when the main chilled
loop is shut down, this small spur into the chow halls will
continue to circulate under its own pump; the main chilled-water
lines then will act like a heat sink, he adds. Thus far, this
innovative system "seems to be working out fairly well."
Grid Interface
Challenges
To be or not
to be grid-connected? And if so, how?
Both of these
are thorny questions for cogen designers, particularly when
turbines produce surplus power that ostensibly could be sold
back to the power company to yield the owner a bit of income
through net metering. In the summertime, this would be irrelevant
at Twentynine Palms because the base needs all of its own
power, but during winter, the facility has an onsite capacity
for generating around 8 MW all told (i.e., combining the genset
and PV systems); the electrical load needed hovers between
6 and 9 MW. California has a net metering threshold of 1 MW.
This means that, at least in theory, the Marines might be
able to eke forth some occasional small excess of its self-made
power to put back into the SCE grid. JCI engineers actually
weighed this option in their design and finance calculations.
Ultimately, though, it was decided that the potential income
wouldn't be enough to offset the additional expenses
and headaches of coping with the issues necessitated by net
metering. "We would have liked
to export power," Morrissett recalls, "but because
of the interconnection agreement and what Edison's concerns
were at the time, I think it was decided that we should not."
Interconnections, he adds wryly,
"are interesting.'" Any utility, SCE included, requires that
rigorous technical controls be applied to would-be grid connectors
"whether you are going to export power or not," he says. This
rigor is ostensibly required to ensure that a customer doesn't
export power inadvertently. As for the Twentynine Palms grid
connection, "even without net metering, our agreement was
a challenge to get through." Negotiations with SCE were handled
by government contract managers from the Marines' Southwestern
Division. This entailed a complex four-way tussle among the
Division, Twentynine Palms' managers, JCI, and the utility
company. Under the resulting agreement, the base was required
to receive a small amount of energy coming in at all times,
he continues, "and just because of the load swings on the
base, we set that at about 800 kilowatts." An added - albeit
minor - complication was Twentynine Palms' combined cogen
and PV output. "We were forward thinking on this," says Morrissett,
"and while the cogen system was under construction, we went
ahead and put in an extra breaker for the PV system we knew
we were going to build. The PV system actually ties into the
breakers at the cogen plant." Thus, "all of the controls in
the cogen plant actually control the PV system as well."
SCE's
grid enters the base from a 34.5-kV main and a 12.47-kV secondary
feed, serving one section of buildings. The cogen and PV feed
into the latter via four main breakers. This separation of
the two subsystems is what basically prevents the cogen power
from leaking back into the grid. "There are times,"
says Morrissett, "when we're actually overgenerating
to those four main breakers and putting out power to the rest
of the base" (i.e., to areas served by the main power
line; however, a monitoring station prevents any current from
flowing back outside the base).
"It is
a very complex system," he decides. Several computerized
control panels link the elements with lots of wiring to make
it run automatically. The combination of two incoming grid
lines, a very big genset, and a field full of PV cells, all
powering multiple heat and cooling applications, "just
makes it quite complicated," he says.
Morrissett
has nothing but praise for JCI for designing it and making
all of the parts work (so far) almost flawlessly. Long-term
maintenance by JCI is part of the deal; recently the contractor
agreed to assign three full-time maintenance techs to Twentynine
Palms to make sure the components keep running smoothly. Says
Morrissett, "We're very happy with Johnson Controls."
Complicated
though it is, this particular installation is also, so far,
a resounding technical and financial success. It dramatically
illustrates how cogen power can not only pay for itself readily
but, with the sometimes-considerable savings that result in
larger projects, also underwrite additional energy measures - thereby
leveraging the initial cogen investment even more.
Regarding their
initial goal of increased energy security, the Marines have
the situation well in hand, with some 8 MW of dual-fueled
genset and solar onsite power.
As cogen demonstration
projects go, Twentynine Palms ranks as one of the largest
and most efficient examples of CCHP cogeneration and thermally
activated systems anywhere, particularly in the public sector.
DOE's Federal Energy Management Program wants to accomplish
similar savings at facilities worldwide and points to Twentynine
Palms as a showcase project. It also underscores the importance
of fully incorporating thermally activated system opportunities
as well as heat-energy recycling in the cost-benefit analysis.
Morrissett concludes, "We're very happy with the
project."
La Mesa, CAbased writer DAVID ENGLE
specializes in construction-related topics.
DE - May/June 2004
|