|
When Progress Energy began construction of its new, 19-story
corporate headquarters in downtown Raleigh, NC, there was
concern that a massive grid failure could leave its 1,100
employees needed to restore the power system literally in
the dark. This concern prompted incorporation of a 2,800-kilowatt
generator capable of fully operating the entire building's
systems into the facility, allowing the power company to quickly
restore power to its customers.
Progress Energy (NYSE: PGN) is a Fortune 250 diversified
energy company with more than 24,000 megawatts of generation
capacity and $9 billion in annual revenue. The company provides
retail electric service through two subsidiaries. Progress
Energy Carolinas provides electrical service to a 34,000-square
mile area that includes the eastern half of North Carolina,
the northeastern quadrant of South Carolina, and the Asheville
area in western North Carolina. It provides service to 1.3
million customers and a population of more than 4 million
people. The company's other retail subsidiary, Progress Energy
Florida, spans about 20,000 square miles in central Florida,
including metropolitan St. Petersburg, Clearwater, and the
greater Orlando area, and provides electrical service to 1.5
million customers and a population of more than 5 million
people.
Like many corporate operations, critical engineering and management
functions are housed in the corporate headquarters, located
in Raleigh. With data management functions interlinked between
the various operating groups, an electrical failure could
result in a serious challenge for the company to communicate
and to restore power to its own service areas. With these
concerns in mind, Progress Energy elected to design a full
backup generation system into the new 386,000square foot
building that would be capable of providing enough energy
to fully operate all of the building's systems, from HVAC
to computer operations.
 |
According to Franz Lang, Progress Energy's facility property
engineer, the new building has both a life-safety generator
and the standby generator. "The 2,800[-kilowatt generator]
is the facility for the building, and the 750[-kilowatt generator]
is the emergency generator. The sequence of operation is that
the 750 starts first when we have a power loss. Once that's
up and running, the second one will get up to speed, make
its transfer over on the main switchgear. The emergency [generator]
will see normal utility power, even though it is energized
by the standby generator. Then [the emergency generator] goes
through a timing mode and drops out and the whole building,
including the emergency circuit, is taken over with the standby.
To meet the requirements by the state and building codes,
you have to have an emergency generator first come on-line
because it comes on quicker."
Typically the emergency generator must kick in within 10 seconds
after loss of power in order to energize emergency lighting
and elevator systems so that, if the building needed to be
evacuated, it could be done safely. With the standby generator,
the full system is expected to come back up within 30 seconds.
Unique to the design of this standby generator is the fact
that, at 2,800 kilowatts and 1,800 revolutions per minute,
it is the largest and most powerful engine generator set ever
built. The generator set is a Detroit Diesel/MTU 2800 DSE.
The Detroit Diesel/MTU 2,800-kilowatt diesel engine generator
set is powered by a DDC/MTU 20V4000 diesel engine with a unit-mounted
radiator. The 20V4000 is a single-block, twin turbo design
and operates at 1,800 revolutions per minute. This engine
has the capability of producing up to 4,036 horsepower with
a displacement of 5,480 cubic inches and a power-to-weight
ratio of 5.2 lb/hp. Covington Detroit Diesel, located in Greensboro,
NC, provided the system.
Responding
to the Need
Covington Detroit Diesel was familiar with the needs of Progress
Energy, due in part to a long relationship between the two
companies. "In their existing corporate facility, we've got
a 1,050-kilowatt Detroit Diesel package that was put in back
in 1977 that backs up the life safety for that existing corporate
facility," states Danny Smith, generator sales engineer for
Covington. "Last year, they decided they wanted to pick up
the remaining portion of their existing corporate facility,
so they called Covington in and we assisted the owner and
their engineers with a design for a turnkey 2-megawatt generator
system. We completed that project, and when it came out that
they were going to build a new corporate facility across the
street, they contacted Covington once again, mainly due to
our service capabilities."
 |
Identifying a generator system that would be capable of operating
the entire system in a single package was a challenge due
to the limited space at the new corporate facility. "To pick
up the entire building we would need something in excess of
2,500 kilowatts," Smith recalls. "We decided to go with our
2,800-kilowatt single-engine generator set. The reason they
[Progress Energy] went with a single engine rather than going
parallel was due to space. Being a downtown corporate facility,
as you can imagine, the real estate is very expensive so with
the room they had available in the building to put the generator
set in, it only made sense to go with a single unit."
In addition to the generator set, Covington provided the ASCO
Bulletin 950 Synchropower Generator Control Switch Gear, furnished
by Automated Switch Company (ASCO), that allows the generators
to pick up the power loading in the building. "We were furnishing
the switchgear as well," states Smith. "We can start the engine
up, parallel it to the utility, do a soft load transfer, and
walk the load over to the engine without the facility ever
seeing an outage. When we decide to go back to the utility,
we can walk the load back over to the utility and then open
the generator breaker so it does have paralleling switchgear
to operate the facility either on generator or utility."
While the standby generator is capable of operating the building
during a power outage, the challenge of bringing a building
smoothly back up to operational capacity was also addressed
especially in the air-handling and ventilation systems. "When
the supply fans and chillers see a drop in voltage, they automatically
shut themselves down," states Lang. "All the fans, pumps,
and chillers are on what is known as a soft start. That helps
the generator and also helps with your peak kilowatt demand.
The fans have variable-speed drives. Everything ramps back
up softly. It does not come up at full-load amps at all, so
that helps bring the building back up on-line."
Putting a Big Package in a Small Location
Installation of a standby generator that weighs 55,000 pounds
and is 25 feet long created a host of design and installation
problems. With the limited building space, there was not a
lot of additional real estate available for design placement,
and concerns regarding noise and fueling all had to play a
role.
 |
"Most jurisdictions have noise ordinances, and we had to
coordinate that," states Paul Carlson, senior associate with
B&A Consulting Engineers of Decatur, GA, the electrical
design engineers on the project. "We had to bring an acoustical
consultant actually onboard to provide a custom solution to
make sure that the sound level is within the requirements
of the local jurisdiction. Plus, as a large company, they
want to be a good neighbor. They don't want to go ahead and
start blasting people as they walk by on the street either.
It is inside of a room, with acoustical sound treatment on
the intake and discharge, and then we have a super-critical
muffler silencer on the exhaust to limit the exhaust noise
too."
The noise limits were of concern, especially since both generator
sets are exercised each week to ensure startup and operation.
"That's one reason for the sound attenuation as a good neighbor,"
says Carlson. "During normal exercising in the middle of the
day, you still don't want to be too much of a bother to any
neighbors around. But you want to be able to load it up, bring
the generator on and off for testing. You can test it with
the building load, which is the best thing to do for an engine
during its weekly testing, to burn the gunk out. Diesels get
unburned hydrocarbons in the stack if you don't get it up
to operating temperature for an extended time to go ahead
and clean everything out. The key is to get it to operating
temperature at a load that will get the engine exercised."
 |
Another challenge was the installation of fueling tanks to
operate the large generator. "It was an issue because the
building codes don't permit the fuel storage," states Carlson.
"If you do fuel storage, you have to put it inside of a four-hour
containment. But we're in a fire district, which local municipalities
can declare in terms of its high-hazard area, usually downtown
areas in which case they allow no fuel storage. They want
to have life-safety generators, so you have to store fuel
on-site, so it just means that the jurisdiction has a better
hand with which to negotiate with us. In our case, we ended
up with an underground fuel storage tank."
With more and more companies facing the challenge of competing
in the global market, the ability of their corporate operations
to operate on a 24/7 schedule becomes imperative. Installation
of generator systems capable of keeping operations functional
in the event of power outages or other disruptions will more
than likely become a trend in the future. "Companies today
cannot afford to be down," says Smith. "If they go down, a
lot of their other branches go down because of the data that
go through corporate, so it's not just that particular facility
that's going down. You may be taking down multiple other sites
if that particular facility goes down. In our case, we have
approximately 2,400 employees in the downtown corporate facilities,
but if you look at all of our facilities, you could be talking
big numbers as far as people not being able to continue to
work."
LYNN MERRILL is director of public services for
the City of San Bernardino, CA.
DE - July/August 2004
|