|
Eagle County,
CO, is home to the scenic Sylvan Lake State Park. Located
in the Rocky Mountains about 30 mi. west of Vail, Sylvan
Lake is a popular spot for outdoor enthusiasts, with
camping, fishing, hiking, wildlife observation, and
photography among the many activities people enjoy there.
The 44-surface-ac.
Sylvan Lake is held by a dam that was installed by a
mink farmer in the early 1940s. In 1960, the Colorado
Division of Wildlife acquired the property, turning
it over to the Colorado State Parks system a few years
later.
The Sylvan
Lake dam was considered a Class I, high-hazard dam because
of the campsites located downstream from the outlet.
During a 1998 inspection, a Colorado Division of Water
Resources dam safety engineer discovered pinholes and
a 4-in. deflection in the 30-in. corrugated metal dam
outlet pipe.
Colorado
State Parks hired a private consultant, Christopher
Manera, P.E., president of Colorado River Engineering,
to advise on the best way to fix the problem. Manera's
first task was to conduct a feasibility study. Initial
inspections showed that although the pipe was deteriorated,
there was no immediate threat of collapse. That gave
the team plenty of time to research replacement and
rehabilitation alternatives.
Over the
course of further evaluations, Manera found that - other
than replacement of the outlet structure, which would
require a complete breach of the dam - the only viable
option was trenchless rehabilitation.
Trenchless
rehabilitation was a less expensive option than replacement.
In addition, because Sylvan Lake is a high-elevation
reservoir, the construction season lasts a mere four
months. "Replacement of the dam would have taken
at least two summer seasons," says Manera.
 |
| Bypass
pumps set up at the inlet to allow for flow diversion
during installation |
 |
| A
concrete gatehouse was built at the outlet to control
spillway erosion. |
The team
decided the best method of rehabilitating the outlet
was to use cured-in-place pipe. Other trenchless methods,
such as sliplining or fold-and-form lining, would have
reduced hydraulic capacity of the pipe to unsatisfactory
levels and would not have met the state's water-level
drawdown requirements for dam safety. "We ran the
hydraulic calculations, and that immediately removed
any other rehabilitation alternatives," notes Manera.
The lining
portion of the project was awarded to Breckenridge,
CO–based Western Slope Utilities (WSU), a full-service
utility contractor and licensee of Inliner Technologies'
method of cured-in-place pipe. Clarke & Co. Inc.
of Grand Junction, CO, was the general contractor for
the dam rehabilitation project.
With the
lake being such a popular recreational destination,
the state didn't want to consider scheduling the project
during summer months. Springtime wasn't an option either:
Because the dam was built over an original stream system,
the creek flow was heaviest in the spring due to mountain
runoff from the long winter snow. Work began in September
2002.
The lake
hadn't been drained in more than 50 years, and the team
didn't know what it was going to find. "The dam
was originally built with onsite materials," says
David Fox, project engineer for Colorado State Parks.
"We didn't know what to expect and how much it
was going to cost."
The lake
is home to a large number of freshwater shrimp. The
Colorado Division of Wildlife lifted fishing restrictions
because it wasn't sure how well the fish would winter.
The team elected to build a cofferdam at the far end
of the lake to retain 4 - 6 ft. of water, which would
help ensure that the remaining fish survived.
 |
| Workers
guide a winch operator as the Inliner tube is pulled
through the pipe from upstream the dam outfall. |
 |
| WSU
workers prepare to install the calibration hose
inside the lining tube. |
Although
the fall season was determined as the best time to schedule
the project, early high-mountain snows and warm temperatures
brought an inflow into the lake at 4 - 6 cfs during
what is traditionally a dry period. A temporary weir
was constructed to allow for bypassing the inflow.
Original
plans called for replacement of the entire inlet structure;
however, after the lake was drained, the concrete inlet
box was discovered to be in excellent condition, and
only the trash rack, slide gate, and lift mechanism
needed to be replaced.
The project
team had originally contemplated building a road through
the reservoir to transport equipment needed to install
the cured-in-place pipe from the upstream end. The ground
was very soft and boggy, however, and the cost for road
building would have been significant.
As an alternative,
the team elected to insert the liner from the downstream
end of the 160-ft. pipe. "Because the lake sits
at 8,500 feet above sea level, we anticipated a significant
decrease in equipment efficiency," relates Dan
Cohen, WSU's director of operations. "We
have extensive experience with high-altitude construction,
and we were able to accurately compensate for the decrease."
The wall
thickness of the liner was determined by measuring the
hydrostatic buckling load along the length of the pipeline
as it traveled through the dam. The wall thickness varied
between 17 and 27 mm. "We designed the liner to
be 17 millimeters thick at the ends, where earth and
hydrostatic loading were minimal," explains Cohen.
"In the middle section, we transitioned up to
27 millimeters - not only to compensate for the
higher loads but also to add structural integrity to
the pipe, which was damaged and ovalized."
The smooth
liner improved the flow rate by decreasing the effect
of the ripples in the corrugated metal pipe (CMP), says
Fox. "Although we elected to use 1-inch liner,
which reduced the effective diameter of the pipe from
30 inches to 28 inches, friction was reduced after the
pipe was rehabilitated."
The team
also modified the design; where the water enters the
new liner, there is a gap where a portion of the old
CMP is still visible. Because the area was small, the
contractor fabricated a 28-in. steel orifice plate to
prevent water jetting between the old CMP and the new
liner interface.
Work was
completed in less than six weeks. Colorado State Parks
and the state's dam safety personnel were very
pleased with the outcome.
EC
- January/February 2004
|