|
Power provided by the grid is more than up to the job of
powering lights and motors, but when you want to power tele-
and data communications equipment, or if you are manufacturing
microelectronics, you need to take the power that comes from
the utility and clean it up. The right kind of UPS (uninterruptible
power supply) not only can keep the equipment running during
a power failure, it can also provide a clean source of power.
The Other UPS
Power disturbances can cause problems for many types of critical
processes, particularly computers, servers, and phone systems
that have become increasingly central to all business operations.
While many systems are able to shrug off minor fluctuations,
larger surges can bring these machines to their knees. And
when it comes to making something as delicate and involved
as semiconductorsespecially when made on a large scalethe
damage and financial loss that can result from a surge or
even dirty power in such a factory is, well, lets just
say more than substantial.
The ultimate industry critical in nature from a power
point of view is the semiconductor industry, begins
Brad Roberts, power quality systems director at S&C Electric
Co., manufacturers of UPS systems. Each little piece
is very, very valuable. The process of making them is incredibly
delicate. If the lights blink [meaning theres a power
disturbance] for any of those companies, the result is just
devastating. Hundreds of thousands, maybe millions of dollars
are lost.
What Led One Company to a UPS
ST Microeletronics in Phoenix, AZ, is using S&C Electrics
single largest UPS system, which is also the worlds
largest outdoor system. Other semiconductor manufacturers
are using this system, as well. Installed in 2000, it went
online that summer. Online UPSs are still the predominant
solution in most computer centers, says Roberts. Semiconductor
factories use a mixture of online and offline systems. Were
the leader in medium-voltage equipment, and were the
only one that builds a large outdoor system.
 |
PHOTO: ST MICROELECTRONICS |
Prior to purchasing S&C Electrics UPS system, ST
Microelectronics didnt have any power protection. Needless
to say, it was a risky situation. In Phoenix, were
very susceptible in the summertime to monsoons, says
Joe Murphy, director of site facilities operations at STs
Phoenix office. It could be a beautiful day and, all
of a sudden, there are wind and storms. When those lightening
bolts strike, they hit power lines, and you see interruptions
and the tools go down. Just one monsoon could cost millions
if a lot of wafers are lost.
ST Microelectronics found they were losing a lot of wafers,
and having to do a lot of reworks as well. That was time and
materials lost. We needed to find something that would
protect the system so we could ride through these storms,
Murphy explains. Very seldom were these total power
outages. Most of the time wed see dips and spikes. But
these are just as harmful, because the tools that manufacture
these wafers run off microprocessors and theyre very
susceptible to power fluctuations.
We were doing the best we could to work with the local
utility, but unfortunately, with this kind of weather, theres
not much they can do. The 230-kV lines are unprotected. They
come into our distribution center. Then we drop those down
to 12,470 V, says Murphy. Initially, the company considered
using individual UPS systems at each tool, but there were
just too many tools for that to be practical. So we
looked at alternatives to having multiple UPSs; then we came
up with S&C Electrics UPS.
This UPSthe Purewave 12-MW system, which uses 12,470
Vwas costly. At the time ST Microelectronics purchased
it, it was $5 million, and since then theyve added an
additional $2.5 million to expand its capacity. The company,
however, could justify the cost when they counted the number
of wafers lost in comparison to the cost of the unit. In the
long run, they came out far ahead.
The Search
Like any smart buyer, ST Microelectronics looked at different
alternatives before deciding on S&C Electrics Purewave
12-MW UPS. It seemed to be the best choice for their particular
needs. An alternative they had also considered were generators
with flywheels on them. We would not have had the size
to have those, says Murphy. We wouldve had
to keep them running at all times, a costly solution,
he felt.
ST Microelectronicss main goals were to find the most
economical solutions that were both reliable and would be
able to ride them through the majority of the interruptions.
We figured that we had to protect the whole manufacturing
area and, to do that, we had to protect the whole building,
says Murphy. So we protected all the facilities-related
equipment and the manufacturing-related equipment. Although
ST had already been familiar with UPS technologytheyve
had UPS systems at other of their sitesthey had never
before had the opportunity to work with a system as large
as S&C Electrics.
Grooving with the Grid
There are two ways to provide UPSthrough online and
offline UPS systems. An online system takes that utility
power and basically regenerates it by running it through a
rectifier to convert it to DC power (battery power),
Roberts explains. Then you float a battery there and,
if anything goes wrong with the utility, the battery will
take over. Then you regenerate the DC power into AC power,
which is done in an inverter. Now there can be clean
power at the building.
With online UPS, you dont know when a problem will
occur, so the process of regeneration goes on all the time.
The problem is, theres a cost that goes with it: inefficiency.
You lose energy when you rectify the power, and even
more when you invert it back to AC, elaborates Roberts.
With this double-conversion process, you stick power in and
you only get about 90% of it out. That means there are losses
in the 6% to 10% range to generate that process. Thats
not so bad for something protecting your desktop, but when
youre talking about a large building, that can be hundreds
of thousands of dollars a year lost.
So, S&C Electric went to work to create a more effective
system geared toward businesses with large energy needs. Roberts
says, On a very large scale, we built an offline UPS
system that allows the power to flow directly to the load
from the utility. To protect a big factory of the size were
talking about, you have to be very, very good at doing that.
And its not easy. So weve perfected a system by
which we can sense and turn on many thousands of kilowatts
of power in about 2 to 4 milliseconds. This system comes out
to be physically smaller because it doesnt have to have
all that energy and capability on a continuous basis. And
its now 99% efficient.
Speed is of the Essence
When the Purewave 12-MW UPS senses any minor disturbance in
any of the three phases of the utility power, it automatically
turns itself on and disconnects from the utility. The
typical event lasts less that a tenth of a second. When the
utility grid has a disturbance, it takes a minimum of 50 milliseconds
to recover, our system fixes it in 2 to 4 milliseconds,
says Roberts. We can protect it before damage is done.
ST Microeletronicss UPS is located in the companys
substation, right inside the walls where the grid supply is
located. Power is flowing through the system at all
times, and the batteries always have a charge on them,
says Murphy. When its needed, we have a fast switch
and, as soon as it sees an interruption, the power will go
to the UPS system that will feed the plant. That happens within
a quarter of a cycle.
The savings associated with these large companies by using
this kind of system are tremendous. Although this is
not the case with ST Microelectronics, says Roberts,
other companies have very large generator systems and,
if the utility fails totally, then our system runs the plant
and then transfers it to the generator.
How Big and How Much?
For a company with medium-voltage needs, such as ST Microelectronics,
Roberts says the most practical choice would be to have a
medium-voltage solution. These companies are pretty
unique. It makes more sense than low voltage. With bigger
systems, a company is more cost-efficient, not just in price
but in operating costs. When a company like ST Microelectronics
looks at their whole lifecycle cost, it makes more sense to
buy a bigger system from us at medium voltage.
ST Microelectronics has UPS systems in every one of their
factories, all of which are very largetypically several
hundred thousand square feet of floor space. Some are even
over one million square feet. The loads in these facilities
are probably in excess of 50 watts per square foot,
says Roberts. ST Microelectronics is 450,000 square
feet; the main areas will be in 50-watt-per-square-foot range.
You need to protect that critical portion of the factorywhere
the tools are, the clean roombut not everywhere. At
ST, they did choose to protect the entire factory because
that was the most expeditious way to get the job done. It
was a retrofit.
Installing the Goods
The installation process was done by S&C, a turnkey company
that manufactures the product, installs it (by hiring outside
contractors), and maintains it. It took about four months,
did not affect the facility or workers, and Murphy maintains
that it went quite smoothly. We had a concrete pads
report, we had to do a tie-in to the electrical feeds, and
all units had to be put together on the site. After they were
tested in Milwaukee, they were shipped here and then assembled
again.
The only real concern ST Microelectronics had was regarding
the installation schedule. It seemed at first like it
was getting delayed but we finally got that under control,
says Murphy. In the end, the timing worked out just fine.
Pricing and Maintaining
Each individual company has different factors to consider
when it comes to whether they can afford to purchaseor
afford not to purchasea UPS system of this capacity.
Typically, if the payback for the investment is not
less than two years, companies wont do it, says
Roberts. But if theyre losing $10 million a year
and the solution is $5 million, that would probably work.
So the bottom line is, the more able a company is to calculate
its losses, the better able a company is to decide whether
such a system is a worthwhile investment.
All systems of this nature require maintenance. In most cases,
the customer depends on the supplier to provide it. And such
is the case with ST Microelectronics and S&C Electric
Co. We have a maintenance agreement with S&C,
says Murphy. They come in periodically and adjust the
machine, and this doesnt really disrupt it. But
some disruptions, even when theres nice weather, just
cant be predicted. Murphy recalls the following incident:
One time, they were doing something to the system this
past year and they took it off line. It was a sunny day. It
was Valentines Day, and someone had mylar balloons that
hit the 230-KV lines. We heard a big bang with balloons.
Unfortunately, that was one costly holiday for the company.
Roberts points out that one of the benefits of the S&C
Purewave 12-MW, 12,470-V system is that it only needs a major
inspection once a year. The customer has the responsibility
of changing air filters and things like that maybe once a
month. They also pay us to monitor the system remotely,
he says. S&C monitors about 50 sites around the world.
Our computer system checks each one of those systems
every night, then reports if everything is fine, or if something
happened at a site, like a thunderstorm and a disturbance.
Our UPS systems have what is called a bypass. That
means if the equipment develops a problem, it will take itself
out of service and put the customer onto raw utility power.
The customers obviously dont like that, says Roberts.
They want a quick response. If a malfunction occurs
at a customer plant, we get notification via remote alarm
system. S&C also sends service engineerswho are
on call 24 hoursthere immediately. So if a system
is down, its not long before its up again.
Expectations and Results
For ST Microelectronics, the decision to purchase the Purewave
12-MW system was one that paid off. It has definitely fulfilled
the hopes and expectations the company had before buying it.
What we do is we measure the number of saves we have
and every time the Purewave system has come on, says
Murphy. To date we have about 112 saves in the four
years weve had it.
Has it ever not worked? Yes. Eight times, to be exact. But
ST Microelectronics was not disappointed by this because a
lot of times the unit was offline when something happenedwhich
isnt the same as malfunctioning. And Murphy asserts
that when its online it always seems to work. It is
usually offline because of maintenance. This could mean that
technicians are changing batteries or making upgrades to the
system.
Each save is a good payback, starts Murphy, but
its a question of how much was the payback and how much
was the hit? In 01 and 03, we had the two worst
monsoon seasons in awhile. In those particular years we saved
millions.
Courageous Pioneering
Before ST Microelectronics decided to use the Purewave 12-MW
UPS, it was not being used much at all. Along with being one
of the first companies to use it, ST was also the largest
single user. Although there was some reluctance on STs
part to buy itbecause of the unknown factors that come
with a product that has not yet been widely usedthey
went forward with it because S&C Electric was noted for
their high-quality product and integrity. In addition, this
particular product was best suited for their specific needs.
We have a lot of praise for S&C for their ethical
approach, says Murphy. Theyre very ethical.
If theres a problem, I know about it right away. They
always try to update the system to make it even better.
And with S&C covering the installation and maintenance,
customers like Murphy never have to deal with an outside party.
So, perhaps the lesson here is to know your needs, research
your manufacturers track record and reputation, and
be sure you are clear about the extent of the services the
company will provide and how that will serve you. Then you
can make an informed decisionwith confidence.
AMY SORKIN is an LA-based freelance journalist and copywriter
who specializes in marketing communications.
DE - November/December
2005
|