|
It's
not often that a municipality pays for something that it
hopes never to use. But Robert McGarrah and officials with
the City of Tallahassee, FL, found themselves in that exact
position last June.
McGarrah is thrilled that he never had
to pull the switch on the temporary power plant city officials
rented for four months last summer. And though the plant,
which operated from June through September, ran only for
brief periods of testing, McGarrah considers the cost to
rent it from Jacksonville, FLbased Alstom Power Rentals
(APR) money well spent.
"It is one of those things you hope you'll never need to
use," says McGarrah, manager of power production for the City
of Tallahassee. "We asked for the temporary power plant to
cover a contingency, to cover us in case of a power emergency
this summer. The hope, then, was that the plant never actually
had to run."
Tallahassee is just one of many municipalities whose officials
have turned to temporary power to help them through an energy
emergency. APR, for example, has been busier than ever supplying
temporary power plantsones that workers with the company
can set up in days, and take down just as quicklyto help
municipalities cover unforeseen outages, equipment malfunctions,
or maintenance projects. The company has supplied temporary
power in such far-flung locales as Sri Lanka, Indonesia, Mexico,
and Haiti.
The
power-rental industry, in fact, is steadily recovering from
the country's sluggish economy. A 2003 report by Frost &
SullivanNorth American Power Generation Rentals Marketssays
that the North American power-rental industry notched $405.9
million in revenue in 2002. The same report predicts that
the industry could reach $706.3 million in revenue in 2008.
This
is hardly a surprise. The rental industry gives utilities
reliable backup power without forcing these same utilities
to spend large amounts of money building their own backup
equipment. Temporary power plants, then, are an effective
solution for municipal officials looking for protection
during potential power emergencies.
And
that is exactly the situation in which McGarrah and his
fellow Tallahassee officials found themselves last summer.
The Problem
Officials in Tallahassee first realized that they might need
temporary power last February, when a powerful steam turbine
in the city's power grid failed. This was an emergency, but
it wasn't a disaster. The city, even with the failed turbine,
still had enough energy for its power needs. And because officials
expected repairs on the turbine to be completed before Junebefore
the increased summer energy demand that begins that monththey
worried little about any potential problems.
But
repair work moved slowly. And the city hit June without
the services of the failed turbine.
"We
could meet our system loads with all the other resources
we had as long as everything was running the way it was
supposed to be running," McGarrah says. "But had we lost
our other large unit or our interconnections to the two
utilities we are connected to, we would then have had trouble
meeting our load. That's what drove us to look at our alternatives."
The Rental
Alternative
The
city turned to APR for a temporary power plant that could
provide Tallahassee with 50 megawatts of backup power. And
city officials wanted the plant up and running quickly,
before the start of the summer peak period, which meant
that APR workers had to finish construction in 30 days.
Fortunately, the company specializes in quick turnaround.
The Tallahassee project was no exception. The contract was
signed on April 27, 2004. Construction began at the start
of May. And the temporary plant began operating June 1.
According
to company officials, the 30-day construction period presented
little challenge.
"We
put in the majority of our projects in 30 days," says Paul
Marcroft, business development manager for APR. "That's
the nature of our business. We're not just about providing
temporary power. We're about putting in temporary power
plants quickly. We are called in for emergency situations."
The
company can install its temporary plants so quickly because
they are largely standardized. This allows workers to quickly
assemble them no matter if they are installing them in California
or Sri Lanka.
The
plants are also designed in a way so that workers usually
have to do little to the land on which they will sit. For
instance, in the Tallahassee project, APR workers simply
located their temporary power station on a bare patch of
earth after having first poured gravel over it and compacted
it.
APR
workers also frequently reuse parts that have been used
in other temporary power plants. In the Tallahassee project,
workers used portions of a 100-megawatt temporary power
plantcircuit breakers, switchgears, and cablingthat they
had installed last year for a six-month backup project in
Vera Cruz, Mexico.
"That
is another reason we are able to execute our jobs so quickly,"
Marcroft says. "Some of the equipment that goes into these
plants are not off-the-shelf items. Some of them have long
lead times. It takes a long time for them to get to you
if you have to order them for every project. It can be a
struggle to get some of these items. The fact that we had
a pre-engineered, pre-designed 100-megawatt mirror-image
project helped us immensely."
The
Tallahassee project consisted of 12 transportable gas-turbine
generating sets and a 69-kilovolt step-up transformer. Each
of the mobile generating systems consisted of one trailer
for the generating set and another holding each set's control
room. Most interestingly, Internet technology was used to
remotely monitor the performance of this equipment. Workers
used the data from this to make sure they were ready should
the plant need emergency maintenance.
"Our
specialty is doing things quickly. That is true. We installed
this plant in 30 days. Everything was done quickly. But
we also do things very carefully," Marcroft says. "This
is a local government utility. We dealt with the City of
Tallahassee, too. We were obviously working under a stringent
process. We had to meet certain requirements. We got through
all of that. Ultimately, we executed the project on time.
The city was pleased with the way we integrated within their
infrastructure."
APR
also took care to design the station so that, if Tallahassee
officials decided to add an additional 50 megawatts of power
to it, as was their option, they could do so easily and
without compromising the availability of the original 50
megawatts.
APR
designed the station to allow for its quick removal once
the four-month contract ended. "Because of the way our plants
are set up, we can very quickly go in there and remove them,"
Marcroft says. "Once we're gone, all that's left is an empty
piece of ground. It's like we were never there in the first
place. What we did was work on a large area of land adjacent
to the existing facility. We put gravel down and compacted
it. What they are then left with once we are gone is a bare
patch of land with some gravel on it. They can use it in
the future. We pull out the high-voltage system. We pull
out everything we brought to the site and take it away.
There are no permanent foundations."
Fast-Track
Permitting
Tallahassee
officials had to move fast as well. After all, the city
had to secure all the proper permits before McGarrah could
pull the switch on the temporary plant.
Tallahassee
needed to obtain construction and operating permits from
both the state and Leon County. And though this was the
first time McGarrah had dealt with renting temporary power,
the experience went smoothly.
The
first step McGarrah took? He went to the county and state
regulatory agenciesthe Florida Department of Environmental
Protection and Leon Countyto explain to their officials
that the city was planning on renting temporary power to
avert any potential problems during the summer months. McGarrah
and the city approached the agencies even before they knew
they were going to work with APR.
"I thought it was important to give everyone involved a heads-up
about what we were going to do. We needed to act quickly so
that we would enter the summer with the proper amount of backup
power," McGarrah says. "The agencies worked extremely well
with us to process the permits in the shortest amount of time
possible. Fortunately, we already had a good reputation with
the state on an environmental basis. That certainly helped
move things along."
McGarrah
estimates that it took the city little more than a month
to acquire the necessary permits for the building and operation
of the temporary plant. First, the city obtainedwithin
about a week's timethe construction permit that allowed
workers to begin building the plant. Obtaining the operating
permits took longer. But the city got those on May 27, less
than a week before turning the plant on.
Did
the city take a risk by authorizing construction before
it had even gained its operating permits? Both McGarrah
and Marcroft say that the actual risk the city took on was
extremely small.
"The
city [officials] had done enough internal lobbying that
they knew the final approval was mostly a formality," Marcroft
says. "They had already done everything the regulatory agencies
had asked of them."
APR
took no real risk, either. The company's contract with the
city contained an out clause stipulating that APR would
be paid even if Tallahassee failed to obtain its operating
permits.
"That
was necessary," Marcroft says. "We were spending a lot of
money on installing equipment, procuring equipment."
Because
the city gained its operating permit a week before June
1, APR officials had enough time to test the temporary power
plant. It easily passed its eight-hour performance test,
Marcroft says.
Now
that his first experience with temporary power is over,
McGarrah says he wouldn't hesitate to turn to it again.
"We've
been very pleased with our relationship with Alstom," McGarrah
says. "They made every commitment they gave to us. They
made all their dates. I'm very pleased with our relationship
with them and how easy the process went on the units the
company installed."
Other Projects
While
the rental power business continues to grow, it has been
especially good for APR. Not only has the Jacksonville company
provided temporary power plants across the United States,
it has also taken on some intriguing projects in other parts
of the world.
In
May 2002, for instance, APR built a 20-megawatt temporary
power station in Chunnakam, Sri Lanka. The 15-month project's
goal was to provide power to the country's Jaffna area,
which, until recently, had suffered through 20 years of
civil war.
The
rental company provided 18 1.5-megawatt diesel generators,
10,000 feet of cable, switchgear, and other electrical equipment
to the country, shipping it from the United States to the
port of Colombo. That process alone took 30 days. Still,
APR managed to install the power stationfrom the time it
signed its contractin 60 days.
This
was no small accomplishment. The station's site was in thick
jungle with dense undergrowth that had to be cleared and
then graded to make sure the ground would drain properly.
This was especially important during the rainy season.
Next,
construction workers laid the foundations for the diesel
generators. Manual labor, without the help of machinery,
dug the trenches for the station's fuel piping and cabling.
To secure the area, workers built a 10-foot-high fence with
floodlights along the project's perimeter. Not only did
this allow for security, the lighting allowed workers to
work around-the-clock shifts.
Another interesting project took APR to Port-au-Prince, Haiti,
where the company delivered 34 megawatts of power in July
2003. The Haitian government was looking for a source of energy,
to be delivered quickly, to support the growing demand for
power in the capital city of Port-au-Prince. Government officials
called on the company to provide a 24-month temporary power
station to act as a "power bridge" while the government created
a more permanent power plant for the city. APR provided 21
diesel power modules to the city, all of them coupled with
step-up transformers.
As
in Tallahassee, installation and commissioning took just
30 days, which meant that power was online on time in early
September. APR provided all power distribution for the project,
including cabling and connection to the Haitian utility's
69-kilovolt substation.
Company
officials don't expect the market for rental power to slow
any time soon. And they also don't expect their travels
across the world to slow, either.
"This
market is strong year after year," Marcroft says. "It is
global. It is everywhere. We track very closely, for instance,
hydro-dependant countries, countries that are extremely
dependant on rain. In places like Sri Lanka and Venezuela,
the cities are very dependant on hydropower. If they get
a dry year, they are left with low reservoirs. They only
have a certain amount of megawatts available to them. During
the summer months and peak periods of energy use they have
to install temporary power. That's when we are called in."
Chesterton,
INbased Dan Rafter is a technical writer specializing in
energy-related topics.
DE - November/December
2004
|