|
After almost a quarter-century of service, the generator
was a source of growing concern to Don Englehardt, the hospital's
facilities manager.
"There were serviceability issues, and parts were unobtainable,"
he explains. "I was told that if the governor or the voltage
regulator were to fail, I would have to replace the entire
unit. Since I couldn't fix it, I started trying to replace
it before I needed to do so."
Englehardt consulted several vendors, including Wolverine
Power Systems Inc. Located in Holland, MI, Wolverine is the
southern Michigan dealer for Generac Power Systems Inc., of
Waukesha, WI. Generac specializes in modular power systems,
including the 750-kilowatt Gemini Twin Pack diesel generator
set.
Housed within a single enclosure, the Gemini Twin Pack's
two 375-kilowatt generators run in parallel. Under normal
operating conditions, integrated controls combine their output,
providing enough electricity to power the entire hospital
if utility power becomes unavailable. That wasn't possible
with the previous system, consisting of a single Detroit Diesel
engine from Detroit Diesel Corporation (a DaimlerChrysler
AG subsidiary) with a Cebra generator rated at 500 kilowatts.
Celebrating
Redundancy
"We're not obligated by the National Fire Protection Association
[NFPA] code to run the entire facility, but it's a nice option,"
Englehardt says. "In a long-term power failure, it alleviates
a lot of temporary wiring issuesrunning extension cords
to operate other machines, tripping hazards, and general safety
concerns."
Alone, either Gemini Twin Pack generator can back up the
other to carry the most crucial aspects of Community Hospital's
load, meeting all NFPA requirements for acute-care hospitals
to provide backup power for life-safety, critical-care, and
fire-pump applications within 10 seconds of a utility-power
outage.
"Don likes redundancy. He doesn't like to be stuck without
power. The Gemini Twin Pack practically guarantees that won't
happen," says Glenn Emmert, Wolverine's president.
The Gemini Twin Pack employs two startup timers: a time-delay
timer to screen for nuisance blips in the flow of utility
power, and a transfer-delay neutral timer that prevents large
motors from connecting out of phase with the backup generator.
Most applications use a 5-second setting for each timer,
Emmert says, "but we can adjust them down to practically zero.
When utility power goes out, both units in the enclosure get
the start signal. The first one comes up in about 6 seconds.
At that point, we can switch the life-safety, critical-care,
and fire-pump loads to the first one. The second parallels
to the first immediately after, in less than 10 seconds overall."
Switch to
Transparency
Englehardt can eliminate even this brief hiatus by a discretionary
switchover to backup power. The hospital's utility provider,
American Electric Power Company Inc., of Columbus, OH, "is
pretty reliable, but we have issues with acts of God," he
says. "Being in a rural area, we get a lot of storms that
bring trees down on power lines. If I see a bad storm rolling
in, I can turn the generators on, and then if we do lose utility
power, it will be transparent to the end users."
Such transparency comes courtesy of an optional feature included
in the hospital's system, the closed transition transfer switch
(CTTS). Generac's CTTS is the same physical size as a normal
transfer switch, but costs about 30% more.
A normal transfer switch has an open transition from utility
to generator power, which means an open relay in the transfer
switch has to sense a failure of utility power before it will
close, launching the generators' startup sequence. With a
CTTS, a discretionary switchover avoids any interruption because,
after the generators come online, the relay won't close until
it's in phase with the utility power. A CTTS also provides
a transparent switchover when utility power returns and the
generator shuts down.
The CTTSs enable Englehardt to perform weekly and monthly
tests of the emergency power system without having to announce
deliberately induced power glitches in advance.
Computerized
Controls
Another Generac option that Community Hospital selected is
the PowerManager System Controller (PM-SC), a programmable
logic controller with remote monitoring and management capability.
It maintains two-way communication with the transfer switches
monitoring utility power. If those transfer switches sense
a utility loss, they signal the PM-SC, which alerts the generators.
As the first generator starts, the PM-SC detects that event
and signals the crucial load elements to switch to the online
generator. After detecting the second generator's online presence,
it signals the rest of the hospital's load to switch over.
| |
 |
 |
|
The two units operate in parallel by comparing voltage and
speed. Isochronous governors count the teeth on the flywheels
and turn that count into a reference voltage, within a specified
window of acceptability, close enough to 60 hertz for the
synchronizer to recognize the similarity and close the contact
for the first generator set. Then the second unit parallels
with the first. Sometimes one unit connects first, sometimes
the other.
Mounted in a panel on the electrical-room wall, the PM-SC
communicates with the transfer switches and generators through
standard RS-485 communications cables. The PM-SC also is tied
to a telephone line with a modem, allowing Englehardt or Wolverine's
staff to monitor the system through a remote computer.
"We've used it to manage the system sometimes when Don has
a question," Emmert says. "We can do updates on the software
via the modem from our own office 50 miles north of Watervliet.
We could be in Hawaii and still do it. We have all the normal
security you would with any system tied into a modem, including
passwords and other security mechanisms.
"We also have the additional capability of load-shedding
transfer switches using the PM-SC," Emmert says. "Say you're
running, everything is fat and happy, and all of a sudden
one of the generators goes offline. The PM-SC senses that
and immediately sheds the transfer switch with the least critical
load. This is user-defined. It's part of the setup of the
whole system."
Testing and
Reality
Although the backup system could operate silently and efficiently
without human intervention, the NFPA code requires installation
of a remote annunciator panel to ensure that humans know when
something is amiss. Community Hospital placed this warning
mechanism in the admitting department, which is staffed around
the clock. Connected to the backup system through RS-485 communications
cables, the annunciator panel sounds a horn and flashes a
series of lights whenever utility power fails or a generator
malfunction occurs, alerting the admitting clerk to notify
a member of the maintenance staff.
Possible generator-malfunction conditions could include failure
to start, overheating, engine oil pressure above or below
specified limits, and the engine operating over or under its
appropriate speedbut none of these has occurred since
Community Hospital installed the new system.
"We manually opened an oil-pressure sensor once to test the
warning system," Englehardt says, "and it also worked during
a real outage. In July, a tree limb fell on the utility line.
Both generators came online, synchronized, and operated the
entire hospital for about three hours. When utility power
was restored, the generators went offline, cooled down, and
shut down just as they were supposed to."
The shutdown sequence employs three timers: a return-to-utility
timer that delays the shutdown long enough to ensure the stability
of utility power; a minimum-run timer that keeps the generators
running long enough for their temperature to stabilize, even
if utility power already has been restored; and a cool-down
timer that allows the engine to run at full rpm without a
load to avoid damage due to overheating and low oil pressure.
An Economical
Alternative
Emmert says the Gemini Twin Pack is an economical alternative
to a single large generator of about the same output for emergency
power applications. Its capital cost is 20%30% less, he says,
"because we're using smaller enginestwo 12-liter engines
from Mitsubishi Heavy Industries Ltd. They're an over-the-road
type, not a specialty engine. That allows us a better price
point per kilowatt-hour, and the smaller the engine, the quicker
it's capable of starting.
"Compared to a single 750-kilowatt unit, the two 375-kilowatt
Mitsubishis are not just small big units. They are different.
Everything is smaller. Parts are readily available, usually
at truck equipment parts stores."
From a service standpoint, the Mitsubishi engines don't require
the skills of a specialized large-engine mechanic, for whom
Wolverine bills $120 to $150 an hour. They can be serviced
by a technician, at a cost of $90 an hour.
The system itself is designed to expedite service, Emmert
says. "A 375-kilowatt alternator made by Generac is connected
to each engine, and both engines are on a single frame inside
a single enclosure. With all of the maintenance items to the
outside of the engine, you don't have to tear it apart to
get into it."
Also, because each generator has its own paralleling switchgear
on the generator frame, a separate room for conventional paralleling
switchgear isn't required. "That means you aren't taking up
real estate somewhere within a building, at exorbitant cost,"
Emmert says. "That's a huge saving. It can be hundreds of
thousands of dollars."
The Mitsubishi engines can be available on short notice,
Emmert says. "It's a high-volume engine, which reduces lead
time. We can get down as low as eight weeks from the date
of order. With a regular 750-kilowatt engine, you're talking
12 to 16 weeks."
Still another benefit of the Gemini Twin Pack is its ability
to accommodate growth. This is especially vital for Community
Hospital, which is considering an expansion within the next
five to 10 years. "The Gemini modular power system is scalable,
so Don can add system capacity if and when he needs to," Emmert
notes. "He could add a second Gemini Twin Pack or a single
375-kilowatt, 400-kilowatt, or 500-kilowatt unit in a separate
enclosure, and he has flexibility in where to put it. There
is room adjacent to the existing Gemini pad, or he could mount
another unit up to 3,000 feet away if he wants to run the
wires."
A Complex
Installation
Englehardt says deciding to replace the old backup system
and choosing a new one took about a year, and installation
took six months, including testing and load banking. "We began
in the fall of 2003 and wrapped it up early in 2004," he reports.
The installation took so long because it involved removal
of the old equipment and retrofitting the new equipment into
a previously constructed space. Installation of a Gemini Twin
Pack during construction of a new building is much less arduous,
costly, and time-consuming, typically involving anywhere from
a few days to a couple of weeks.
Parkway Electric & Communications LLC, of Holland,
MI, engineered and performed Community Hospital's Gemini Twin
Pack installation. "First we poured a concrete pad 22 feet
long, 10 feet wide, and 18 inches thick," explains Jim Achterhof,
Parkway's project manager. "Then we set the new Gemini
Twin Pack on the pad, and temporarily tied it into the hospital
before removing the old generator."
The Gemini Twin Pack sits behind the building near the loading
and shipping dock, about 30 feet from the boiler-room wall
and 3 feet from the edge of a parking lot. Its enclosure is
about 17 feet long, 7.8 feet wide, and slightly over 9 feet
tall (plus an additional 2 feet of height for the fuel tank).
Without fuel, the unit weighs 17,316 pounds.
Emmert says the enclosure's footprint is 20% smaller than
that of a single 750-kilowatt generator. Its patented design
incorporates internal baffles and corners that optimize air
flow and attenuate sound. At a distance of 7 meters (23 feet),
the measured 60-hertz sound level averages just 82 decibel-amps.
"The old generator was 6 feet wide, 6 feet high, and 15 feet
long," Achterhof says. "We had to remove a wall and pull it
with cranes and forklifts through that opening past the new
generator. We made the empty space our new main electrical-service
room, where the main distribution panel is located."
Wires in three underground conduits 30 feet long and 4 inches
in diameter link the Gemini Twin Pack to the main distribution
panel. "We drilled through the foundation walls and cut the
floors to run the new feeders into the hospital, then replaced
the floors," Achterhof says.
Each conduit contains four 600 mcm [1,000 circular milsa
wire-gauge measurement] cables with a total rating of 400
amps, for a grand total of 1,200 amps. The wire is three-quarters
of an inch in diameter and weighs slightly over a pound per
foot.
Four Transfer
Switches
The main distribution panel feeds two 800-amp circuit breakers.
One is for the three transfer switches supplying the code-mandated
loads (400 amps for critical care, 200 amps each for life
safety and the fire pump). The other feeds a 2,000-amp main-service
transfer switch for everything else. It's the last to come
online during a utility-power outage, and the first to fall
offline if one of the Gemini twins isn't available to carry
the hospital's entire load.
Parkway installed and fed wire to new life-safety,
critical-care, and fire-pump transfer switcheseach 2
feet, 8 inches wide, 4 feet high, and a foot deepin
the old electrical room. The new 2,000-amp transfer switch,
which is 5 feet high, 5 feet wide, and 4 feet deep, went into
the new electrical room.
When the time came to complete the final hookups, "we did
it in six hours with eight people," Achterhof says. "That
was eerie, while we had the automatic transfer switches out
of the circuit in a hospital. We picked a nice night with
no storms predicted, and we had a backup generator in case
of an outage, with wires ready to go and people standing by.
In case we would have had to start it, everything would have
been on the generator within minutes."
The hospital paid about $70,000 for the Gemini Twin Pack.
The installation cost an additional $97,000, of which 45%
is attributable to materials (including concrete, wire, the
new main service, crane rental, and fuel lines) and 55% to
labor. In operation, it will consume about 0.36 pound of fuel
per horsepower-hour. Assuming the cost of diesel fuel at $1
per gallon, that translates to 8¢ per kilowatt-hour. Annual
maintenance costs, for routine oil changes, oil sampling,
coolant maintenance, filter changes, turbocharger overhaul,
and the labor costs for these procedures should range from
$500 to $700 a year.
George Leposky is an energy and technology writer based
in Miami, FL.
DE - November/December
2004
|