|

Chicago-area
contractor moves 1.5 million yards of soil to merge wetlands
and retail space.
By Larry Trojak
Many people harbor
the misconception that all development projects are alike—that
is, simply level it, clear it, and build it. For those who
do, a look at the area that will soon be home to the North
Aurora Town Centre should convince them otherwise. The 330-acre
site contains 100 acres of wetlands that have to be relocated
before construction can begin. However, doing so in accordance
with environmental mandates set forth by the US Army Corps
of Engineers has proven to be one of the most challenging—but
rewarding—aspects of any project undertaken by Rubloff
Excavation LLC.
Unique
Development
Located about 45 miles west of Chicago on Interstate
88, North Aurora is the next logical extension of a metropolitan
area that continues to expand outward in every possible direction.
As people relocate, sites like the North Aurora Town Centre
with its nearly 600,000 square feet of available retail space
will provide for their needs. According to Bob Marsh, president
of Rubloff Excavation, the firm charged with making the site
construction ready, getting to that point has been anything
but routine.
 |
PHOTO: TEREX |
| One of 14 Terex trucks at the North Aurora site |
“Not only
is this the largest excavation project we have ever undertaken;
it has also been the most complex, because of the 100 acres
of core wetlands that have to be created. And it has to be
created in a planned, sequential order which will ensure the
least possible amount of environmental impact, with regular
inspections by Army Corps, Soil and Water, and conservation
officials along the way.”
The need to create
the wetlands area stems from past construction of an auto
mall located adjacent to the site. That location was initially
designed to retain an area as wetlands. By the time it was
completed, however, the wetlands concept had become little
more than a pond. Marsh says when Rubloff Development Group
negotiated to buy the property, a clause in the agreement
said that, in exchange for relocating the streams that ran
through the center of the property, the firm would create
100 acres of new viable wetlands.
Slow Beginnings
It’s hard to say if any contractor is really
equipped to tackle a project with the constraints and demands
present at the North Aurora site, but Rubloff’s resources
and willingness to work with the Corps of Engineers kept the
project moving along, even during some taxing early periods.
“The early
part of the project was held up for about two-and-a-half months,
again mostly due to sequencing constraints. With the right
equipment on a job like this, we can easily move 1.5 million
yards of dirt in 30 to 60 days; having the entire site available
to you makes that possible. But this is not like any other
job. Here we had to first dig diversion channels, stabilize
them, plant them, and then reroute the creeks onsite.”
With that done,
Marsh says they created a number of wetlands areas, mindful
of strict adherence to elevation, outfall elevations, and
so on, to maintain appropriate water levels. Different plant
communities have been designed into each of the levels of
wetland elevation. A 40-acre basin, for example, might have
five different plant communities designed into it. Sculpted
mounds can have 6 inches of water covering one part, and then
be tapered down and terraced to a depth of 1 foot, then 18
inches, and then back up to just damp and again to dry, with
a different plant species and community on each of those levels.
“We even
had to put dead trees into several areas, making us one of
the few projects with line items in their budgets to buy dead
trees to be strategically placed in the bottoms of ponds.”
Bringing
in the Iron
To handle issues related to wetland plantings and
the like, Rubloff hired a wetland consultant and a landscaping
firm, both of whom specialize in that area. To do the actual
earthmoving and development, the company called upon its own
strengths: an impressive fleet of Terex equipment, utilizing
everything from an HR-18 mini excavator to a TXC-470 excavator
and almost everything in between.
“We are
fortunate in that we are in the process of becoming the Terex
dealer for this part of the state. But that move, in itself,
stems from the fact that we were a huge user of Terex equipment
before deciding on a dealership position. When we first got
into the excavation business, we had a tendency to purchase
the least expensive equipment—mostly older machines
sorely in need of repair. We quickly learned that it made
far more sense to buy good equipment, make sure it is well
maintained, trade it out on a regular basis to upgrade, and
so on.”
Marsh says that
while there is a certain amount of blind loyalty among many
equipment users, such is really not the case with Rubloff.
“For us it is simply a cost/benefit study. If I can
buy Terex, factor in the operating costs—including fuel,
upkeep, repair, et cetera—and move a yard of dirt from
Point A to Point B less expensively than a competitive piece
of equipment, I will request Terex forever. And that has been
the case. We’ve found that our Terex fleet is not only
productive; it is a good value-added investment for us.”
Removing
the Spoils
Rubloff got to utilize the largest piece of equipment
in its fleet—the TXC-470—in the early stages of
the project when a berm left over from the auto mall’s
construction had to be removed.
“This mound
was probably in excess of 200,000 yards of dirt that had to
be hauled out before work could proceed on that area,”
says Steve Full, Rubloff’s project superintendent. “We
had a steady stream of 18-yard TA-40 haul trucks being fed
by the 470 with a 4.5-yard bucket, and they were staging and
leaving every minute or so. The 470 really set the pace; it
had that berm down, and the dirt redistributed to low areas
throughout the site, in no time.”
Marsh says they
initially mobilized more equipment than was necessary during
the early stages of the project, but he knew that once the
creek diversion channels were cut, stabilized, and inspected,
things would open up.
“Once we
got to that point, it opened up nearly two-thirds of the site
for us,” he says. “Things were also complicated
by the wide range of material we’ve encountered—everything
from a gumbo-like clay to sand and cobbles—and the area’s
high water. So creating several basins onsite, some of which
have 200,00 to 300,000 yards of fill excavated and used to
build beds in areas in the creek bottom, took a wide variety
of equipment based on what layer of soil we were in. Tractors
pulling Ashland scraper pans worked great in the topsoil and
in the clay where it was dry. However, as soon as they got
into the sand and wetter material, they bogged down and we
had to switch to the Terex 14G scrapers. We ran those until
we got to a point where traction became impossible, and then
set the TXC-470 out there feeding the 40-ton off-road trucks.”
Additional
Benefits
Rubloff has 14 trucks committed to the North Aurora
project. Should they still need additional capacity, however,
or if haul distances get too long, they are prepared to top-load
the scraper pans and the 14G scrapers for additional volume.
“Again,
that’s all a byproduct of the sequential approach,”
says Marsh. “We can’t always take the fill from
one basin and move it to the closest area in need of fill.
It may be that we are not allowed to fill in that area until
another step in the sequence has occurred. So we take it elsewhere.
Of course there is always the possibility that we will then
have to bring it back at a later point in the sequencing,
but that’s just something we’ve learned to deal
with.”
As challenging
as the project has been, Marsh is quick to add that it has
also proven beneficial from a number of standpoints. “A
project like this tends to scare some contractors,”
he says. “During the course of the job, we monitored
the design, did the entire permitting process, handled the
budgeting, and did all the earthmoving, site utilities, and
wetlands before turning it over for construction to begin.
So it really has been a turnkey full-service operation, and
that, coupled with the equipment we can bring to bear, allows
us to compete in areas in which many others simply aren’t
equipped to operate. The development arm of our company has
projects ready to go throughout Illinois and elsewhere in
the country; North Aurora has us better prepared for anything
those projects have to offer.”
Larry Trojak,
president of Trojak Communications of Coon Rapids, MN, is
a marketing communications professional who writes extensively
on construction, material handling, demolition, and recycling
issues.
GEC
- March/April 2006
|