|

By Dan
Williamson
The $3.4 million
upgrade of the Glorietta Bay Pump Station in Coronado, CA,
initiated in January 2002, posed challenges similar to those
faced by municipalities trying to efficiently manage upgrades
to aging infrastructure nationwide. A difficult excavation
included in this project was helped along by technology new
to North America but long relied upon by European cities likewise
refurbishing crowded and aging public worksthe GME/ES
slide-rail system.
The Coronado project
involved building a brand-new pump station while the old one
remained on-line. This included a new gravity sewer and a
sewer force main, along with 2,000 ft. of sewer piping.
To do the job,
HPS Mechanical, the California-based general contractor, needed
to create a 30-ft.-deep excavation in extremely sandy soil,
extending below the water table and within a few feet of a
heavily used bicycle path. Whalers and sheet piling were considered,
but HPS Mechanical consulted with several specialty shoring
companies in hopes of finding a box strong enough to handle
the lateral forces at this depth. Allied Trench Shoring Service
& Traffic Control Service Inc. conceived the solution
in consultation with Griswold Machine Engineering (GME).
Scott Fox, HPS
mechanical superintendent, reports, Other shoring companies
we consulted could not guarantee that their box could handle
the requirements of an excavation so deep and in such difficult
soil conditions. We were readying to use sheet piling when
the shoring specialist at Allied Trench brought our attention
to this new type of slide rail from GME.
Aaron Zelt, shoring
specialist for Allied Trench explains, While sheet piling
and whalers could also do the job, it would have involved
considerably more cost. It only took HPS Mechanical three
days with a four-man crew to do the job. Conservatively speaking,
it would have taken the same crew two and a half weeks to
do the same job if they only had sheet-piling methods at their
disposal.
Fox adds that above
and beyond the savings in man-hours involved in the job, there
were considerably less rental costs involved. We were
quoted $55,000 for the sheets and whalers compared to $16,000
for the slide rail. Moreover, we were able to bypass hiring
a subcontractor to do the work, and instead HPS Mechanical
installed the slide rail and completed the excavation in just
three days. It was quick and easy and handled the requirements
of the lateral system with no problem.
According to Mike
Hayet, branch manager of Allied Trench, other California contractors
will be able to dramatically reduce their costs in those jobs
traditionally handled by sheet-piling methods. In fact,
for excavations with overhead obstacles, the unique pivot-to-place
configuration of the GME/ES slide rail makes it the only slide-rail
system that can work. It uses an open-track rail that allows
panels to be pivoted into place rather than the typically
cumbersome and unsafe method of threading panels into a closed
rail from above. While dramatic cost savings compel many to
try the design, it also is a significant boon to worker safety
because it can be installed at grade, eliminating precarious
situations involving ladders and attempts to handle heavy
slide rails in midair.
Dan Williamson
is slide rail specialist for Griswold Machine Engineering.
GEC - November/December 2003
|