|
In 1997, the US Department of Veterans Affairs (VA) was looking
for ways to save money on its growing utility costs and take
better control of energy assets at its two Chicago medical
centers. One site, called North Chicago, is adjacent to the
Great Lakes Naval Training Center. The other, Chicago West
Side (the Jesse Brown VA Medical Center), is located near
the University of IllinoisChicago.
Within a year, the VA started a review of its entire asset
portfolio, rethinking its core mission and how best to enhance
services to veterans. As a result, the energy project was
put on hold. Two years after a VA study of what type of capital
asset realignment should be done in the Chicago area, the
energy study was reopened. "The North Chicago site,"
says Ed Bradley, the VA's program leader for energy,
"was good to go as a medical center and would be a part
of that realignment. We revitalized the original energy project
at that time."
 |
 |
The VA is the second-largest cabinet agency and has an inventory
of sites that includes 168 hospitals and hundreds of other
medical facilities, such as nursing homes and outpatient clinics,
throughout the US. About 4.5 million veterans and family members
receive care from the VA each year. With the rising costs
of providing health care, the VA constantly looks for ways
to reduce other costs so that more dollars can go directly
to providing medical services.
The cogeneration (combined heat and power or CHP) concept
has been around for nearly 20 years. Other federal agencies
using it include: the Department of Defense, US Mint, General
Services Administration, and US Postal Service. "We are
interested in a centralized cogeneration facility," Bradley
says, "in lieu of just doing small-scale combined heat
and power or putting down a packaged generator to basically
do peak shaving."
Cynthia Cordova, a member of the VA's central energy
team, adds: "We did a study in 2003 that looked at all
of our facilities for cogeneration potential and identified
those sites that seemed to have the highest potential for
energy and cost savings. Out of our 168 medical facilities,
we found about 48 sites with high potential for benefiting
from this type of cogeneration arrangement. Hospitals are
often good candidates for cogeneration because they have high
thermal loads in relation to electric loads."
To contract for the installation of cogeneration plants,
the VA uses a special authority called enhanced-use leasing.
This allows the VA to lease underutilized land and buildings
to other parties in return for services or other forms of
consideration. For cogeneration projects, the lease is part
of a public-private partnership between the VA and a selected
contractor to construct and operate a cogeneration energy
center.
When the only alternative in North Chicago appeared to be
continuing to purchase steam from the neighboring Navy facility
and electricity from the local utility, Commonwealth Edison
(ComEd), the VA decided on the more cost-effective choice.
Energy Systems
Group
After the request for proposals (RFP) was
put out and bids were submitted, the company that eventually
won the project was Evansville, IN-based Energy Systems Group
(ESG), which does performance contracting according to Norm
Campbell, the firm's marketing director. "This includes
consulting, engineering, installation, operations, and even
financing. ESG guarantees their results, both in energy savings
and final outcome. If we don't perform, we're financially
responsible.
"This particular project, though, was completed five
months ahead of schedule and right on target. One interesting
part about the whole project is if you look at the players
that are at the table: the VA, national and local; the US
Navy; the University of Chicago Medical School; our company;
the equipment vendors; and also the utility itself, it was
like a big saucepot. It really took a whole lot of hands pulling
together to make this project work and was a good deal all
around.
"It really allows the VA some pretty good flexibility
in being able to leverage the different utility services [electricity,
steam, and chilled water] out of our energy center; it increases
the overall efficiencies to make it a very cost-effective
solution."
"This whole project was on hold," says Drew Gosling,
ESG's program manager, "for roughly two and a half
years. That's why this was a project with an RFP that
went out in 1997, yet no one signed a contract until 2002.
The VA had selected the contractor to do the project and then
it went on hold for the study. The VA didn't want to
implement an energy center in case this study came up with
the results that the hospital had to be shut down."
The VA's Two
Chicago Sites
The VA's North Chicago site is
adjacent to the NTC, from which the VA used to buy steam.
"There are a lot of benefits for the VA with this application,"
Campbell says. "Our energy center provides energy security
and independence to the North Chicago VA facility. The facility
has been there a long time. Its more than 20 buildings date
back to World War II times. There are existing steam tunnels
that we've revitalized and utilized for our utility as well
as making sure that the electric distribution systems are
able to maximize the benefits of a cogeneration setup."
 |
The VA originally bought all its steam from Great Lakes Naval
Training Station and all its electricity from Commonwealth
Edison. It was tied to this system. "The cost that the
VA was paying for their steam," says Gosling, "made
them decide to put out their RFP to see if they could do it,
finance it, get economic results that could make it cheaper
for them to put a system in and operate it, pay for the capital
on it, and still save money."
Preliminary economic analyses done by an outside consultant
indicated that these were good sites at which to build an
energy center, and that it would save money. Nearly one quarter
of the Navy's steam output23%went to the
VA. "The real kicker in all this," Gosling says,
"is that when the Navy had outgrown their landlocked
base and required additional land to build recruit barracks;
VA land was available. As part of the deal, the VA negotiated
with the Navy to buy steam and electricity from the new energy
center as part of the interagency agreement. Thus the chief
rationale was that instead of having to buy electricity and
steam from ComEd and the Naval Training Center, the VA now
has an energy center there that produces its own steam and
electricity.
"As the Navy load grows, the VA's savings gets
better because the Navy takes a higher percentage of the usage
of the plant. They are becoming a bigger user with the number
of barracks increasing. The more the Navy uses the more they
have to share in the fixed costs of the facility and therefore
it just increases the savings that the VA experiences.
"The Navy needed more space," Gosling continues.
"The VA wanted to pay less than what they did have to
pay for steam and electricity. Between both those things happening
and the VA deciding to go ahead and do an energy center, that's
how they are going to be able to, over the long-term, save
significantly large amounts of money. Probably by the time
they get to year three, when the Navy barracks are fully online,
they're looking at savings of over a million dollars per year."
The North Chicago project had two phases. Phase I was a brand-new
cogeneration energy center because there wasn't an existing
steam plant or energy system in place. "It was what they
call a Greenfield-type construction--so it was very much a
straightforward new-plant construction," Gosling says.
"With this one it wasn't like you were going to
go back and retrofit an already-existing plant. Here we basically
had to construct an entire plant and deal with running steam
and electric lines to tie into the distribution system, as
well as all interconnection with all the existing steam and
electric distribution systems. Phase II was an expansion of
the energy center that was already built in Phase I.
In Phase I of the energy center, ESG had two 53,000-lb/hr
package boilers and a 5-MW Solar Taurus 60 turbine, with a
60,000-lb/hr heat-recovery boiler attached to it. The phase
had a total of three boilers, one a recovery boiler mated
up with the turbine.
Phase II added another 53,000-lb/hr boiler, a slightly larger
7-MW Solar Taurus 70 turbine, and another 60,000-lb/per hour
heat-recovery boiler attached to that turbine. Now the VA
has two turbine heat-recovery boiler trains and three package
boilers at the energy center. All the turbines for both phases
are natural gasfired. Steam and electricity is metered
and split at the plant. Some gets sent directly to the VA;
some gets sent to the Navy distribution for its barracks.
"ESG does not have to be commercially available with
Phase II until February 2005," Gosling says. "Everything
is there and in place, still being wired and piped, and will
be operational and ready for testing by this winter. Once
online and operational, Commonwealth Edison will then buy
back excess power from the energy center."
Both of ESG's Chicago VA projects were standalone operations.
"They are both very similar plans and designs,"
says Lawrence Roth, head of corporate operations for ESG,
"but the Chicago West Side facility was actually purchasing
their steam from the University of IllinoisChicago.
What we did was build them a new steaming facility in an existing
dairy building [circa 1920]. Thus we were utilizing an existing
structure that was 80-plus years old. This was a cast-in-place
concrete building, two floors in size
about 20,000
square feet total."
The equipment that had to go into the Chicago West Side site
included a gas turbine, gas compressors, two package boilers,
a heat-recovery boiler on the turbine, a two-stage absorption
chiller, and a cooling tower on the roof. The two ESG energy
center sites are about 30 miles apart.
"The main thing that the VA seemed to be looking for,"
says Roth, "was independence. Both facilities were purchasing
their steam from other sources, the Navy and the University
of Illinois at Chicago. They wanted to take control of their
own destiny in a sense."
Roth admits to having the normal "little hurdles"
in working on this project. "It is always challenging
to work with a utility when your project will produce electricity
paralleled and into their grid. There's a lot of red
tape and precautionary measures required. The utility we worked
with in Illinois was much more stringent in their requirements
than what I was used to. They are very thorough in their review
of your design and they specify a lot of requirements. These
requirements add up, creating a great deal of expense to provide
the interconnect work."
Expectations
and Results
The main expectation of the project
was that the VA would be able to have an energy center installed.
With that, the VA could then pay for its steam and electricity
as well as the cost of the energy center's operations--and
actually be paying less, out of pocket, than what it was paying
for steam and electricity originally.
"That was the bottom line," says ESG's Gosling.
"ESG was the general contractor. Everyone was under us.
We designed it, built it, and now we operate it. We don't
directly receive payments from the Navy. They pay the VA.
The VA is responsible for procuring all the power and steam
for both those parties. The VA and Navy settle up the Navy's
usage between the two of them. Commonwealth Edison is the
local electrical utility, and the VA could still draw the
full site load of electricity from them if they had to. Under
normal operation, they are constantly connected to the local
electric utility."
One part of the results has changed. When the contract was
signed the baseline was different. Gas prices at that time,
(2002) were about $3.50 per MMBtu. Now gas costs are $6 to
$7 per MMBtu. The reality is that the Navy uses gas and it
has to charge more for its steam now, too. The bottom line
is that the VA will consistently save from a half million
to a million per year compared to the baselines.
Win-Win Situation
for the VA
According to Luke Brockman, ESG's
director of operations and maintenance services, one of the
beauties of an energy center is how it handles a blackout.
"Having an energy source that is fully reliable and secure
is of the highest importance to us and our customer,"
he says. "The outskirts of our Mountain Home, Tennessee,
VA facility noticed some of the effects of the 2003 Northeast
blackout. The control systems for the Tennessee facility detected
the direct effects of what was happening throughout the Northeast,
and these systems were set up so that the facility and attached
customers could ride through the disturbance without any impacts.
The energy center's customer [VA hospital operations] did
not notice the event as the energy center disconnected from
the electric grid at the first indication of a disturbance.
 |
"It's a highly reliable system and design operation,
but in short, the way we have structured our energy centers,
they are able to island' themselves so everybody else
can be out of power and we'll still be running," Brockman
notes.
The VA's Bradley is satisfied with the results and has
an eye on the future. "From what we've seen, we're
matching or exceeding our expectations with this project.
The future looks bright for the Chicago projects and for implementing
cogeneration energy centers in other VA facilities. But I
will add that it all depends on the economics for cost-effectiveness.
In time we may be looking at other technologies and fuel sources.
Our project agreement specifies that we remain as up-to-date
a facility as possible. If there are changes in technology
and fuel options, those are things that at that time we will
address."
PETER HILDEBRANDT writes extensively on engineering
and scientific subjects.
DE - January/February
2005
|