|

By Greg
Northcutt
When American Backhoe
Co., of Omaha, NE, won the contract to excavate and install
a diesel fuel tank at a new hospital addition in Winnebago,
NE, it faced a job that challenged the company's typical approach
to this type of work.
The environmental
contracting firm specializes in hazardous-waste removal and
containment, tank installation, and removal and utility installations.
Still, it had never faced a project quite like this. Normally,
installing a fuel tank is a pretty straightforward job for
the company: Put in a sheet-piling system to prevent cave-ins.
Dig the pit. Set the tank in place. Then, remove the shielding
and backfill the excavation to finish the project.
In this case, the
job called for installing a 15,000-gallon fiberglass tank
to power backup generators as part of a US Army Corps of Engineers
project to expand a health care facility for the Native American
tribes of northeast Nebraska, northwest Iowa, and southeast
South Dakota. However, several factors complicated this particular
installation:
A tight fit.
Installing the 8½-foot-diameter tank, which measured
36 feet long, required a trench shielding system that would
provide and maintain an unobstructed opening at least 46 feet
long, 16 feet wide, and 16 feet deep. The required excavation
would leave just 8 feet of clearance between the edge of the
pit and three structures—a retaining wall on one side
and a concrete slab for HVAC equipment and a utility building
on another.
Nearby utilities.
The work also meant protecting a water main. Located 6 feet
deep and parallel to the excavation, it ran between the edge
of the pit and the concrete slab and utility building. Other
adjacent utilities plus railroad tracks and a street restricted
access to the site.
Structural concerns.
To prevent structural damage to the existing hospital building
while protecting such sensitive equipment as computers, imaging
devices, and other high-tech hospital systems, no heavy vibrations
could be generated while doing the work.
 |
| The
second of two liner posts is installed for the second
bay of the shielding system. |
 |
| The
third and final bay of the shielding system is being excavated
to a depth of 16 feet. |
Challenging
soil conditions. The soil was C-60 weak clay down to 8
feet. Also, as it turned out, the water table was just 9 feet
below the ground.
Choosing
a Shielding System
Facing these conditions,
Wally Kanne, American Backhoe's project superintendent, considered
his options for protecting workers from cave-in:
The threat of structural
damage from vibrations during installation eliminated the
use of a sheet-piling system that would have required a diesel
or vibratory hammer to drive the sheets and piles. Even if
this approach had been allowed, it would have required a site-specific
engineering plan stamped by a Nebraska professional engineer.
A beam-and-plate system also would have required an engineering
plan for the project plus the added cost of drilling equipment
and a crew to install the soldier piles. Also, both approaches
are typically most cost-effective for shielding projects that
involve both longer and shorter trenchers and longer duration.
However, for this job, the shielding system would be in place
for only three days.
Kanne turned to
Todd Hayes, with United RentalsTrench Safety Division
in Council Bluffs, IA, for advice. The two had worked together
on variety of trench- and pit-shoring systems in the past.
Hayes recommended
Efficiency Production's Slide Rail System for this particular
application. His company has rented this system to contractors
for many other successful projects. Also, because United Rentals
stocks the system, it would be readily available.
Kanne had never
used a slide-rail system but he liked the advantages of this
approach. It not only meets the shielding requirements of
a steel sheeting or beam-and-plate system, but installation
is easier and faster. It can be installed using onsite equipment
and a smaller crew. The modular system is also more versatile.
It can be adapted easily to fit a variety of excavation sizes
and configurations. As a result, rental and installation costs
of the slide-rail system can be as much as half the cost of
a steel sheeting system, Hayes notes.
Like all trench-protective
systems, this slide-rail system has an OSHA-required manufacturer's
tabulated data sheet of tables, charts, and other information,
which is approved by a registered professional engineer and
used to design and construct the system.
"Also, it was important
to work with a distributor, such as United Rentals—Trench
Safety, who has experience installing slide rails on many
projects with various applications and who can provide the
equipment within several hours of when we need it," Kanne
adds. "We were on a tight schedule and couldn't afford to
wait for equipment from a dealer or manufacturers hundreds
of miles away."
Installation
Procedures
Kanne and his crew
installed a three-bay linear slide-rail system, consisting
of panels, linear posts, and corner posts. With two 16-foot
bays on either end and one 14-foot bay in the middle, it measured
46 feet long and 16 feet wide.
Typical excavation
site equipmenta large excavator and a front-end loaderwere
used to install the system.
Unlike tongue-and-groove
posts, unique open-face corner posts of this system provide
a margin of error in terms of keeping the system plumb and
level during installation. This design minimizes post and
panel binding when installing the system down to grade, allowing
panels to be inserted easily, even if the system is not truly
square.
Unlike sheet piling,
in which the sheets are driven to the desired depth before
the pit is excavated, slide rails offer a dig-and-push approach
in which the pit is excavated as the system is installed.
After digging a pilot trench several feet deep, the first
8-foot-high panel is placed in the cut and the ends are inserted
into the outer guides of corner or linear posts. Then, one
after another, additional panels and posts are installed and
connected to enclose the perimeter. Once the system is in
the desired location and the posts are perpendicular, the
panels are backfilled on the outside to secure the system
in place.
Then, excavating
and pushing the panels and posts down in 1-foot increments
using an excavator bucket and alternating from one end to
the other, the system is installed to the bottom of the excavation.
When the excavation reaches the 8-foot depth, another panel
is inserted into the interior guide of the posts and the dig-and-push
process continues until the edge of the bottom panel reaches
the desired depth of the excavation. Using either 4- or 8-foot-high
panels, this system can be built to depths of 24 feet or more.
The system is removed
much the same as it was installedin increments. After backfilling
and compacting in a 2- to 4-foot-high lift, the panels are
pulled up and the process is repeated until the entire pit
is backfilled and compacted.
A safety officer
and Corps of Engineers representatives were on-site overseeing
this installation.
A Smooth
Process
 |
| The
completed slide-rail system prior to removal of the spreader
assemblies and tank installation. |
 |
| A
slide-rail system was built to install this 15,000-gallon
fiberglass fuel tank. |
"The panels went
in really smooth," Kanne says. "We were able to keep things
nice and level and had no problems with binding."
Efficiency's ClearSpan
tie-back waler system was used so that the parallel beam spreaders
could be pulled out for a continuous unobstructed opening
once the entire system was set.
"The wide-flange
beams bolt together and pin to the side panels," Kanne explains.
"This holds everything together when you remove the spreaders
to get a continuous unobstructed opening after the system
is set up."
Wide flange beams
were also attached to the bottom of the linear posts to prevent
the posts from toeing in. These beams were abandoned in place,
since the tank installation prevented their removal.
"Other slide-rail
systems require a welder on-site and a tremendous amount of
time to weld the linear posts to the beams used to prevent
the system from cantilevering," Kanne says. "This Efficiency
tie-back design with a C-clamp allows multiple slide-rail
bays to be built in both directions while working within OSHA
regulations."
A Wet Surprise
Not long after
starting excavation work, the crew hit ground water at a depth
of 9 feet. This water pushed the weak clay soils up from under
the shoring system and threatened to undermine the water main
and adjacent structures. Three pumps, running 24 hours a day,
were able to remove the water to prevent buildup, and sand
was filled in under the water main to protect it.
The knife edge
on the bottom of the slide-rail system allowed Kanne to push
the panels several feet below the excavation level, creating
a dam to stop water from flowing into the pit. Once the water
was under control, a single pump at the bottom of the excavation
was sufficient to prevent water from accumulating. However,
dealing with the water and its related problems threw the
project behind schedule.
The pressure from
the water also affected removal of the panels, which was done
with a crane and excavator. "The initial lift was hard," Kanne
says. "But, once the hydropressure was off, the panels slid
right out."
Assessing
the Results
With no prior slide-rail
experience, Kanne was hesitant to try the approach at first.
But, the results quickly changed his view.
"I was really pleased
with it," he says. "This system installs a lot faster and
much easier than a sheet-piling or beam-and-plate system.
We were able to dig down to grade in just two days. It would
have taken six to 10 days to reach grade with a beam-and-plate
system. The slide-rail system saved us a lot of time. In fact,
using this equipment and working with good people helped get
us back on schedule to complete the project on time."
Author Greg
Northcutt writes frequently on construction and business issues.
GEC
- September/October 2004
|