 |


You can run
into any number of hardships with trenching projectssteep
grades, groundwater, or unstable soil, to name just a few. But simply
put, it's not that difficult to practice proper trench safety.
By Dan Brown
Some contractors don't
use safe trenching procedures despite the fact that it's not
tough to do. Not only do they endanger their employees, they risk
high fines from OSHA. "I know of one contractor who got fined
in the $70,000 neighborhood because he was a repeat offender,"
relates Tim Scully, president of the Underground Contractors Association
of Illinois. "All it would have taken to comply with OSHA regulations
is a trench box or sloping trench walls."
And OSHA is in no mood
for leniency these days. "In most cases, if you don't
have a protective system, OSHA will probably issue a citation for
a willful violation, and the fines can range up to $70,000,"
points out George Kennedy, vice president of safety for the National
Utility Contractors Association (NUCA). And, he adds, the states
of Arizona and Michigan are seeking to apply criminal penalties
to serious violations of trench safety regulations.
OSHA's rules for trench
safety are relatively straightforward. You can find a complete listing
of them at www.osha.gov
(look under CConstruction Standards, 1926 Subpart PExcavations).
The following are a few of the basics:
- The contractor must
designate a competent person to assess the excavation and determine
that it is safe for project personnel to enter and work. That
person must have the authority to tell workers to get out of the
trench if unsafe conditions develop.
- In most states the
contractor must provide a protective system, such as a trench
shield, for a trench that is more than 5 ft. deep. In some states
the limit is 4 ft.
- Prior to digging,
the contractor shall locate and identify all underground utilities,
such as sewer, telephone, fuel, electric, and water lines, that
might be encountered during excavation.
- The bottom of the
shielding system cannot be positioned more than 2 ft. above the
bottom of the excavation.
- The removed soil shall
not be stockpiled closer than 2 ft. from the excavation's
edge.
- No workers shall enter
or work in excavations where standing water is visible, unless
adequate protection is used.
Dewatering in Oak
Lawn
 |
| The
excavator on the Oak Lawn project pulls ahead stacked boxes.
|
 |
| Using
a Komatsu excavator, Glenbrook places nine 20-ft. lengths of
pipe per day on the Oak lawn project. |
In fact, groundwater
and running sand are the main problems posed by an 8,000-ft.-long
water-main project for Oak Lawn, IL, says Terry Barnett. He is president
of the project's excavation contractor, Glenbrook Excavating &
Concrete Inc. Last spring, Glenbrook began digging a 12- to 17-ft.-deep
trench and placing a 54-in. water main on the project.
To cope with the groundwater
and help make the project safe, Glenbrook is digging dewatering
wells. At locations 10-15 ft. to the side of where the trench will
pass, the contractor digs a small hole down about 18 ft., places
a 12-in.-diameter slotted pipe in the hole, and backfills it with
0.75-in. washed rock. "Then we put a pump inside the pipe and
begin dewatering," explains Barnett. "We have put in five
wells; we leave them in place until we pass them with the pipe-laying
operation."
To ensure worker safety
in the trench, Glenbrook is using two stacked trench boxes. The
bottom unit is an 8-ft.-high x 24-ft.-long Pro-Tec box; attached
on top is a 4-ft.-high x 24-ft.-long trench box from Efficiency
Production Inc. "That gives us 12 feet of box," notes
Barnett.
Because the trench runs
down the middle of a residential street, Glenbrook has to work around
any number of utilities. "We've got gas lines, water,
poweryou name it, we've got it," says Barnett. To
deal with the utilities, "We can take the 4-foot box off, duck
under some utilities, and still keep a safe trench."
Digging with a Komatsu
PC600, purchased new in 2000, the contractor places some 180 ft.
of pipe per 10-hour shift. That means laying nine 20-ft. lengths
of prestressed concrete cylinder pipe per day. The Komatsu is sized
well for the job, Barnett remarks. "A big part of success on
this project is having an excavator that's big enough to pull
the double-stacked trench box. Lifting a 22,000-pound piece of pipe
is nothing compared to the force it takes to pull those boxes in
bad ground.
"Another big key
to being safe is that our crews have worked together for years,"
he observes. "Each man knows what the other is thinking. So
they work as a unit, and they're efficient and safe at the
same time." In bad ground, he says it's important to have
a good safe trench. "That way you can set pipe as quickly as
possible and work yourself out of the bad ground as quickly as possible."
As an added safety measure,
Glenbrook sometimes uses large steel plates that are inserted between
the trench wall and the trench box. "We'll drop the plates
alongside the box to increase the protection area," says Barnett.
"OSHA accepts the plates. They've inspected us and never
said anything about the plates. We use them if we're working
especially close to traffic or if the semi-trucks have to get close
to the hole. We'll use plates to supplement the trench boxes
but not to substitute for them."
Safety at Boston's
"Big Dig"
 |
| Speed
Shore's Waler System provides sidewall stabilization for formwork
installation. |
 |
| Double
Wall Trench Shields (stacked) used on large-diamenter pipe installation |
A number of safety challenges
were presented in building the Leverett Circle highway connectors,
a Central Artery/Tunnel project in Boston, MA. As the prime contractor
on the project, Modern Continental Construction was faced with building
two below-grade highway connectors under 10 Amtrak train tracks
as the tracks entered Boston's North Station. For the 400-ft.-long
twin connectors discussed here, the contractor used the "roof
first" construction method.
During construction,
Modern Continental was allowed to shut down only two train tracks
at oncethe other eight had to remain open to trains. So construction
proceeded sequentially across the tracks, with only one pair of
tracks closed at a time. The first step was to place two pairs of
concrete walls using the slurry wall method. A clamshell excavator
dug out the walls while heavy slurry filled the excavation and maintained
the trench walls. The walls extended 60-100 ft. deepdown to
bedrock. Once the slurry wall excavation was complete, the contractor
placed soldier piles, spaced at 4-ft. intervals, into the excavation.
Concrete was then tremied into the excavation from the bottom up,
and the displaced slurry was reclaimed for future use.
The walls of each pair
were spread about 35 ft. apart; the entire "roof first"
section of twin tunnels was about 400 ft. long, reports Ed LaVallee,
area safety manager for Modern Continental.
Next the contractor excavated
a shallow sectionabout 8 ft. deepbetween each pair of
concrete walls. That made space for construction of the roof. It
was built by first placing steel girders that spanned the area between
the soldier piles in the concrete walls. With the addition of steel
pan decking, reinforcing steel, and a concrete topping, the roof
was complete. The roof was then backfilled and the tracks were restored
to service.
That made the walls and
roof ready for excavation below. To permit access to the excavation,
Modern Continental left three large openings in the roof, called
"glory holes." Following the initial excavation of the
glory-hole area, a Gradall 5200 excavator was lowered into one glory
hole and began digging out the material below the roof and stockpiling
it at the base of the glory hole. A clamshell excavator then removed
the stockpiled material from the glory hole.
 |
The first step in excavation,
recalls LaVallee, was to take the excavation floor down to about
15 ft. below the roof. The contractor was careful to maintain proper
sloping within the excavation, because survey crews and support
personnel had to work in the area. At a point 15 ft. below the roof,
the contractor installed wide steel walers that ran along the concrete
walls. For additional wall support, 48-in.-diameter pipe struts
were placed to span the area between the walers on each wall. Spaced
at 20-ft. intervals, the big pipe struts acted as bracing to support
the walls. "That was the support of excavation as designed,"
LaVallee says.
Again, the excavation
process was repeated; the contractor took the tunnel floor down
another 20-25 ft. below the pipe struts. Modern Continental's
last major steps in the connector construction were to pour 8- to
16-ft.-thick concrete floors and to close the glory holes.
Such an undertaking required
a number of safety measures, including:
- All personnel involved
underwent comprehensive safety training.
- Lighting, communication
equipment, and ventilation fans were mounted under the roof.
- The wall-mounted walers
were used as walkways. The contractor installed handrails along
the 3-ft.-wide walers.
- Ladders and/or stair
towers were positioned at each glory hole. The holes were located
so that no worker was ever more than 100 ft. away from an exit.
"If an evacuation was necessary, we had a designated muster
point above the ground," says LaVallee.
- A five-gas meter was
used to monitor air quality for oxygen content; gases at the lower
explosive limit, such as methane; carbon monoxide; nitrogen dioxide;
and carbon dioxide.
- Electric air horns
were mounted below the roof, with toggle switches at the top and
bottom of each stairway. One blast from the air horn signaled
that a load was suspended overhead in the glory hole; three blasts
were the signal to evacuate the excavation.
- Each foreman was responsible
for knowing the locations of the workers on his crew and for taking
a head count at the muster point following an evacuation.
- With an electronic
accountability system, each employee carried a photo ID badge
with a chip embedded in it. Card readers located at every access/egress
point reported to a central monitoring station every time an employee
entered or exited the excavation. The name, time, and location
of access or egress were logged.
"If I entered the
excavation at one point and exited down the line at some other point,
the electronic system would be able to track when and where I entered
and exited," explains LaVallee. "Fortunately, through
the successful implementation of our safety program, an evacuation
was not necessary, but we were prepared nonetheless." The Leverett
Circle connectors were completed safely and on time.
Rock Trenching on
the West Coast
 |
| Using
the Multi-Shore system in a deep excavation project |
Steep grades and hard
rock confronted PCL Civil Constructors on a 13,000-ft. water pipeline
project in the Rancho Santa Fe area of north San Diego County, CA.
Most of the pipe was 48 in. in diameter; the job also had some 36-in.
pipe and one 700-ft. section of 30-in. pipe, says Kevin Joe, PCL's
superintendent on the job. Construction began in June 2000 and was
completed by August 2001.
"It was all uphill
and downhill," describes Joe. "We had six severe downhill
slopes in excess of 40%. And we were limited to a 100-foot width
of right of way, so just getting physical access to the job on those
slopes presented quite a challenge."
Blasting the rock along
the trench alignment came first. That job went to Baxter Drilling,
a subcontractor to PCL. Baxter blasted the granitic-type rock to
depths of 12-18 ft. across a width of 8-10 ft. "Then we moved
in with our Hitachi EX-750 to excavate the trench," says Joe.
PCL could not work from
uphill downward to place the pipe; the force of gravity would pull
apart the joints. And the contractor couldn't work from downhill
up by excavating and placing pipe at the same time because loose
rock would roll downhill onto the workers setting pipe. The answer:
excavate the trench working from uphill downward for the entire
slope, then place pipe working the other wayfrom downhill
upward.
"We excavated to
1 foot below the design invert elevation," recalls Joe. The
invert elevation was 10-16 ft. below grade. There was no need for
trench boxes. "We were able to scale it back to competent rock
on both sides." The contractor sloped the trench sides back
on a 0.5:1 ratio, leaving a flat, 6- to 8-ft.-wide trench floor.
"In some areas it was dirt, and we sloped it back on a one-to-one
ratio."
At 40-ft. intervals,
the Hitachi dug out holes for the pipe's bell joints. "We
had to backfill to within 1 foot of the top of pipe with imported
sand," says Joe. "For the rest of the backfill we crushed
the shot rock to 6-inch-minus."
To safely haul the 40-ft.-long
pipe joints, PCL used a 35-ton Volvo rock truck pulling a specially
made trailer. According to Joe, the homemade trailer basically consisted
of a couple of truck axles and a long H-beam welded together. The
contractor would load the rock truck box with bedding sand and place
one 40-ft. pipe joint on the trailer, then head for the job site.
"A regular highway truck couldn't handle the steep slopes,"
remarks Joe.
Whether you're trenching
in rock or digging in wet, sandy soil, achieving a safe job site
takes careful planning, say the contractors interviewed for this
article. And careful planning not only will produce a safe job siteit
will bring more money to your bottom line.
Frequent contributor
Dan Brown is the owner of TechniComm, a communications business
based in Des Plaines, IL.
|
|