|
What is the most important
best management practice (BMP) needed on a construction site to
ensure minimal discharge of sediment during runoff events? Is it
strategically placing barriers to block the path of runoff? Or should
sediment containment systems be placed to intercept runoff? How
about implementing erosion control practices?
Actually, it is none
of the above. It's communication!
Communication is such
a simple and inexpensive BMP. But with whom should communication
be implemented? Should it be with the project manager, who is simply
following a set of plans? Maybe better communication with the designer
is needed? But isn't the designer simply following rules and
regulations set forth by a regulatory agency? If those rules and
regulations are flawed, shouldn't this problem be communicated
to the regulators? Finally, don't forget about the inspector,
who is supposed to be well informed about erosion and sediment control
(ESC) plans and knowledgeable about BMPs. What happens when inspectors
don't know everything about the plans and have limited knowledge
about ESC?
 |
The above discussion
suggests that a hierarchy of communication to ensure effective ESC
on a construction site is not a one-way street. Figure 1 illustrates
the interdependency of individuals and/or agencies if the goals
set forth in the Clear Water Act (CWA) and EPA requirements are
to be met. Notice there is no one group of individuals or agencies
accountable for effective ESC. Instead, everybody must be responsible
and be able to communicate with each other. Essentially, interaction
among all of those working on a construction project must occur.
Regulatory Agencies
What is the role of regulatory
agencies? Few would argue that they must enforce the environmental
laws of the United States. However, enforcement must be done in
a manner that is realistic, achievable, and consistent. This can
only be accomplished by regulatory agencies continually communicating
with all impacted parties. At the same time, it is equally important
that designers and inspectors provide feedback to regulatory agencies
so that their policies remain effective and realistic.
Political Backing.
Regulatory agencies must have the political resolve to enforce the
law of the land. This is the role of the Environmental Protection
Agency (EPA), and it has the backing of the US government. Unfortunately,
local regulatory agencies do not have the luxury of such support.
Instead they must obtain local political supporta task that
is not always easy to achieve. Thus, effective communication (sometimes
known as marketing) is needed to ensure political support if reduction
in runoff-water sediment from construction sites is to become a
reality.
Requirements.
Once political backing is ensured, regulatory agencies must clearly
communicate their requirements to designers, contractors, and inspectors.
Clearly defining requirements for drawings, identifying acceptable
BMPs and recognizing their limitations, discussing timing issues
for installing BMPs, and allowing for innovation must be the norm.
"Cookbook" submittals should be avoided since they stifle
innovative methods and can cause ESC to be a sham.
Review Process.
Regulatory agencies must clearly communicate submittal requirements
and let the applicant know how and when plans will be reviewed and
processed. Review processes that exceed 30 days should not be tolerated.
Also, if a regulatory agency requires professionals to develop ESC
plans, then similarly qualified people must review the plans. Any
other action communicates the impression that qualified people are
not necessary to oversee National Pollutant Discharge Elimination
System permit requirements.
Identify Penalties.
In an ideal world, everybody would try to protect the environment.
Reality dictates that the possibility of penalties is required if
compliance is to be achieved. Doing nothing gives the impression
that regulatory agencies are not serious about protecting the environment.
A lack of action is construed as doing business as usual and does
little to protect the environment while construction activities
occur. Small hand-slapping fines will be ignored! Work stoppages,
however, catch everybody's attention.
Designers
Often, regulatory requirements
mandate that designers of ESC be professional engineers. This requirement
puts engineers having minimal ESC skills in a compromising position
since professional ethics might prevent them from attesting that
they have designed a plan. Fortunately, regulatory agencies (e.g.,
EPA), states, counties, and cities are overcoming this problem by
recognizing that a Certified Professional in Erosion and Sediment
Control has the expertise and skills to ensure development of effective
plans (see www.cpesc.org
for more information).
Designers have the difficult
task of interpreting regulatory requirements, satisfying demands
of the client, and developing plans that contractors can implement
in a cost-effective manner. Effective ESC on construction sites
requires designers to be properly trained and have extensive experience.
This means that designers have to be cognizant of hydrology, engineering,
drainage issues, ESC BMPs, agronomy, geology, soil science, and
politics and (perhaps most important) possess common sense.
Identify the Needs.
Designers must understand what is required to reduce sediment from
runoff waters and how to minimize erosion while construction activities
occur. They need to assess how construction might impact critical
areas such as wetlands, streams, and ponds. Also, designers need
to maintain communication with regulatory agencies and contractors
to ensure their needs and requirements are being met.
Understand What
Is Needed. Designers must complete site visits before, during,
and after construction activities occur. Preconstruction site visits
help designers identify critical habitats, observe existing vegetation,
develop a feel for the site, and identify potential problems. By
completing site inspections during construction activities, designers
can learn about problems that contractors and inspectors experience
daily. Also, designers need to complete postconstruction site visits
to assess whether erosion control measures are minimizing downstream
discharges of sediment. In summary, designers must inspect all aspects
of their work if they are to become competent in ESC.
Develop Plans for
Contractors. Plans are a "first appraisal" of
what needs to be completed on a construction site. As such, they
must change if effective protection of the environment is to occur.
Thus, ESC plans must be developed for the contractor. This requires
designers to communicate what is required for preconstruction, construction,
and postconstruction activities. Plans must have numerous notes
on each page, adequate contour lines, identification of BMPs, and
clear instructions as to when something is to be completed. Designers
must avoid "cookbook" solutions that result in exactly
the same template for every submittal. Finally, designers should
never assume contractors know everything about controlling sediment
and erosion while construction activities occur. They don't!
Get Involved.
Designers have to be involved with all aspects of ESC. Communication
with the client, contractor, inspectors, regulatory agencies, and
(if needed) the general public is a must. As a minimum, biweekly
meetings with all parties must occur. During these meetings, frank
discussion about the ESC plan has to occur. Are some of the BMPs
not practical? Should there be modifications to the plan? Why is
noncompliance occurring? What can be done to improve the current
situation? Only by asking these, and similar, questions will designers
learn what is happening on the construction site.
Contractors
Contractors make or break
an ESC plan developed by designers. If the plan is confusing, then
only minimal measures will be installed. However, when plans clearly
communicate what is needed, what is to be installed, and when installation
is to occur, effective ESC on a construction site will become a
reality.
Take the Plan Seriously.
Protecting the environment is a responsibility everybody must share.
Since construction activities can potentially disturb and expose
vast amounts of land, every effort must be taken to minimize sediment
leaving a site. Thus, contractors have to take ESC plans seriously.
The CWA mandates severe fines, and EPA is serious when it identifies
the contractor as being responsible for implementing the plan.
Install, Inspect,
and Maintain. Contractors can reduce ESC costs initially
by always installing BMPs correctly. Once installed, BMPs must be
continually inspected and maintained. In addition, noncompliance
issues are to be reported to the regulatory agency through an inspector
report. Don't forget: Those reports might have to be available
for review up to three years after completion of the project.
Educate.
When plans illustrating specific BMPs will not function as designed,
contractors must communicate to designers and inspectors. This means
contractors might have an obligation to (diplomatically) educate
designers and inspectors when changes or modifications are recommended.
Likewise, contractors must be ready to learn about new methods from
the designers and inspectors.
Inspectors
Pity the poor inspector!
In what other profession does one have to be a politician while
communicating with contractors, designers, and regulatory agencies
and at the same time be knowledgeable about all aspects of ESC?
Not an easy task for any one person.
Understand the
Plan. If inspectors do not understand construction plans,
then more than likely they will not know how to read ESC plans.
Plans are more than just symbols on a piece of paper. They are a
blueprint for contractors to follow. Thus, inspectors have to know
the implementation schedules, where and when BMPs are to be installed,
and what BMPs are to be maintained or eliminated, as well as fully
understand the limitations of BMPs.
Be Certified.
An inspector has to maintain communication with regulatory agencies,
designers, and contractors. As such, certification is needed to
demonstrate competency with issues related to ESC. Certification
also requires an individual to keep current on the many BMPs that
can be used on construction sites. Thus, continued education is
a must.
Know the Limitations.
An inspector might or might not be qualified to be a designer.
However, inspectors must know their limitations when modifications
and updates of an ESC plan are required. Thus, inspectors must maintain
communications with designers when major modifications are required.
Keep in mind that if an inspector completes major modifications
to a plan and designer approval is not obtained, then the municipality
might be liable for damage caused by the changes.
Communicate Concerns.
The contractor needs to be informed by the inspector of noncompliance
and violation issues. However, sufficient time must exist to allow
for repairs, installation of new BMPs, removal of structures, and
so forth. When it appears a plan is not workable or has obvious
problems, then the inspector must relay these observations to the
designer, contractor, and regulatory agency. Likewise, when regulations
prevent or hamper the implementation of effective ESC techniques,
inspectors must inform regulatory agencies of these problems. Lastly,
the inspector must insist on meeting weekly with the contractor
so that updates about construction activities are communicated.
Summary
Effective ESC on construction
sites requires continual communication among all parties associated
with the project. Whenever this simple and cost-effective BMP is
continually implemented, problems associated with ESC will be minimal.
However, ignoring the use of this straightforward BMP can lead to
excessive costs.
Jerald S. Fifield, Ph.D.,
CPESC, is president of HydroDynamics in Parker, CO, and author of
Field Manual on Sediment and Erosion Control Best Management
Practices for Contractors and Inspectors and Designing for
Effective Sediment and Erosion Control on Construction Sites,
both available at www.ForesterPress.com.
GEC
- November/December 2002
|