|
Although emergency power systems typically
are thought of as crucial for public health and safety, for
casinos in Las Vegas, NV, keeping power running nonstop to
slot machines and other gaming operations is considered just
as critical.
Everyone agrees that the lights should never go out in Las
Vegas - and not only the lights but also the slot machines,
the surveillance cameras above the blackjack tables, and the
Keno board in the 24-hour restaurant. This is why such new-generation
casinos as the Bellagio and the Venetian have installed massive
emergency power plants that are on a par with what typically
is found in data management and telecommunications centers.
"All the lights, all the slots, all the air conditioning - if
they lose the electricity, they're dead in the water,"
says Keith Lozeau, sales manager at Cashman Power Solutions
in Las Vegas, which provides the generators for 80% of emergency
power systems on the Las Vegas Strip. "And that's
not counting lost revenue." This is why the 7 million-ft.2
Venetian complex-casino - comprising 3,000 luxury hotel
suites, high-end retail shops, the Sands Expo Convention Center,
and a network of canals that mimic the real thing in the city
the hotel was named for - has installed five 2,000-kW
Caterpillar 3516B diesel generators (2,934 hp). The gensets
are controlled as part of an elaborate electrical power distribution
and management system designed by Electrical Systems Consultants
(ESC) in Fort Collins, CO, in partnership with General Electric
(GE) Industrial Systems, that utilizes GE's state-of-the
art power management control system (PMCS), ESC custom-designed
software, and InTouch human-machine interface software from
Wonderware FactorySuite. The standby operation is part of
the Venetian's facilities infrastructure that among
other functions allows the complex to manage 15,500 tons of
chilled-water capacity, 125,000 lb. of steam and 6.8 million
gal./hr. of hot water for heating, and more than 360,000 gal./hr.
for guestroom showers and sinks (all powered with electricity
off the grid), the result of the management's decision
to operate as a power distributor rather than a retail power
consumer.
 |
At the heart of the Venetian's energy management system are
two transformers that step down the 138,000 V of electricity
the complex receives from Nevada Power to 25,000 V for internal
distribution through 41 substations. The cost of the electricity
is less because the utility bills the Venetian at a transmission
rather than a distribution rate. Each of the main transformers
has a bank of feeder breakers, with one feeder breaker from
each unit feeding a substation, which in turn is equipped
with a tie breaker. "This means," says Michael Helbert, assistant
chief engineer in the Venetian's facilities division, "that
we have what we call 'double-ended substations,' with a feed
off the number-one transformer and a feed off the number-two
transformer to the same substation and an open tie breaker
in the normal position. If we were to lose one of the transformers
or part of the loop out there, it would automatically throw
open the breaker at the substation and pick up the load. On
eight of the double-ended substations, one side is for standby
power."
Keeping Things
Running "No Matter What"
"There is the philosophy that it is the interest of
the economy in Las Vegas to keep things running no matter
what happens," says Ken Miller, assistant fire protection
engineer for the Las Vegas city fire department. "Among
the gaming industry, as well as the fire and building departments
and city management, the thought is 'the better the
backup and redundancy, the better things will be all around.'"
"If we lose power for a minute or two, people are out of
the building," says Helbert. But Richard Pidruzny, energy
facility manager for San Diego, CA - based Sempra Energy Solutions,
which owns and operates the Venetian's backup power plant
along with its massive cooling, steam, and hot-water operations,
disagrees that the emergency power system at this huge complex,
or in Las Vegas generally, represents an unusual amount of
backup capacity. "Nobody can foresee how long a blackout is
going to last," says Pidruzny. "And although rarely will one
go more than a couple of hours, we're set for four days, which
is more than anybody ever needs."
Both Clark County and Las Vegas City codes are specific about
fire and life safety functions that must be up and running
within 10 and then 60 seconds of any power loss. "The code
doesn't specify how much power a facility has to have," says
Miller. "What it does is outline the type of life and safety
equipment that's required to be on emergency power. It's up
to the electrical engineer or the design team in conjunction
with the owner to appropriately size the minimum-sized generator
to meet those requirements. The idea of the code is to buy
enough time to get the occupants safely out of the building.
But the owner may decide he wants his entire building and
all of its operations to remain fully functional in the event
of a blackout. Some properties, for example, are using only
one-third of their installed generator capacity for emergency
services. This means if there's a power outage, there's enough
standby capacity that the guy playing craps wouldn't even
know that something happened."
Although the International Building Code and the National
Electric Code were developed for high-rise buildings, in Las
Vegas these requirements are applied to the entire hotel-casino
complex. "As large as some of these complexes are, the fire
department has put its foot down and required the same level
of life safety throughout," says Miller. Clark County, which
has actual jurisdiction over the Strip where the large hotels,
casinos, shopping malls, convention centers are located, enforces
the same requirement unless there is a four-hour fire separation
between the high rise and the rest of the complex.
According to Lozeau, the requirement that select fire and
life safety systems must be back on-line in 10 seconds was
a major factor in the Venetian's decision to use the
five Cat 2,000-kW gensets, which at the time the choice was
made were the largest machines that would meet the 10-second
start requirement. "The other reason for the multiple
machines, a kind of happy byproduct if you will," says
Lozeau, "is the fact that you now have redundancy in
the system. If one machine fails, you can selectively shed
load and still keep the essential functions up and running.
After fire, life, and safety, the usual priorities are the
casino loads - slot machines first and then mechanical
loads, such as chillers, et cetera."
Fire!
"The way I think of the fire and life safety equipment
required to be powered within the 10-second window is that
you have to know there's something going on, so you
have to hear it, which means basically horns and strobes,"
says Douglas H. Evans, fire protection engineer for the Clark
County building division. "And you have to be able to
get out of the building, which means you have to be able to
see where you're going. This means power for exit signs
and exit illumination and lighting circuits for elevator cabs
and stairs, plus water control switches and the fire command
center and your communication systems and lighting for the
fire pump room and at the emergency generator. What has to
be up in 60 seconds is the high-power-demand items. Elevators
have to recall, and they have to be switchable so the fire
department can use them for emergency purposes. Also, your
fire pumps and smoke control fans and hence your fire pump
controller and status panels have to be up in 60 seconds."
Helbert estimates that at the Venetian the draw for the entire
fire and life safety requirements is 3.4 MW, which could be
fed with two generators. "With our motor-operated circuit
breakers, we can prioritize our load shedding, and most of
the equipment is programmed so if one of the generators dropped
out, the circuit's load would be shunted automatically.
The breakers will open in sequential order right down the
line."
"The operation of the generators is pretty much hands-off,"
says Kevin Hartig, ESC's project manager. "The
initial startup is done by protective relaying. From that
point on, the PMCS takes over. Let's say we lose power,
one generator comes up, and as soon as that one generator
is up to speed and its load breakers close down on the gen
bus, by relaying we close a tie breaker on a substation that
feeds all the emergency substations. We have programmable
logic controllers [PLCs] in every substation throughout the
facility, and these locally control each substation. So the
automatic throw-over scheme when they lose power is done by
a local PLC that we programmed in each substation. That way
if it loses communication with the system, it still has a
certain set of tasks that it's responsible to perform.
Instead of one big brain making decisions, the control is
distributed.
"There is a specific PLC that resides in the facility
where the generators are located and acts as a director for
the PLCs that are in the standby substations. These are the
only PLCs that do any kind of control during standby power.
So let's say you have 20 substations and only eight
are standby subs; only those eight are going to be doing anything
during emergency power operations. The eight are responsible
for all the staging and breakers; they do all the load-shedding
and load-adding operations in concert with whatever the paralleling
gear is doing. The one that's acting as the director
brings the data in and massages it for the parallel gear and
does certain calculations to figure in the reserve factors
and that sort of thing. And then that data is made available
to the other standby PLCs. If you lose a genset, then certain
priorities are lost and the associated or corresponding feeder
breakers are tripped and then reset. If another generator
is added, we close those loads back in.
"In a facility this size, it can literally take 15
to 30 minutes to get to a substation. With the Venetian's
PMCS, I can be on-line in 10 seconds, and if we're on
normal power, I can tell exactly what we're drawing.
I can tell if there's a fault somewhere. If we're
on generator power, I know exactly how many generators are
running and which emergency loads have closed. I can go in
and change a priority on another one."
Everything Up
and Running
"When the county fire department does a high-rise facility
on one of our major properties," says Joe Noble, Clark
County deputy fire marshal, "we get what's called
a Fire Protection Report, which we review in conjunction with
the county building department. One of the specific sections
in that document identifies what life safety devices or fire-protection
equipment is installed within the facility and therefore what
requires emergency power. So when the electrical engineer
goes through to perform his calculations, all of that emergency
equipment is identified, and he simply searches out the required
voltages. Then he works with the owner to provide a generator
that's sized adequately to power whatever else the hotel
property wants powered."
 |
"At the Venetian," says Helbert, "after fire and life safety,
surveillance is first and foremost in coming back up. Actually
it's covered with battery-powered UPS units so the gaming
lights and the surveillance systems, along with the fire alarm
system, never go down. Expensewise, however, you can only
afford to do that for so long, so you rely on your generators
to come up and pick up the load for you."
Helbert agrees that the key element in the Venetian operation
is the GE PMCS, which makes it possible to remotely complete
such functions as turning breakers on and off. "The
PMCS has battery backup so it never goes down," says
Helbert. The system's centrally located management and
control consoles utilize InTouch human-machine interface software,
which provides the Venetian's system managers with a
graphic representation of any substation, power line, breaker,
or panel and mimics the real control panels in the power systems
exactly as if the staff were on the actual plant floor.
The Venetian is about to break ground on another 3,000-ft.
tower, and Helbert says he's set to make recommendations
about priorities for discretionary standby startup for this
next go-around. "The pump skids for the towers, for
example, don't necessarily have to be on standby - it's
not life critical, but you don't want toilets backing
up. So if we don't put the pumps on standby, let's
at least make sure they're on the other end of the standby
substation so we can throw the tie and backfeed if we have
the capacity left. Same with the 24-hour restaurant. When
we were testing this backup system, we were considering knocking
them out. While we may not want the restaurant on standby,
we'd like the ability to backfeed them."
"We don't care how many generators are on,"
says Hartig. "We just look at what available kilowatts
are left over and stage load accordingly. Take chillers. Let's
say we have all five generators running and we've got
10 megawatts and we're only using 4. Even though the
chillers are not essential, let's go ahead and get one
of those back on-line. We can send a signal over to the building
management system that would allow this or that chiller to
automatically come on. It's not essential, but if you've
got the power, let's go ahead and make use of it. The
system operators can analyze the historical data that we log
into the PMCS to determine where they can make priority changes
to make better use of generator capacity." Hartig projects
that the Venetian will add two more gensets when the 3,000
rooms come on-line, for another 4 or 5 MW.
Genset Modifications
Lozeau reports that the five gensets that make up the Venetian's
backup power plant are equipped with oversized batteries and
multiple starters. Extra large radiators were included to
accommodate the high ambient temperatures in the desert (115-120°F
in the summer), and engine heaters were added to heat the
coolant and keep the engines at 100°F or greater, which
he says "is a really crucial link in the ability to come on-line
in 10 seconds." At the Venetian, the generators take up 20,000
ft.2 of space in a room with an 18-ft.-high ceiling.
The switch gear is from Automatic Switch Company.
"In Las Vegas, you need about twice as much ventilation
as is typical," says Lozeau. "And even with this,
you'd be surprised where people put generators. They
don't consider that this equipment needs air and that
if they overheat, they'll shut down. This happened in
one of our older properties that expanded and built a wall
in front of the generator. Management never tested the generator
under 100% load, and when they did have an outage, the air
from the generator hit the wall and recirculated back and
shut the unit down. A woman who claimed she fell down the
stairs in the dark sued and won a multimillion-dollar settlement."
 |
The Venetian gensets also are equipped with silencers - "although
nothing exotic" because the location of the plant is in a
self-contained building attached to the Sands Expo where noise
is not a significant issue. The Venetian's generators came
equipped with Caterpillar's electronic fuel system, which
among other functions automates fuel-air mixture because,
as Lozeau points out, standby units have a tendency to overfuel,
especially on startup. Ten thousand gallons of fuel (the four
days' supply) is stored in an underground tank and fed to
the individual generators, each of which has its own individual
fuel tank, housing enough fuel to run the genset for the two
hours required by code. According to both fire departments,
there are no limits to what can be stored in an underground
tank as long as the requirements of the building and fire
codes are met. Aboveground storage has to have two-hour fire-exposure
protection.
Quarterly maintenance includes checking batteries, belts
and hoses, and fluid levels; testing engine safety; and particularly
checking controls, which Lozeau points out often can go wrong
in machines used in standby operations. "People sometimes
take maintenance for granted because the machines don't
run that much. But maintenance materials deteriorate even
when the machines aren't running." Annual maintenance
includes oil and filter change. The generators are subject
to a weekly startup and a monthly test with load.
With all of the extra power, it would seem logical that the
backup systems would be used to peak shave, especially during
summer. Helbert reports that Nevada Power has contacted the
casinos about going on generator power during high demand
but so far has not called upon them to do so. One difficulty
is air-quality regulations. Except for a power outage, the
facilities are only permitted to operate in test mode, and
casinos located along the Strip "corridor" cannot
exceed 50 tpy of overall emissions.
And that five-generator blackout everyone's planning
for? So far it hasn't happened. "I've seen
hospitals," says one generator serviceman who works
the Las Vegas Strip, "that weren't as tense about
being in the dark."
Journalist PENELOPE GRENOBLE O'MALLEY is
a frequent contributor to environmental publications.
DE - May/June 2004
|