|
John Carlo Company
Inc. (JCC) of Clinton Township, MI, one of the states
leading road paving and construction companies, received not
one, but two national industry awards for its recent reconstruction
work on Interstate 275, Detroits largest commuter highway
with 200,000 vehicle operations per day. Both the American
Concrete Paving Association and the National Quality Initiative
singled out the project for recognition for its immense scope,
innovations, state-of-the-art equipment, and ahead-of-schedule
completion, but these accolades merely scratch the surface.
 |
Prior to letting
of the ambitious, $50 million contract entailing the
design, paving, and reconstruction of a 6-mi. stretch of divided
interstate highway between M-14 and I-696a task requiring
replacement of more than 50 lane-miles of 12-ft.-wide pavement,
removal and replacement of the southbound portions base
layer, demolition and reconstruction of two bridges, rebuilding
and painting of 10 other bridges, and reconstruction of 18
ramps (all in the presence of heavy traffic)many Michigan
Department of Transportation (MDOT) officials held serious
concerns as to whether the job could be completed in just
one construction season. Accordingly the contract established
180 days from the scheduled commencement date of April 20,
1999, as the target, reinforcing the tight schedule with bonuses
and/or penalties of $50,000/day for completion.
"These awards
are a testament to the dedication and teamwork of everyone
involvedall our employees, Wilcox Associates [the project
engineer], and the Michigan Department of Transportation,"
remarks Steve Gregor, manager of JCCs concrete division.
Holding to the
Critical Path
According to Dennis
Hanley, JCCs manager of the I-275 project, "Staying
on schedule was absolutely mandatory." Just a quick walk
with him through the task list is ample proof of his assertion.
"First we
created a divider down the northbound side by pouring 26,000
linear feet of temporary cast-in-place barrier wall, before
routing southbound traffic over. We lost a lane in each direction,
but traffic was still able to move along without too much
disruption." Construction then began on the southbound
lanes with the removal of all the concrete and aggregate base.
We followed this by reprofiling the roadbed in preparation
for the replacement of the base with new aggregate and geotextile
liner." A GEOTEX 315-ST geotextile liner from SI Geosolutions
of Chattanooga, TN, was placed on top of the subgrade prior
to the addition of the new sub-base materialwhat the
contractor calls a 5G open-graded drainage course.
"The woven
geotextile serves to prevent contamination of the subgrade
by the sub-base," explains Kevin OBerry of CSI/Geoturf
in Highland, MI, supplier of the material. "Not only
does this serve to eliminate the primary cause of roadway
failure by distributing the load more uniformly, but it also
actually reduces the amount of sub-base required for stabilization."
Removing longitudinal
rebar can be quite a chore, but as Christopher Shinners of
Antigo Construction Inc. in Antigo, WI, explains, "We
operated up to four Badger Breakers [Models 8600 and the self-transporting
T8600] on the project at one time to meet John Carlos
production requirements. We hit the pavement at 6-inch intervals
with our guillotine breakers to allow Carlo to rake the rebar
to the surface to remove it prior to removing the concrete.
The rebar is essentially debonded from the concrete."
The exposed rods were then raked into piles along the edge
of the slab, where shears attached to backhoes cut them into
8- to 10-ft. lengths, allowing grapplers (also mounted on
backhoes) to load them into scrap Dumpster boxes for removal.
"We were carrying
off between 20 and 30 of those a day, so there we were with
four breakers, a pair of rakes, three backhoes with shears
and grapplers, and three backhoes loading out 70 to 80 trucks
going full-tilt, while dozers windrowed the rubblized concrete.
In less than 10 days we removed 5 miles of pavement from four
lanes," describes Hanley with a certain amount of amazement.
"And after the old concrete on the southbound lane was
removed and replaced, we switched the barriers over onto the
new southbound side and began the removal process all over
again on the northbound lanes."
Meanwhile the demolition/reconstruction
and repair of bridges proceeded at full tilt to accommodate
the tight schedule. Two decks had to be completely renovated
on one of the major mile roads, and the demolition, pavement
removal, and repaving had to coincide with the highway schedule
so that the 36-ft.-spread pavers could track over the decks
when they reached that point in the job.
"The bridges
were just about in the middle of the job, so the timing was
crucial to make sure the bridge was back in place and cured
when the paver was ready to cross the deck." Here again
Hanley seems impressed by the fact that the subtask was completed
within 24 hours of plan, but such success was by no means
an accident. "We use a Primavera scheduling package to
provide MDOT and us with a critical path schedule for all
the work, and we find that the Primavera does a good job.
Even though the majority of our control takes place on-site,
were doing more on-line these days with instant messaging
and e-mail."
How many people
worked on the project? The job was insured under a wrap-up
policy by the state, which provided all the insurance and
the safety inspections. "We had two to three safety inspectors
with us on-site each day," Hanley recalls, "and
one of the things we had to do was provide safety-training
orientation for every person on the jobmore than 900
people total." At the height of construction there were
250 workers on-site at one time. "One of our biggest
concerns for the company is safety and safety training. Our
signs are in English and Spanish, and we hold biannual safety
meetings for all our workers." Additionally, the company
pushes for on-the-job "toolbox" safety meetings
10-15 minutes each day.
Where Are the
Rest of the 25 Reasons?
Well, lets
see. Aside from the techniques, equipment, and accomplishments
noted above, we should list the following:
- The I-275 project
was one of the first in the state to be let on a design-build
warrantee contract, an approach finding increasing favor
among public- and private-industry project owners alike.
In it JCC warrants its work for a period of five yearsquite
a show of confidence in the value of its product.
- A 36-ft.-spread
paverirreverently known by JCCs workmen as "The
Intimidator," a Gomaco 4000was able to pave three
lanes in one pass.
- A Gomaco IDBI
automated dowel bar placer operated by computer did away
with the need for baskets. Dowels are loaded into the machine,
which distributes them over the width of the pavement into
a holding area and then depresses them into the concrete
to the proper elevation.
- An innovative
barrier-wall method borrowed from the post-tensioning used
in bridges knocked an entire week off the schedule. Two
conduits were slipped through the barrier wall, and cable
was pulled through and post-tensioned, holding barriers
in place.
But mostly you
can chalk up the "25 reasons" to the number of days
it took to complete the already optimistic 180-day project.
Except for site vegetation touch-up work that carried on into
the 2000 growing season, JCC crews were on and off the job
in 155 days. Remember the earlier remark about $50,000/day
bonuses and penalties? That pencils out to $1.25 million added
to the bottom line
the best award of all.
|