|
Beers Construction Company
has a long history of adopting innovative construction techniques
and management practices, so when it first heard of Georgias
stormwater permit law, to become effective in the summer of 2000,
it adopted an aggressive implementation strategy. When the new permit
took effect on August 1, 2000, the Beers team was determined to
be not only ready, but at the forefront of compliance in Georgias
construction community.
From the outset, developing
and implementing a compliance plan presented a tremendous challenge.
Georgias new General Storm Water Permit mandates the most
stringent guidelines in the United States for stormwater runoff
from construction sites. Designed to reduce turbidity (the level
of suspended solids that makes water look muddy), the permit holds
general contractors, owners, and developers jointly responsible
for compliance with the law. The law requires that all sites disturbing
5 ac. or more of soil have best management practices (BMPs) in place
and that they be properly designed, installed, and maintained. Projects
found out of compliance can be fined and/or shut down.
Beers first step
in developing a plan for compliance with the new law was to have
executives, senior managers, and legal consultants closely read
both the permit and the law. While the documents were being reviewed,
Geoff Bewleythen a manager in Beers Environmental Departmentand
I, Bob Provan, assessed the full scope of the task before us.
 |
| Silt-Saver
is a one-man installation job and reduces the turbidity by about
1,000 NTUs compared to silt fence. |
We determined that there
were 25 Beers projects in the state of Georgia falling under the
provisions of the new permit: They met the criteria of disturbing
5 ac. or more of land. The projects were as diverse as the terrain
in which they were situated, ranging from a sprawling 160-ac. wastewater
treatment plant site on the outskirts of Atlanta to a school in
the heart of the Blue Ridge Mountains.
After determining which
sites were affected by the law, we began the process of determining
what we would have to do to bring each site into compliance. Georgias
new permit is written around the design criteria of a 25-year rain
event, which correlates to 6.75 in. of rain falling in a 24-hour
period. Permittees are in compliance as long as their construction
sites BMPs have been designed by a competent state-registered
engineer, have been properly installed, and are being diligently
maintained.
Particularly challenging
to us was the fact that there are no data to confirm that the desired
nephelometric turbidity units (NTUs) can be met on a job-site level.
The permit allows the addition of 25 NTUs to a state warm-water
fisherys background readings and 10 NTUs to a state cold-water
trout fisherys background readings. For example, water leaving
a job site near a state trout fishery can only raise the background
turbidity level in the stream 10 NTUsroughly the equivalent
of pouring bottled water into the same stream.
 |
| Coffer
dam at a water treatment plant project |
 |
| Effluent
pumped from the coffer dam into the sand filter and small stone
energy dissipater berm at the edge of the filter |
We soon learned that
another difficult aspect of the new permit to qualify was the Memorandums
of Agreement (MOAs). MOAs give a municipality or a local government
the option of letting its own job-site runoff guidelines, provided
that those guidelines are at least as strict as the state guidelines
and that the local government proves to the states Environmental
Protection Division (EPD) that it can enforce and document violations.
We enrolled in what was
then the State of Georgias only sanctioned class to qualify
us as competent persons as mandated by the new permit/law.
By the end of the two-day class, it was apparent that a number of
Beers team members would have to qualify as competent persons in
order for Beers to meet its goal of unequivocal code compliance.
At that time, however,
no training class large enough to handle the number of people we
needed to train was available anywhere in Georgia. We worked with
Jim Spotts, a state-approved consultant, to set up our own monthly
Competent Person Training Classes. We advertised the class internally
through mini-presentations at our 2000 Superintendents Retreat and
other company functions. To date, more than 175 Beerss project
managers, superintendents, engineers, and estimators have attended
these classes.
To supplement in-class
training, Bewley developed a Field Manual for Erosion Control
and NPDES for Project Managers, Superintendents and Project Engineers.
The manual provides all the necessary forms and permits, instructions
on how to complete and submit them, and a color-coded erosion control
procedures sheet that is time-sequenced from the initial Notice
of Intent (NOI) to the Notice of Termination.
We received approval
from Beers CEO Joe Riedel and COO Dwight Morgan to establish
an in-house Erosion Control Committee with representatives from
each Beers group doing work in the state of Georgia. The committees
mission was to distribute information on our procedures and evolving
corporate policy to the 25 projects initially affected, as well
as new project startups after August 1, 2001.
The committee meets monthly
and has proven to be tremendously beneficial, particularly in the
early stages. In addition to dispersing information, the committee
has established and maintains a database of BMPs. We have tested
and kept records on numerous state-of-the-art BMP products, including
(but not limited to) polyacrylamides, tackifiers, geotextile fabrics,
and various seed blends. Our database gives us the resources to
overcome any erosion control problem that might arise at our sites
in Georgia and other states.
 |
| Slopes
before test application of Soil Guard |
By August 2001, a competent
person had been trained for each of our 25 sites and each site had
submitted an NOI. That month was hectic, particularly since the
permit was as new to government officials as it was to us. Bewley
regularly monitored the initial 25 sites to ensure that they were
compliant with the new law and to troubleshoot sites where erosion
control was particularly challenging. Our preparation paid off:
We have yet to be shut down or fined. In fact, we recently procured
a contract based on our superlative erosion control policy/programs.
Since the implementation
of the new erosion control law, we have continued to monitor affected
sites to check in-place BMPs and assist in developing erosion control
measures for sites with difficult terrain or close proximity to
wetlands. We also continue to evaluate and test new erosion control
products and methods. A few of these have proven particularly effective
on our job sites and are worth mentioning.
Mat Inc.s Soil
Guard, tested at the Rockdale County Water Treatment Plant and Bear
Creek Water Treatment Plant, has greatly reduced erosion in mass
excavations. Soil Guard can be used with or without seed in a hydroapplication
and goes down thin enough to not affect backfill compaction around
concrete walls. It also eliminates mud and silt cleanup around concrete
formwork. Soil Guard germinates seed very well and does not break
the surface tension of hydroseed applications.
We also have used polyacrylamide
at numerous sites with great results. Currently we are testing
it in conjunction with multiple erosion control materials and methods.
To date, all tests are very promising.
 |
| Test
application of Soil Guard without seed around slopes |
 |
| Slopes
after 1.5-in. rainfall event in 24 hours. Broken areas are from
equipment operator moving materials across slope areas. |
Silt-Saver saves time
and money because it requires only one person for installation.
We install Silt-Saver over stormwater drop inlets, and it greatly
reduces the NTUs passing through the device, as compared to silt
fencing. Silt-Savers design is very strong, supporting mud
all the way up to the top of the device.
We are currently testing
about 15 other products and methods. To support our field implementation
program, Beers remains proactive in keeping up with erosion control
regulations. Beers currently represents "big construction"
on the Georgia Governors Storm Water Advisory Committee. This
20-member committee meets monthly and is made up of a wide range
of community and business representatives. Members are charged with
drafting recommendations for the new permit/law that is slated to
take effect on August 1, 2003, and will apply to all construction
sites disturbing 1ac. or more of soil.
This committee also is
charged with the review and evaluation of General NPDES Permit No.
GAR 100000 for the discharge of stormwater associated with construction
activity. Committee members evaluate alternatives, taking into account
current construction practices. Our committees recommendations
are submitted to the director of Georgias EPD.
The Governors Storm
Water Advisory Committee is chaired by Bob Kerr, director of the
Pollution Prevention Assistance Division of Georgias Department
of Natural Resources. He also serves as the State of Georgias
senior representative in the "Water Wars" negotiations
between South Carolina, Georgia, Alabama, and Florida over state
water rights/ownership. His many years of experience in successfully
dealing with complex matters serve him well as he chairs the diverse
social cross-section making up the Governors Storm Water Advisory
Committee.
Both Beers and Skanskaour
parent companywelcome Georgias new stormwater runoff
guidelines. Because commitment to initiatives that protect our environment
is an integral part of our corporate culture, we are proactive in
addressing such issues as the supply of available drinking water.
We understand that as worldwide populations soar and population
centers shift, we all must take steps to safeguard and improve our
environment. This permit and any successors are a step in the right
direction.
Similar to many other
states, Georgia is seeing the financial impact of substandard water.
The expense of dredging reservoirs that have lost capacity as a
result of silt deposits is paid through tax dollars. Municipal water
treatment plants must charge customers for the increased chemicals
and electricity necessary for water treatment when influent raw
water has high turbidity levels.
Additionally, recreational
sport-fishing is a major industry in Georgia. State waterways that
cannot support fish do not draw fishermen, not only reducing revenues
from fishing licenses butmore importantlyreducing revenues
for the small businesses that serve the fishing industry: motels,
campgrounds, stores, restaurants, and bait and tackle shops located
near once-productive fishing spots.
From the construction
industrys perspective, the new law helps address the publics
perception of constructions negative impact on the environment.
Although most silt enters state waterways through such nonconstruction
means as logging operations, farming, and major rain/wind storms,
the public often attributes silt to nearby construction sites.
In Georgia, a long-standing
drought has increased stormwater runoff. Vegetation has died on
streambanks and lakeshores and is no longer able to help prevent
erosion, resulting in significantly increased levels of soil-laden
runoff flowing into state waterways.
The new law affords construction
firms an opportunity to protect themselves through documentation
of background turbidity levels in state waterways adjacent to our
projects. By documenting fluctuating background turbidity levels,
construction companies help fulfill the intent of the new permit/law
by tracking "true data."
Our analysis shows that,
in the long run, proper erosion control saves construction projects
money. Unchecked erosion washes out project access roads. Not only
do the roads have to be reestablished, but productivity is reduced
when accessibility is reduced. Unprotected manholes can fill up
with silt, as can associated piping. Storm drains and their associated
piping have the same problem. These scenarios necessitate the labor-intensive
removal of soil and the costly high-pressure water jetting of piping
systems.
Unchecked erosion also
fills riprap channels with silt and reduces the storage capacity
of detention ponds via sediment deposits. On larger projects, mud-covered
material lay-down areas can cause project teams to reorder material
that is no longer "readily visible."
The bottom line and corporate
social responsibility are not mutually exclusive. Ultimately we
all share stewardship of the environment. Beers understands the
importance of this commitment and has incorporated it into its corporate
culture.
Geoff Bewley is an
environmental manager and Bob Provan is a group vice president with
Beers Skanskas Heavy Civil Group. Both co-chair Beers Skanskas
in-house Erosion Control Committee and are members of the Governors
Storm Water Advisory Committee. Maggie Tripp is a technical writer
for Beers Construction.
|