|
To get a realistic view
of how a welding shop works, we talked to a typical medium-size
grading and excavating contractor in the Midwest doing grading and
excavating of roads and highways and asphalt paving. It also owns
and operates a quarry that produces aggregate for both itself and
other contractors. This company, which chooses to remain anonymous
and therefore we will refer to as XYZ Construction Company, has
150 pieces of construction equipment in its fleet, including bulldozers,
loaders, backhoes, excavators, graders, and rock-crushing equipment.
Virtually all maintenance is done in-house.
Many repairs of construction-equipment
metal components are done in the field when the day’s shift is over.
Other repairs, especially major ones, are done in XYZ’s central
maintenance facilities. Why does the company do the vast majority
of repairs in-house? Primarily, says a company spokesperson, "to
minimize downtime of construction equipment—to make hay while the
sun shines." There is a long winter in this northern region,
with only so many months a year to do construction. Accordingly,
the company doesn’t have the luxury to wait for a dealer or other
outside maintenance facility to repair its equipment.
Basic
Equipment Needed for a Welding and Fabrication Shop
What sort of central
maintenance facilities does XYZ have; what sort of shop for repairing
metal on construction equipment?
XYZ makes a clear physical
separation between its engine and equipment repair facilities and
its welding and fabrication shop. The latter, separated from the
former by a solid wall, consists of five bays. The welding shop
is sharply separated from engine repair because: (1) there is often
much dust in the air in the welding shop, harmful to engine repair,
and (2) the intense light from arc welding might cause eye damage
to ungoggled mechanics working in adjacent areas.
What equipment does XYZ
have in its welding and fabrication shop? Most important are the
power sources for doing electric-arc welding. The shop has three-phase
AC electric power coming in from an outside electric utility. That
power is used to operate 20 arc-welding power-supply units. All
these units are DC; XYZ does not use AC for arc welding. These DC
power-supply units are of varying sizes, with outputs ranging from
300 amps to 600 amps, and are priced new from $6,000 to $8,000 (including
gasoline or diesel engine). XYZ uses these units in the shop and
in the field. The three leading suppliers of arc-welding power-supply
units are ESAB, Lincoln Electric, and Miller Electric.
In the shop, XYZ uses
both stick electric-arc welding and MIG (metal inert gas) electric-arc
welding with wire feed (see the "Metallurgy and Welding 101"
article in the November/December 2000 issue). In stick welding,
a flux coating on the surface of the electrode stick melts during
welding, covering the weld pool with a protective layer, which prevents
atmospheric oxygen and nitrogen from contaminating the weld pool.
With MIG welding, on the other hand, the weld pool is protected
from direct contact with the atmosphere by the release of an inert
gas, which hovers over the weld pool. The trigger of a welding gun
initiates both the feeding of the wire electrode and the release
of the protective inert gas.
For many shop-welding
applications, XYZ prefers MIG to stick electric-arc welding. MIG
welding is much faster, for the consumable wire electrode (with
many feet wound onto a nearby large reel) is fed automatically and
rapidly through the welding gun. With stick welding, the welder
must stop often to clamp on a new consumable welding
electrode, slowing down
the welding process. Also, with MIG welding, since no flux is used,
no slag covering forms on top of the weld pool, as in stick welding.
In stick welding, after the weld pool hardens, the welder must first
take the time to chip off this slag surface coating before laying
down an additional layer of weld material.
Also
Needed: Torches, Grinder, and Overhead Crane
In addition to welding
metals, XYZ also cuts steel plates—for example, when welding abrasion-resistant
plate onto excavator buckets. For cutting, it uses an oxyacetylene
torch. Incidentally, such a torch is rarely used in the actual welding
of construction equipment, for oxyacetylene welding is far too slow—it
takes too long to heat the base metal to appropriate temperatures.
Heating metals electrically, as in electric-arc welding, is far
more focused and efficient.
For cutting steel, XYZ
also has in its shop a gas-plasma torch. This is much more expensive
than an oxyacetylene torch—$10,000 versus $275 for the oxyacetylene
hardware. Yet if a shop is doing a lot of cutting, oxyacetylene
can become expensive, for a considerable amount of gases are burned.
At $35 per tank for oxygen and $30 per tank for acetylene, that
can add up fast. But the plasma torch consumes no gases; it merely
operates off shop compressed air. If a shop does a lot of cutting,
it may make sense to purchase a gas-plasma torch; although it has
a high initial capital cost, operating costs are low.
In repairing a metal
crack, the welder must first gouge or widen it out to make room
for the weld material to flow in. To that end, XYZ’s welding and
fabrication shop has air-arc gouging equipment, which runs off shop
compressed air.
Finally, XYZ’s welding
shop has band saws, drill presses, and grinders. Why this equipment?
A major task is cutting steel plate to appropriate sizes—for example,
cutting a plate for later welding onto inside or outside walls of
an excavator bucket. Once the steel plate has been cut by an oxyacetylene
or gas-plasma torch, its rough edges must then be smoothed—the reason
for having a grinder. A shop also needs a band saw to cut steel-shaft
material to appropriate lengths to be pivot-hole pins.
This well-equipped construction-company
welding shop also needs an overhead crane for moving heavy objects
around the shop. Often, for instance, a bucket needing major metal
repair may be removed from an excavator in the field and lifted
onto a trailer by a truck-mounted crane. The truck would then pull
the trailer to the welding shop, backing the trailer into a bay.
The bay overhead crane would now lift the bucket off the trailer
and place it in an appropriate welding position.
An overhead crane for
a construction-equipment welding shop, says XYZ, needs to have a
10-ton lifting capacity, an item with a price tag of about $25,000.
Among leading producers of such cranes are North American Crane
(Philadelphia, PA) and P&H Crane (Wakashaw, WI). A well-equipped
welding shop also needs a 10,000-lb.-capacity forklift (which costs
$18,000) for unloading steel sheet and plate off trucks and moving
them into the welding shop.
To do numerous repairs
on construction equipment, XYZ regularly purchases a variety of
steel plate from a regional steel warehouse, in this case Leeco
Steel in Chicago, IL. Typically it buys two types of steel plate,
T1 steel and abrasion-resistant (AR) steel, in 8- x 10-ft. sizes,
ranging in thickness from 3/8 to 2 in.
Excavator
Buckets: Protect With Both Steel Plate and Hardfacing
With the above equipment
and materials in its welding and fabrication shop, XYZ can do a
wide range of metal repairs on its construction equipment. One of
its biggest problems is excavator buckets. To protect bucket surfaces
from wear, XYZ workers weld AR steel plates onto bucket inside and
outside surfaces, then add hardfacing on top of these welded-on
plates.
Specifically, XYZ welds
AR steel plates onto both the inside and outside surfaces of excavator
buckets. Yet there are areas of bucket surfaces where it is not
possible to weld on plate—for instance, across the bucket teeth
and along the top of the bucket. In such uncongenial areas, XYZ
applies hardfacing to protect the bucket base metal.
On the outside bottom
surface of an excavator bucket—a region of especially high abrasion—XYZ
not only welds on AR plate, it also adds a grid pattern of hardfacing
ridges on top of the AR plate itself. Without the hardfacing grid,
the company, when working in highly abrasive soils, might have to
replace the AR plate in less than a month. But by hardfacing the
surface of the AR plate, XYZ can protect it indefinitely. After
a few months, it will have to rehardface the surface of the AR plate,
which remains intact.
Actually, how often the
bottom surface of a bucket has to be rehardsurfaced depends on the
character of the soils being excavated. If a site contains an abrasive
granite quarry or soil, rehardfacing might have to be done every
four to six weeks; if it has limestone-laden earth, the bucket might
be able to go up to six months without being rehardfaced.
In applying hardfacing,
XYZ adds not a continuous coating but a pattern (either grid or
hatch) of ridges. These welded ridges are anywhere from 1/4 to 3/8
in. high. The ridges must be oriented so that they lie perpendicular
to the direction that the earth will "flow" over the bucket
surface. In this way, the earth will no longer flow directly in
contact with the original T1-steel surface of the bucket. Instead,
it will slide over the hardfacing ridges, thereby protecting the
bucket base metal.
XYZ does most of its
hardfacing in the field using either self-shielded–stick or wire
electric-arc welding. The choice depends on the welder. If the bucket
can be placed in a good welding position in the field, many welders
prefer using wire welding, for it is much faster than stick welding.
Many of XYZ’s maintenance trucks are equipped with the wire reels
needed to do the wire welding. Hardsurfacing the bottom of a bucket
might typically take five hours.
Protect
Blades With Steel Liners
Another major activity
done in XYZ’s welding and fabrication shop is the repairing of bulldozer
blades. The bottom cutting edge, bolted onto the 4-ft.-high blade,
must be replaced fairly frequently. It is merely a matter of removing
the old cutting edge, purchasing a new cutting edge from an aftermarket
dealer, then bolting it onto the blade, a repair readily done in
the field.
But XYZ has a program
to protect the entire 4-ft.-high surface of the blade itself. And
to do this, it does not use hardfacing because a grid-shaped pattern
of hardfacing ridges on the blade surface causes soils, especially
those with a high clay content, to build up on the blade surface
itself. This caking of soil on the blade inhibits the smooth lateral
flow of earth during bulldozing.
Accordingly, to provide
protection of the T1 alloy-steel dozer blade (subjected to both
tensile forces and abrasion) while at the same time sidestepping
the dozer-blade caking problem, XYZ welds a T1 alloy-steel liner
over the entire dozer-blade surface. The company buys 1/2- to 5/8-in.-thick
steel plate from a steel vendor and has it bend the steel to the
actual curvature of the 4-ft.-high dozer blade. In its own shop,
XYZ now welds this steel liner onto the bulldozer-blade surface.
The smooth, shiny surface of the liner ensures that soil glides
over it during dozing without surface caking. The liner usually
lasts for two or three years, then is replaced with a new liner.
Gene
Dallaire is a former feature article writer for Chemical Engineering
and Civil Engineering magazines. He currently teaches history at
Lansing (MI) Community College.
|