| |
When people think of
building demolition, they almost invariably conjure up visions of
spectacular implosions with large buildings collapsing in seconds.
And indeed that is a part of the $2.5 billion business that is building
demolition. However, it is a small part, accounting for less than
one percent of demolition work. The National Association of Demolition
Contractors (NADC) asserts that "more than 99% of demolition
work is handled with specialized heavy demolition equipment or skilled
manual techniques
. Todays standard equipment includes
the hydraulic excavator with attachments such as grapples, shears,
hammers, and concrete crushers."
To that list should be
added cranes, loaders, and even balers. (Recently, David Mardigan,
president of MCM Management Corporation of Detroit, MI, reportedly
announced that his firm purchased an Al-Jon 400 baler. "It
has expanded our horizons as a demolition company (because) it is
more cost-effective to ship loads (of scrap metal) to market with
bales as opposed to boxing loose metal.")
It should not be surprising
that demolition contractors use standard construction-industry tools;
after all, they routinely lift down the trusses and other
roof support members that some construction contractor once lifted
up into place. Also, they must excavate to remove foundations
and basements, and they must grade the site at the completion of
the demolition job.
Similarly, their use
of balers, magnets, wood chippers, and other equipment typically
used in the recycling industry makes perfect sense too. After all,
recycling is a major part of a demolition contractors business.
According to the NADC, recycling often represents 20-50% of demolition
project revenues. With current technology, contractors are able
to separate demolition debris and thereby maximize the recovery
of resalable materials and consequently reduce waste disposal costs.
Thus, demolition contractors have the two best possible incentives
to maximize recovery: increase revenues and decrease disposal costs.
Not just a demolished
buildings wood and metal are recycled either, the NADC points
out. "Demolition contractors have become masters of efficient
materials recovery. High-value materials suitable for refurbishing
or reuse are removed and sold. The salvage industry has grown hand
in hand with the demolition industry and is a reliable outlet for
architectural features, woodwork, lighting, plumbing fixtures, et
cetera. Rare items have established national markets, and there
are strong regional markets for fixtures, used brick, decorative
items, timbers, and other recoverable material." And on a more
mundane level, concrete and woodwaste also have recycling value.
Since there is such a large quantity of these materials at typical
demolition sites, concrete crushing and wood chipping can generate
significant revenues and preclude landfill costs that would otherwise
be incurred. As a result of all these factors, demolition professionals
routinely achieve very high levels of recovery.
However, their work is
by no means routine. A successful demolition project requires a
working knowledge of both construction and the law. Decisions involving
mechanical and electrical systems engineering as well as environmental
regulations must be constantly addressed. Many job problems require
innovative solutions based on experience and creativity. And part
and parcel of these decisions is the need to control danger in an
inherently dangerous environment. Amazingly, most professional demolition
contractors have outstanding safety records. For example, Brandenburg
Industrial Service Company in Chicago, IL, has a current workers
compensation experience modification of just 0.51, and its OSHA
recordable-incident rate is less than one-third of the national
construction-industry average.
To illustrate how all
this is accomplished, we investigated five separate and diverse
demolition projects to see how demolition contractors dealt with
site conditions and nonstandard problems. These projects were: The
Sears Catalogue Warehouse in Chicago; the Northwest Motor Inn in
Crystal Lake, IL; the Metropolitan Airport parking ramp in MinneapolisSt.
Paul, MN; the River Center Arena in St. Paul; and the Fort Vancouver
plywood mill in Vancouver, WA.
Sears
Catalogue Warehouse
 |
| The
Sears Catalogue Warehouse |
 |
| The
tower was saved. |
The Sears Catalogue Warehouse
on Chicagos West Side is thought to be the largest timber-framed
building ever built. Constructed in 1906, this former Sears &
Roebuck national headquarters was a nine-story, 3 millionft.2
timber and brick structure with a distinctive clock tower soaring
five additional stories. The building consisted of approximately
23 million bricks and more than 12 million board-ft. of lumber,
including 7.5 million board-ft. of heart-pine beams and decking.
"Both the bricks
and the heart pine were unusually valuable," states Bill Moore,
Brandenburgs vice president of marketing. "The bricks
were Chicago common bricks, much in demand for their yellow-brown
color and their smooth texture. Whats more, this smooth texture
enabled them to be easily cleaned; one tap with a hammer and the
mortar pops right off. With this low-cost cleaning available, recycling
of these popular bricks pays off even more than recycling of todays
rough-textured bricks.
"The 12-inch by
12-inch by 20-foot timbers were all antique heart pine, a handsome
wood that is almost extinct now. Probably 200 to 300 years old when
it was cut for this building in 1905, it was too valuable to be
reused for structural timber. With its 15 to 20 growth rings per
inch, it is commercially marketable at up to $10 per square foot
for use as flooring. We had bids for it from antique dealers all
over the world before we ever started the demolition."
With the unusually high
recycling value of the bricks and the pine, Brandenburg went about
the demolition carefully. Employing a fleet consisting of two large,
165-ton American cranes; a half-dozen Koehring excavators equipped
with grapples and shears; and both tracked and rubber-tired Cat
loaders (973s and 980s), Brandenburg dismantled rather than demolished
these materials. The cranes clam buckets bit into the 36-in.-thick
brick walls and brought each bucketful of bricks down to the surface,
where they were cleaned and prepared for shipping by a local crew
of a minority business enterprise (MBE) company. Similarly, the
pine timbers were carefully lifted down to the surface, and a crew
of a newly founded MBE company prepared them for shipment. Most
of this planking went to The Joinery Company of Tarboro, NC, where
it was sold for use in various projects, such as the restoration
of a 16th century tavern in historical Williamsburg,
VA.
"There were other
unusual wrinkles on this project," Moore recalls. "For
example, we had to individually remove 37,000 fluorescent-light
ballasts and dispose of them separately since they contained PCB.
And we discovered that the foundations were made primarily of brick
with a little concrete binding, so we dug out and salvaged these
brick, too, before filling and grading the site."
The cleared site made
room for the Homan Square Project, an affordable-housing development
of 600 new apartments, townhouses, and single-family homes. Setting
off the project as a landmark was the 14-story clock tower. Brandenburg
had literally dismantled the building around the 50-ft. square clock
tower. Crews bricked up the fire doors that had connected the tower
to the warehouse and added a new skin around it.
"This project involved
every aspect of our business," Moore says. "Large-scale
engineering, efficient yet safe operations, environmental issues,
political considerations, national and international marketing,
recycling, complete salvage, historic landmarks, minority business
enterprises." But today these are considerations that every
demolition and dismantling contractor needs to be prepared to deal
with.
Northwest
Motor Inn
 |
| Wrecking
in progress |
The Northwest Motor Inn
was a more modest project, but it illustrates how professional demolition
contractors develop and adapt equipment and techniques to meet the
unique conditions and problems of individual sites. The low-budget
project entailed dismantling a 30,000-ft.2, single-story,
L-shape hotel built on a concrete slab with face brick. One of the
principal requirements was to salvage intact 900 roofing-system
wood rafters, each made up of planks that were 2 ft. thick, 10 ft.
wide, and 20 ft. long on 1-ft. centers, for reuse by the new owner
of the site.
The contractor, CornerStone
Material Recovery of Richmond, IL, performs demolition and demolition-debris
removal and hauling for builders and developers. To perform these
varied tasks, the company has adapted standard equipment, adding
cranes to its 30-yd.3, open-top hauling trucks. According
to CornerStones Steve Clements, these hybrid trucks are ideal
for cost-effective demolition and source separating of recoverable
materials on small jobs and for hauling the debris from project
sites.
"For the Northwest
Motor Inn project, we used these vehicles for the dismantling of
the rafters," he says. "With the cranes bucket,
we literally pinched off several of those 12-in.-on-center rafters
at a time and brought them down into the truck, and then stored
them for reuse. It kept our labor costs low and enabled us to salvage
every one of those rafters."
CornerStone was named
Illinois Recycler of the Year in 1994, and it lived up to that reputation
on the Northwest Motor Inn project. According to Clements, all of
the inns metal I-beams were either sold on-site or recovered
for later use. Even the signposts and sign panels from the old hotel
were sold, and the old-hotel windows were taken to the contractors
warehouse for reuse. Moreover, air conditioners as well as soffit
and face brick from around the windows were recovered, and all the
swimming pool water-filter tanks and embedded piping were sold for
scrap value.
"We recycled 90%
of the demolished building," Clements says. "We knocked
down and broke up the concrete block partitions and broke up the
concrete slab, footings, and sidewalks at the site. We then took
all this concrete debris to a local concrete crushing company, and
they crushed it and also salvaged the rebar. We have a reputation
of being able to recover materials no one else here can. This keeps
escalating landfill fees to a minimum, and that means more stable
disposal costs."
Metropolitan
Airport Parking Ramp
 |
 |
| This
excavator with universal processor is shown breaking foundation
walls. |
Carl Bolander & Sons
was able to achieve an even higher recycling percentage at its Metropolitan
Airports Commission parking-ramp project in MinneapolisSt.
Paul. The project required the removal of a one-level parking ramp
to make room for a multilevel parking structure at the expanding
airport. According to Bolander Project Manager Larry Langer, the
structure was a 320,000-ft.2 precast concrete building
with double "T" beams, columns, and spandrels.
"Using an American
999 crane, we dismantled the parking ramp using the same process
with which it was constructed," Langer says. "We disassembled
each of the ramps double-T sections, each of which was 60
feet by 10 feet and weighed approximately 29 tons. We then transported
the sections to a storage site for reassembly. We had originally
thought that we would truck them directly to the new site 5 miles
away, where they were to be erected immediately by the developer
of a new warehouse/office building there. Unfortunately, the new
owners permit was delayed so we couldnt achieve the
seamless project wed hoped for. However, theyll be moved
from the storage site and reerected this summer instead.
"Using Cat 966 loaders
with buckets, we also removed and recycled 200,000 square feet of
bituminous material that had been below the ramp. We took this material,
as well as concrete foundations and any damaged concrete pieces,
to our crushing site. Well use it for road base on our construction
projects. Companies throughout the Twin Cities metropolitan area
bring their concrete demolition wastes to our crushing facility
for processing into Class 5 or Class 6 aggregate base for road building.
We process as much as 200,000 tons of material each year. Very little
if any concrete gets landfilled up here."
River
Center Arena
Veit & Company might
well have been one of those companies using Bolanders crushing
service, but the Rogers, MN, company does so much demolition work
that it, too, has its own concrete crushing facility, as well as
four construction and demolition (C&D) landfills. Recently,
Veit needed much of its total capability when it performed the demolition
and excavation work for the arena for the new NFL team, the Minnesota
Wild. The work included the demolition of the St. Paul River Center
Arena, more than 40,000 yd.3 of overburden excavation,
110 yd.3 of rock excavation, and the structural excavation
and backfill for the new Wild Arena.
"The demolition
project was tricky," recalls Don Rachel of Veit. "The
arena was a circular building 440 feet in diameter. Forty-eight
220-foot trusses, each weighing 20 tons, radiated out to the perimeter
from the center ring apparatus. The height of each truss was 3 feet
at the perimeter, increasing to 40 feet at the center. Whats
more, the steel all had to be lowered to the ground. We had to dismantle
the roof structure without any trusses or center ring apparatus
free-falling.
"We knew that as
soon as we removed one truss the whole roof system would be out
of balance and might well collapse. To prevent this, we designed
and constructed an eight-leg, 63-foot-high shoring-tower system
designed to carry a load of about 3.5 million pounds. The shoring
towers base plates were screwed into the arena floor to preclude
any uplift potential and carry the weight of the roof truss system
throughout the demolition. Then, one by one, we cut each 220-foot
truss free and, using a 318 Link-Belt 80-ton crane, lowered it to
the arena floor. There, we cut the trusses into manageable pieces,
using a Cat 375 excavator with an MSD 50R LaBounty shear attachment,
and trucked them away for scrap recovery. In all, we recycled 2,000
tons of steel."
Once the trusses were
removed, Veit lowered the 48 40-ton, 100-ft.-high concrete columns
to the ground and pulverized them using a Caterpillar excavator
with a concrete-pulverizer attachment. This concrete, plus the concrete
seating, amounted to 36,000 tons of concrete that Veit processed
at its crushing facility and will use as road base on construction
projects. In addition, the 40,000 yd.3 of soil and 110,000
of rock that were excavated were also recycled. (The rock had to
be jackhammered out and then crushed by Cat 350s with MPK hammer
attachments. The crushed rock was then used for backfill and road
base.)
"This job certainly
didnt tax our C&D landfill capacity," Rachel observes.
"From this entire demolition and excavation project, only 1,100
tons of C&D were brought to our landfill."
Fort
Vancouver Plywood Mill
Northwest Demolition
and Dismantling of Wilsonville, OR, took on the dismantling and
recovery of materials from the 300,000-ft.2 Fort Vancouver
plywood mill in downtown Vancouver, WA. In a sense, working in that
busy urban location was an advantage, contends Northwests
Project Manager Richard Wayper, because the dismantled materials
could be trucked directly to local salvage and recycling sites without
a need to cut them up for efficient long-haul transportation.
"There was a huge
amount of dimensional lumber300,000 board feet, in factwith
good commercial value," Wayper recalls. Therefore, we dismantled
the trusses very carefully, one bay at a time, using Komatsu 400
excavators equipped with grapple and shear attachments. These were
backed up by Komatsu 220 wheeled excavators to sort and position
the dismantled materials in a staging area. There, our crews manually
denailed the lumber, cut it to commercial size, and banded it. Then
we sold it to several different local lumberyards.
"We also pulled
up all the foundations and the basement slab and crushed the concrete
on-site using our Eagle Horizontal Impact Crusher. Since that machine
can crush 1,000 tons of concrete a day, we were easily able to crush
the projects 30,000 tons of concrete into 2-inch-minus aggregate
and leave it in piles on-site for use as a structural base when
the site was redeveloped. This savings in transportation to and
from a remote crushing facility saved the owners a considerable
amount of money. All in all, we were able to recycle 98.43% of the
total materials [by weight] that we demolished and dismantled. Only
588 tons of the 37,477 total tons had to be landfilled."
With this project under
its belt, Northwest took on the demolition and dismantling of another
plywood mill, a Potlatch mill in a remote area of Washington at
a 4,000-ft. elevation. This time, however, the conditions were quite
different. Not only were there no nearby markets for recyclables,
but the scope of the job was greater. This time, Northwests
contract called for it to also sell, recycle, or otherwise distribute
a substantial amount of manufacturing equipment before the actual
demolition could begin. The company did indeed sell much of the
equipment to buyers throughout the nation. It removed the balance
of the equipment from the building, cut it up into 4-ft. pieces
for ease of long-haul transportation, loaded the pieces (using magnets)
into railroad cars, and shipped them to salvage companies located
in urban areas.
"What remained was
a 300,000-square-foot wooden building," Wayper says, "but
this time the building wasnt made of readily salable dimensional
lumber, it was constructed of manmade gluelam timber. And the commercial
value of these did not justify the extensive labor that would be
needed to recycle them for use as construction wood. Instead, the
company decided to grind this wood on-site into hog fuel and ship
it via rail or truck to companies that need fuel for their boilers."
As far as the concrete
slab is concerned, Northwest is leaving it intact since the site
will be reused as a log yard. Thus, neither of the two plywood-mill
demolition projects will generate significant waste that must be
landfilled, despite their wide differences of scope, transportation,
and site reuse.
Differences such as these
are not too unusual. There are rarely any two demolition projects
that have the same conditions and hence the same demolition solutions.
According to the NADC, the professional demolition contractor assesses
each project with a comprehensive series of site evaluations to
determine the unique conditions of that site. "Typical prebid
steps include a structural engineering evaluation, which identifies
optional methods for [and hazards associated with] taking the structure
and its components apart efficiently and safely; a utility survey
that identifies connections requiring termination and specifies
services needed during the project; a hazardous-materials survey,
which identifies materials necessitating special handling and worker
training; a safety analysis that incorporates both the structural
and hazard information into a preliminary safety plan for the job,
specifying additional equipment, training, and materials handling
that will be necessary; and a top-to-bottom salvage evaluation that
provides estimates of the marketable value of recoverable materials
[for reuse or for recycling]a step integral to minimizing
the net costs for all projects."
Armed with this information,
the contractor is in a position to do the most cost-effective demolition
possible. As a result, the industry has been able to safely dismantle
and demolish many different types of structures, achieve high recycling
and reuse results that both generate revenues and avoid landfill
costs, and do all this at a net cost that is generally less than
2% of the replacement cost of the structure.
Guest
author Charles D. Bader is with Dateline II Communications in Los
Angeles, CA.
|
|