|
It's not your textbook model for launching a grid-wide distributed
generation (DG) strategy, but in the summer of 2002, Detroit
Edison "sort of stumbled into" onsite power, as engineer Richard
Seguin recalls. Sweltering days and muggy nights were keeping
air conditioners at full blast and stretching circuits beyond
capacity. Outages began hitting on consecutive days. Seguin
and his colleague in energy resource planning, Haukur "Hawk"
Asgeirsson, and other Edison engineers realized they needed
a major solution, quick. And so, in less than four days they
rigged and applied a transportable backup generator, complete
with hookups. At any sign of trouble, it could be dispatched
instantly to restore power or prevent a shutdown. All in all,
says Seguin, "It saved our bacon."
It also stimulated their thinking about DG's wider possibilities.
Now, two years on, DG has evolved from its role as a one-shot
"repair kit," into a permanent and indispensable specialty
tool. It gives Edison's engineers much greater flexibility
and improved grid reliability—all cost effectively.
Seguin and
Asgeirsson had heard about and entertained various DG applications
before, but, in weighing the possibilities, there were always
the overriding negatives: first, concerns about DG's impact
on grid security, and second, on the business side, the
potential loss of revenues if customers should opt to buy
their own systems.
Besides, these
distributed energy resources (DER) would have to be deployed
and perhaps serviced by old school "sticks-and-wires guys"
who, although adept at cable-splicing, know next to nothing
about generation.
Then there's maintenance: How often do generators need monitoring,
inspection, and care? How reliable are they? What's the downside
if that six-figure investment throws a bearing and locks up
at 3:00 a.m.óboth as a safety hazard and as a material loss?
On the plus
side, though, Edison's DER planners realized that having
a couple of quick megawatts at their disposal would come
in handy all over the place: "There's a lot of times we
have generator needs," says Seguin, "but we just don't know
when they're going to occur."
Power on Wheels
It wasn't a
big leap to realize that the first transportable generator,
originally slapped together in crisis, could also stay parked,
if need be, for longer-term assignments. For example, if
a substation needed a boost during extended peak hoursóand
this solved a problem one seasonówhy not leave the equipment
nearby for next year? In business terms, 1 to 3 megawatts
of "booster" power could allow the postponing of expensive
substation upgrades. Without the stopgap generator, Edison
might easily be compelled to meet any yearly overload of,
say, 50 or 100 hours on a circuit, first by broadcasting
public requests that people turn off appliances (not very
appealing, and it doesn't make utility planners look very
bright) or, eventually, by investing $1 million-plus in
new power lines, transformers, and substations. This works
out to huge sums per kilowatt-hour. The utility is forced
to build infrastructure that's used, initially, a tiny fraction
of the year.
By comparison, deploying generators might easily meet the
peak load "for a cost of $50,000 to install… and $32,000
in annual charges. That, "notes Seguin," is a big potential
savings." Better still, it will keep paying off for years,
until the nearby slowly growing baseload increases beyond
the generator's output. Substation upgrades eventually become
necessary, but if you can delay them three, five, or seven
years, so much the better.
Also, as most
utilities have discovered, people generally don't like new
stations in their backyards; often they complain rather
noisily to regulators and politicians. Besides which, notes
Seguin, "You can't pick up a substation and move it very
easily as the load migrates out to the suburbsóbut you can
move a generator on wheels to follow it very easily."
Transportation
and deployment is easily done with rented tractor-trailer
rigs. All the necessary hardware is securely mounted on
skids, including, as Asgeirsson explains, the transfer and
switchgear, protective equipment, and so on. The size of
a generator set for this mission is constrained only by
the hauling rig. "The biggest thing we could fit" on a 40-foot
trailer turns out to be 2 megawatts, notes Asgeirsson.
Once parked
at its application site, the sturdy container serves as
the generator's housing and sound baffle. Additional connection
and switching gear follows along in a second flatbed trailer,
but, Asgeirsson points out, crews are working on squeezing
everything into one box.
Refueling and servicing haven't turned out to be significant
chores either. The natural gas‚fired units (1-megawatt Deutz
Engine models) are served by the regular distribution pipes,
and the 2-megawatt Cummins diesels are equipped with 6,000-gallon
storage tanks. Late in the spring of 2004 another new Cummins
was being installed for the upcoming hot season; it will run
four to six hours a day for peak shaving, Asgeirsson notes,
and it's equipped with a 2,100-gallon onboard tank, sufficient
for about 18 hours of operation.
Growing Fleet,
Multiplying Roles
As of the spring
of 2004, Edison already had deployed nine generators in
this mobile fleet, seven of them fully portable and permanently
truck-mounted. Each boxed unit might remain at any given
location for as little as two days or as long as five years.
Permitting is
required, of course, as well as compliance with the state's
environmental and safety standards for such equipment, but
these rules are straightforward and not unduly restrictive.
How do residential
customers react to tractor-trailers rolling down their street
with hefty generators, and parking them for the summer?
Curiously enough,
although some complaints have been received, the overwhelming
reception has been fairly positive. The fact that the system
remains on a truck bed rather than on the ground is actually
somewhat appealing, because it reminds residents that the
installation is meant to be temporary. Local residentsóperhaps
remembering the brownouts of 2002óknow that extra power
is absolutely necessary for their year-round comfort. Also,
because the container is solidly built, the sound level
isn't onerous. In communities where Edison must secure permission
to park the setup on common property, the utility first
introduces the portable power concept, using a persuasive
eight-minute video that shows examples and explains the
necessity. Residentsógiven a choice between the relatively
unobtrusive truck, and the prospect of rolling brownoutsófind
that it's not a tough call.
Besides providing
emergency power and helping defer upgrades, still more uses
for portable sets have emerged. For example, whenever a
section of the grid needs to be turned off to allow service
on a distribution line, instead of putting people in the
dark for a few hours, a DG truck can be dispatched, and
distribution continues even while primary lines are deactivated.
Another example:
In 2004, construction on a cable conduit serving a heavily
loaded circuit was delayed due to problems obtaining rights
of way. The circuit would surely be outted under the air-conditioning
load, so Asgeirsson's department installed a generator "to
get us over this summer," he says. "By the time next summer
rolls around, we'll have additional circuits to take care
of all the growth that's going on." Meanwhile, the Cummins
can be picked up and re-deployed somewhere else.
The availability
of a mobile fleet has dramatically affected emergency-response
planning at Detroit Edison, allowing it "to sort of ëstandardize'
or even ëpre-plan' " all its emergency responses, Seguin
notes. Potential problems are anticipated by the usual means
of examining load curves and historical outages. This provides
an overall picture of "where emergency backup power may
be needed next, how much, and at what voltage," Seguin says.
"We know what we're going to do when the situation arisesóeven
if we don't know where."
Making the
Business Case
Discovering
more and more applications has meant that there's relatively
plenty of work for the generators to do. It's not likely
to sit idle during the peak season. Outright purchasing
of generators, rather than leasing, has turned out to be
advantageous because the Michigan rate-setting commission
tends to look more favorably on capital investments.
What happens
if big electric customers see the utility company buying
onsite power and decide they want to own some too? Edison
isn't really averse to this, because it's often a win-win
outcome. First, the customer wins by getting its peak shaving
and saving money this way. Second, Edison usually wins by
getting some deferral of its seven-figure expense for the
big substation upgrade. In any case the utility gets to
collect standby charges. Besides, as an alternative to having
a customer buy DG from a third party, another Edison sister
company may offer a deal on leasing an Edison-owned generator
for five to seven years. This ëPremium Power' plan guarantees
the customer standby power, while simultaneously helping
Edison manage the wear and tear on heavily loaded circuits.
If the customer still wishes to purchase a third-party generator
after all, a nice deal may be worked out with another one
of Edison's unregulated sister companies, DTE Technologies
(see sidebar), which markets DER nationwide.
Spreading
the Word
If mobile DG could blossom in the Motor City, it could probably
do so in lots of places. So, starting in 2003, Edison's DER
planners began helping other companies overcome the few basic
hurdles to DG, and to learn from Edison's innovations, by
inviting them attend a forum on DG implementation. This was
held in September in Detroit. About two-dozen people representing
17 utilities attended; the turnout was marred, however, by
an ill-timed hurricane on the Atlantic coast that forced attendees
to scramble back to work.
A second, greatly expanded conference followed in May 2004,
drawing 62 energy professionals. Presentations were given
by other recognized experts as well as Edison's, and covered
nearly two-dozen critical topics, such as DG's long-range
prospects; regulatory perspectives; distribution planning;
capital budgets for DG; project development, analysis, and
site selection; environmental factors; interconnection issues;
protective relay issues; DG for transmission and distribution
relief; and several case studies, including both utility-owned
and collaborative or customer-owned cases. Attendees toured
the region to see generators in operation and observe an innovative
wireless load-following, monitoring, and remote-control system
for DG, which is completely integrated with other automated
controls (see sidebar).
For those interested, conference
proceedings are available for purchase at nominal cost. Asgeirsson
is thinking about sponsoring a third conference in the spring
of 2005; for attendance information or other inquiries, contact
him at asgeirssonh@dteenergy.com.
Edison engineers
also have been busy presenting DG success strategies at
other industry conferences, and are currently gathering
their studies, findings, and reports into a book of best
practices.
Seguin points
out that many utilities probably fit the profile for adopting
DG, following Edison's model. In particular, those "whose
load is growing slowly, which are strapped for capital,
or constrained by reliability-based ratemaking could probably
benefit greatly from learning how, when, and why to implement
mobile generation. Asgeirsson adds: "One of the reasons
we put on this second conference already is because we feel
strongly that the utility industry has a large interest
in adding distributed generation on a grid system. It is
definitely one of the tools that we, as planning people,
can use to help on distribution."
It's Time
to Get Going
Now that the
nation's seventh-largest utility is urging others to get
onboard with DG, it's ironic to recall that, only two years
ago, Detroit Edison itself was more or less forced into
buying its first generator. Far more typically, a big utility
must plot each change with extreme caution. In this case,
however, Seguin proposes a radical departure. "Just go install
one," he says. "Go through the experience of installing
a generator, and do it."
Engineers and
crews will find that the learning curve and break-in experience
"isn't that bad," he avers.
As for discovering
specific application, don't worry about that either: There'll
be plenty. "Buy one the first time, and you will begin to
see the reward of having it available," he says.
An Edison official
who addressed the 2003 forum suggested that other utilities
"set up a DG working group," Asgeirsson recalls. "And not
just to handle the interconnection standards Ö but they should
actually be charged with the responsibility of looking for
applications." The key to launching DG "is to start encouraging
it within your own organization" in a proactive wayóand not
have it forced upon you by a public service commission, as
happened this year in New York.
What about technical assistance? Reliable technical advice,
persuasive business arguments, hand-holding, and other supportive
grid-connection resources can be obtained from the Electric
Power Research Institute (EPRI.com),
the Electricity Innovation Institute (E2I.org),
Gas Technology Institute (gastechnology.org),
the US Department of Energy's Office of Energy Efficiency
and Renewable Energy's Distributed Energy Program (eere.energy.gov/de/),
and two Detroit Edison divisions (see sidebar)ónot to mention
the rest of the DG industry, which, naturally, is eager to
see barriers fall and cooperation grow.
Seguin's advice
to DG providers who would prefer utilities as partners instead
of competitors, is, "first and foremost," don't complain
about long delays or standby charges; instead, try to appreciate
"what they need, why they need it, and approach it in a
partnership instead of from an adversarial standpoint."
A supplier who approaches customers as if seeking to "steal"
some utility business isn't exactly building bridges of
cooperation, and resulting DG projects will likely go nowhere
against a determined opposition.
A far better
strategy is to find out what the utility's needs and problems
are, which DG might solve, then look for specific project
proposals in that context. As noted already, one of DG's
most attractive selling points is its role in handling peak
loads, thus allowing the utility to defer major upgrades
until needed. DG will prove itself far more affordable and
flexible there. Another role is in power reliability. For
example, Seguin explains, "Where you're going to have a
stranded 30-MVA [megavolt-ampere] substation out there and
maybe you're better off putting in a 2-megawatt generator"
as a backup for it. One or two megawatts "may be the right
solution to get you out of sticky situations" and circumvent
an outage.
Nor is it really
all that difficult, he says, to find win-win-win scenarios
in which third-party customers get to save on current electric
bills and future rates; the utility wins by deferring the
underutilized upgrade and by keeping regulators at bay;
and a DG supplier gains a toehold on the grid, thanks to
a few success cases. Seguin thinks that, based simply on
this model, perhaps 1%‚3% of many utilities' power should
be coming from onsite generationówhich, though small, is
in fact "a huge market" compared to nothing. Approached
in this realistic range, a generator is no longer an invasive
threat but an important, if specialized, tool to fix local
problemsóanalogous to, say, certain digging equipment.
On a final note, Asgeirsson points out that DG must ultimately
make sense, above all, from the customers' financial standpoint,
because they're the ones paying the bills. "We're always looking
for the most economic way to serve our customer," he says.
And so, when it comes to designing circuits to handle a few
peak days' load, "this [DG] is a tool that allows us to manage
that peak well. That's been our approach. We believe in this
concept, and it's working for us economically. It's solving
utility problems. That's how we're doing it, and we are spreading
the word."
La Mesa, CA‚based writer David Engle specializes
in construction-related topics.
DE - September/October
2004
|