|
HOD Landfill is located within the eastern boundary of the
Village of Antioch in northeastern Illinois. The closed 51-acre
municipal and industrial solid waste disposal facility was
active from 1963 to 1984. During that time, the landfill accepted
approximately 2 million tons of municipal waste.
On September 28, 1998, the Environmental Protection Agency
(EPA) issued a Record of Decision (ROD) for the site, with
concurrence from the Illinois EPA, which required that specific
landfill closure activities be performed. The final Remedial
Design (RD), including a landfill gas (LFG) and leachate management
system and final cover, was approved by EPA on August 9, 2000.
The final RD included 35 dual gas extraction wells located
to allow for athletic fields as an end-use option. Construction
activities for the RD were essentially completed in April
2001. At that time, the LFG and leachate collection systems
began operating.
Initial operation of the gas management system indicated
that approximately 300 cubic feet per minute (cfm) of LFG
were available for potential use as an energy source. Local
businesses and industries were identified as potential users
of this LFG. Ultimately, Antioch Community High School (ACHS)
was identified as the only user able to use the energy from
300 cfm of LFG.
In 2001, RMT Inc. contacted ACHS to inquire about its interest
in using LFG as an energy source.
In April 2002, the Antioch Community School District applied
for and received a $550,000 grant from the Illinois Department
of Commerce and Community Affairs' (DECCA) Renewable Energy
Resources Program (RERP) to construct a cogeneration system
to use the LFG to produce electricity and heat at the high
school.
During the fall of 2002, ACHS and RMT began to explore options
for using the LFG being collected and flared at HOD Landfill
approximately half a mile from the school. Potential options
evaluated included using the LFG to produce electricity for
use in the school's existing boilers and for use in a combined
heat and power system. Through these evaluations, it was determined
that the only economically viable option was to produce electricity
and heat for the school.
The overall cost of this project, including design, permits,
and construction, was approximately $1.9 million.
On December 24, 2002, construction of the system began.
The design and construction of the energy system posed a
number of challenges, including resolving local easement issues,
meeting local utility requirements, cleaning the LFG, connecting
to the existing school heating system, crossing under a railroad,
and meeting EPA's operational requirements to control LFG
migration. The design of the energy system also included tying
into the existing gas collection system at the landfill, installing
a gas conditioning and compression system, and transferring
the gas to the school grounds for combustion in the microturbines
to generate electricity and heat for the school. A half-mile
of piping was installed to transfer approximately 200 cfm
of cleaned and compressed LFG to the school grounds, where
12 Capstone MicroTurbines are located in a separate building.
The 12 Capstone MicroTurbines produce 360 kilowatts of
electricity and, together with the recovered heat, meet the
majority of the energy requirements for the 262,000square
foot school. The system began operating in September 2003.
| |
 |
 |
|
A schematic layout of the LFG-to-energy system is shown in
Figure 1.
RMT staff worked with the local government, school officials,
and EPA, in addition to leading the design efforts and managing
the construction activities throughout the project. RMT also
provided public relations assistance to ACHS by attending
Antioch Village Board meetings to describe the project, to
answer any questions from concerned citizens and Village Board
members, and to resolve any conflicts that arose during the
project.
RMT was the designer and general contractor on the project.
Specifically, RMT's team was responsible for
- designing the system;
- administering contracts, including coordinating access
rights, railroad access, and obtaining all appropriate permits;
- creating a health and safety plan;
- managing construction; and
- coordinating utility connections.
Project Design
This is the first LFG project in the United States to be
owned by and to directly provide heat and power to a school.
The challenges surrounding the design of this system are
discussed below.
HOD Landfill Gas Collection System
Tie-in
The collection system at HOD Landfill, which includes 35 LFG
extraction wells, a blower, and a flare, must remain operational
to control LFG migration. Therefore, the construction of the
new cogeneration system required connection to the existing
system to allow excess LFG to be combusted in the flare. Additional
pipes and control valves were included in the system to route
the gas to the conditioning and compression building and to
allow the existing blower and flare to remain operational,
while providing the correct volume of LFG to the microturbines.
Gas Cleaning and Compression
The gas that is collected from the landfill is conditioned
through a series of chillers that drop the gas temperature
to 10°F to remove moisture and siloxane compounds. A schematic
diagram indicating the LFG compression and conditioning system
is shown in Figure 2. An activated carbon unit is also
included to remove additional impurities. The LFG is compressed
to 95 pounds per square inch to meet the input fuel requirements
of the Capstone MicroTurbines. The gas cleaning and conditioning
system is located at HOD Landfill in a building adjacent to
the blower and flare.
Gas Piping to the Microturbines
Located at the School
High-density polyethylene (HDPE SDR 9) pipe 4 inches
in diameter and 0.5 mile long was installed 4 to 12 feet
below ground, running from HOD Landfill to the microturbines
at the school. The use of horizontal drilling techniques allowed
the pipe to cross beneath a stream, a road, public utilities,
athletic fields, and a railroad, with minimal disturbance
of the ground surface. This was extremely important for the
community and the school's athletic programs.
Electric Generation
 |
Each Capstone MicroTurbine fueled by the LFG produces up
to 30 kilowatts of three-phase electricity at 480 volts, using
12 to 16 cfm of LFG for a total of 360 kilowatts of electricity‹enough
to power the equivalent of approximately 120 homes. The microturbine
system incorporates a combustor, a turbine, and a generator.
The rotating components are mounted on a single shaft supported
by air bearings that rotate at up to 96,000 revolutions
per minute. The generator is cooled by airflow into the gas
turbine. Built-in relay protection (over/under voltage and
over/under frequency) automatically trips off the microturbines
in the event of a utility system outage or a power-quality
disturbance. Excess electricity not used by ACHS is sold to
Commonwealth Edison. A 12-turbine system was selected to provide
a system that will remain functional as LFG production from
HOD Landfill decreases. Based on the initial LFG collection
rates, up to 18 turbines could have been installed. The final
payback for this project, based on conservative assumptions
for future energy costs, is approximately eight years.
Heat Generation
Each Capstone MicroTurbine produces exhaust energy of around
290,000 Btu/hr at 550°F. The exhaust from the microturbines
is routed through heat exchangers that heat the liquid, which
then circulates through underground insulated steel pipes
running beneath a parking lot to the school's boiler system.
Because heat is being transferred to the school through insulated
4-inch-diameter pipes, locating the turbines next to the school
was critical in preventing excess heat loss. When waste heat
recovery is not required by ACHS, the microturbine exhaust
is automatically diverted around the exchanger, allowing for
continued electrical output. During extremely cold weather,
the school boiler system automatically uses natural gas to
supplement the heat output of the microturbines.
Project Experience
This project serves as a model of how a landfill with relatively
small quantities of LFG can be used to produce clean, efficient
energy. By using the electricity and heat created during power
production, ßmicroturbines become more practical for
LFG utilization. The main advantages of microturbine technology
over other more traditional internal-combustion engines are
the clean, quiet operation and the ability to add and remove
microturbines as gas flow increases or decreases.
The project's design and construction can be a model for
other communities interested in the beneficial reuse of nearby
LFG resources. It is an example of how to deal with the numerous
community concerns related to developing an alternative energy
system based on LFG. Determining suitable equipment for system
design, construction, and operation, while considering local
community needs and requirements, is critical to a successful
project.
This project is a prime example of how innovative partnerships
and programs can take a liability and turn it into a benefit.
The solution has created a win-win situation for all involved,
including HOD Landfill, ACHS, the Village of Antioch, the
State of Illinois, Commonwealth Edison, and EPA. Each key
player is seeing significant benefits of the energy system:
- Low energy costs for the high school
- Use of waste heat for internal use in the high school
- Clean, complete combustion of waste gas
- Decreased emissions to the environment through reduced
need for traditional electrical generation sources
- Reduction in greenhouse gas emissions
- Public relations opportunities for ACHS and the community
as the first school district in the United States to get
electricity and heat from LFG
- Educational opportunities in physics, chemistry, economics,
and environmental management for ACHS students as a result
of this on-campus, state-of-the-art gas-to-energy system
MARK TORRESANI and BEN PEOTTER are
members of the Solid Waste Engineering Division of RMT Inc.
in Madison, WI.
DE - July/August 2004
|