
Must
a general contractor formally substitute a listed subcontractor
when the subcontractor refuses to perform disputed work or
extra work for which a change order has not been issued?
By Nanette
M. Beaumont
The performance
of extra work or disputed work on any given competitively
bid public works construction project has become customary
in the industry. Generally, controversies regarding such work
arise out of the scope of work to be performed pursuant to
the contract documents. A typical situation involves the public
agency (Agency) asserting that the contract documents require
the contractor to perform specified work for which the contractor
or subcontractor contends is outside the contractual scope
of work.
Pursuant to Section
3-3 (Extra Work) of the Standard Specifications for Public
Works Construction (the “Greenbook”), new and
unforeseen work will be classified as extra work when the
engineer determines that it is not covered by contract unit
prices or stipulated unit prices. Consequently, expenses would
be necessitated by the conditions being other than as represented.
In accordance with Section 3-5 (Disputed Work) of the “Greenbook,”
if the Agency directs the general contractor (General) to
proceed with work that cannot be agreed upon, the General
(or its subcontractor) must complete the work in accordance
with the plans and specifications and dispute such work, per
the “Greenbook,” for payment resolution at a later
date.
Duties
and Options of the General Contractor
Problems do, however, arise, when it comes to making
a request that a listed subcontractor perform extra work or
disputed work. In most cases, the listed subcontractor will
perform the work pursuant to the Disputed Work provision in
the “Greenbook.” However, the General is placed
in a precarious position when the subcontractor refuses to
perform the work. The General must decide whether it will
hire another subcontractor or perform the work itself.
If the subcontractor
refuses to perform the work, the General is left open to the
“purported” risk of violating Public Contract
Code §4107. In accordance with Public Contract Code §4107,
a prime contractor whose bid is accepted may not substitute
a subcontractor in place of the subcontractor listed in the
original bid. There are, however, exceptions to the statute,
wherein the Agency may give the General permission to substitute
another subcontractor.
Frequent situations
falling within such exceptions include, but are not limited
to, the following:
- Bankruptcy
or insolvency
- The listed
subcontractor’s refusal to execute a written contract
- Performance
of substantially unsatisfactory work or delaying or disrupting
work progress (as determined by the awarding authority)
- Improper licensing
- Failure or
refusal to perform its subcontract
- Failure or
refusal to meet the bond requirements
- Determination
by the awarding authority that a listed subcontractor is
not a responsible contractor
- When the General
makes an inadvertent clerical error in its listing of a
subcontractor (For purposes of this article, specific procedural
compliance with Public Contract Code §4107.5 will not
be discussed herein.)
If any of the
above situations arise, the General may substitute the listed
subcontractor. In doing so, it must make a request (the code
does not specify whether it is necessary for the General’s
request to be in writing) for the subcontractor’s substitution
to the Agency, or its duly authorized officer. Although not
specifically required by statute, case law dictates that the
General should specifically state a reason for the request,
and get permission from the Agency as to the replacement subcontractor(s)
who will be performing the work in place of the listed subcontractor
[E.F. Brady Company v. MH Company (1997) 58 Cal. App. 4th
182, 192, 67 Cal. Rptr. 2nd 886].
Failure to comply
with the statute may result in penalties against the Agency
and/or General (Public Contract Code §4110–4111).
However, special circumstances such as emergency situations
do arise, which would likely provide justification for such
a departure from the formal substitution requirements. But,
as a practical matter, unless one of the statutory exceptions
is satisfied, the General has no right to substitute another
subcontractor in place of the listed subcontractor for work
in which the subcontractor is listed. To that end, the statute
confers upon the listed subcontractor the right to perform
the subcontract, unless statutory grounds for a valid substitution
exist. Moreover, that right may be enforced by way of an action
for damages against the General to recover the profits (i.e.,
benefit of the bargain), which the listed subcontractor would
have otherwise realized had it not been prevented from performing
the work contained within the original bid documents [Southern
Calif. Acoustics Co. Inc. v. C.V. Holder Inc. (1969) 71 Cal.2d
719, 726-727, 79 Cal. Rptr. 319; R.J. Land & Associates
Co. v. Kiewit-Shea (1999) 69 Cal. App. 4th 416, 421, 81 Cal.
Rptr.2d 615 (rev. denied)]. Conversely, if any setoff is claimed,
the general rule is that a setoff must rest on a claim enforceable
in its own right [R.M. Sherman Co. Inc. v. W.R. Thomason Inc.
(1987) 191 Cal. App.3d 559, 563, 236 Cal. Rptr. 577].
Duties
of the Agency
Upon receipt of the General’s substitution
request, the awarding authority or its duly authorized agent
is required to give notice in writing to the listed subcontractor
of the General’s request to substitute and the reason
for the request. Although the notice is required to be served
by certified or registered mail, case law indicates that substantial
compliance is acceptable under Public Contract Code §4107.5
[there is no statutory duty placed upon a prime contractor
to directly give a subcontractor notice of its desire to substitute,
except in the limited case of substitution for clerical error
when the subcontractor fails or refuses to execute a subcontract
after being afforded a reasonable opportunity to do so. W.J.
Lewis Corp. v. Harper Construction Company (1981) 116 Cal.
App. 3rd 27, 28, 171 Cal. Rptr. 806], and may very well be
acceptable under Public Contract Code §4107 [Cal-Air
Conditioning Inc. v. Auburn Union School District (MP Allen
Prime Contractors) (1993) 21 Cal. App. 4th 655, 668-69, 26
Cal. Rptr. 2nd 703].
The effect of
Public Contract Code §4107 is to limit the right of the
General to make substitutions, thereby putting it in the hands
of the Agency to give permission to substitute in those situations
listed above. Notably, all of the named situations are keyed
to the unwillingness or inability of the listed subcontractor
to properly perform (Southern Calif. Acoustics Co. Inc. v.
C.V. Holder Inc., 71 Cal. 2d at 723). In accordance with Public
Contract Code §4107, the aforementioned procedure is
used for subcontractor substitutions falling within the statute’s
enumerated descriptions. The main exception to this procedure
pertains to the forwarding of the notice of substitution request
to the listed subcontractor. If the substitution request is
made due to a clerical error (e.g., where the General mistakenly
listed subcontractor A in a bid, instead of subcontractor
B, the General has a duty to give notice to the subcontractor).
In all other circumstances the duty to notify the subcontractor
of the substitution request falls to the Agency (W.J. Lewis
Corp. v. Harper Construction Company, 116 Cal. App.3rd at
31).
Duties
and Options of the Listed Subcontractor
Upon receipt of notification as to the substitution
request, the listed subcontractor will have five working days
within which to submit to the Agency written objection to
the substitution. Failure to file such written objections
constitutes the listed subcontractor’s consent to the
substitution. Subsequently, if written objections are filed,
the awarding authority is then required to give written notice
of at least five working days to the listed subcontractor
of a hearing conducted by the awarding authority as to the
General’s request for substitution.
Analysis
of Rationale Behind the Act
Both the statute and case law are silent with regard
to whether a formal subcontractor substitution is necessary
pursuant to Public Contract Code §4107, for extra work
or disputed work. Additionally, the legislative history makes
no mention of such. The purpose of the Subletting and Subcontracting
Fair Practices Act is to prevent “bid shopping”
by the General, including the pressuring of other subcontractors
to submit lower bids than listed subcontractors or “bid
peddling” by unlisted subcontractors to undercut known
bids of listing subcontractors in order to procure the job.
As such, it is highly questionable whether non–change
order extra work and disputed work fall within the realm of
what the legislature intended within its public policy reasons
for enacting the statute (Cal. Pub. Con. Code §4101;
R.J. Land & Associates Const. Co. v. Kiewit-Shea, 69 Cal.
App.4th at 428).
On a similar plain,
Public Contract Code §4107(c) allows for the subletting
or subcontracting of work involving the performance of change
orders causing changes or deviations from the original contract
and/or any portion of the work in excess of 0.5% of the prime
contractor’s total bid, as to which his or her original
bid did not designate a subcontractor. However, since the
statute and case law are silent with regard to separate formal
substitution procedures for non–change order extra work
or disputed work, it might be inferred that the lack of precedent
in this specific area is due to problems relating to extra
work and disputed work being classified under one of the other
categories justifying the substitution (e.g., the subcontractor’s
failure or refusal to perform the subcontract). Although the
act likely was not intended to apply to extra work or disputed
work, clarification in this regard would be efficacious.
Absent specific
guidelines or specific handling procedures, until the code
is amended or there is a judicial determination that takes
into account the intricacies arising from competitively bid
public works construction projects, it is best to take precaution
and strictly comply with Public Contract Code §4107.
Although such a factual situation seems innocuous, the limited
time and effort it takes to comply with the statute may save
the Agency and the General unnecessary protracted litigation
later on down the line.
This is an intricate
area of the law. As such, if you have issues pertaining to
the above, please contact an attorney or other legal advisor.
Nannette Beaumont
may be contacted for more information at Beaumont Law Firm,
PC by phone at (559) 658-8771 or via e-mail at www.blflaw.com.
GEC
- March/April 2006 |