|


In
March 2001, routine monitoring of perimeter probes around
the Davis County (Utah) Solid Waste Management and Energy
Recovery Special Service District landfill revealed
that high concentrations of landfill gasgreater
than 50% in some caseswere
present at the property line.
By
Dick Sprague and David Lutz
March 2001
testing around the Davis County (Utah) Solid Waste Management
and Energy Recovery Special Services District landfill
area showed that the landfill gas had migrated beyond
the property line, and, since methane is commonly explosive
in concentrations between 5 and 10%, Wasatch Energy
Systems (WES), the district's operating name, recognized
that the migration of landfill gas could result in dangerous
conditions. To meet its commitments to the Utah Department
of Environmental Quality and the adjacent landowners,
WES opted to use the design-build process to quickly
implement the needed solution to control the migration
of landfill gas.
Gas Migration
at Davis County
The integrated
solid waste management utility in Layton, UT, consists
of a waste-to-energy (WTE) plant, which burns approximately
half of the collected solid waste; a landfill, which
accepts ash from the WTE plant as well as difficult-to-burn
wastes; and various recycling facilities. The 25 ac.
Davis County Landfill, part of the WES system, includes
both a lined Subtitle D - compliant landfill cell and
a historic, unlined landfill cell.
The landfill began operating in the early 1950s, and
the WTE plant went on-line in 1987 to complement and
extend the life of the landfill. The historic cell started
as an end-dump canyon fill approximately 50 years ago
and was closed during the fall of 2000. As part of the
closure, WES installed 11 horizontal wells to collect
landfill gas accumulating directly below the closure
cap. These horizontal wells augmented three vertical
wells previously constructed in various parts of the
landfill.
The discovery that landfill gas, which results from anaerobic
digestion of solid wastes, was migrating away from the
westernmost property of the landfill propelled WES to
commit to implementing a landfill-gas migration
control system by mid-December 2001.
The chosen landfill gas migration control system consists
of four main elements: a flare station to burn landfill
gas; a gas extraction system, consisting of wells within
the landfill to reduce pressure, driving gas outward;
a soil-gas extraction system, consisting of wells at
the property line to draw gases back to the site; and
monitoring wells on the adjacent property.
WES Implements
Design-Build Solution
In May 2001,
WES released a request for proposals (RFP) for engineering
services to design the landfill-gas migration control
system. As part of the responses to the RFP, HDR Inc.
and another consultant suggested that the needs of WES
might be better met through the design-build method,
particularly since WES had committed to a tight schedule.
In July, WES accepted the design-build proposal and
jointly entered into a two-part design-build contract
with HDR.
Several agencies have developed two-part model contracts
for design-build projects. The first part is intended
to provide the owner with a conceptual design and a
firm price for the second part, which includes the final
design and construction of the project.
As part of the initial contract, WES and HDR entered
into an agreement to provide conceptual (30%) design
and a proposal for the final design and construction,
including a guaranteed-maximum price for the construction.
As part of the conceptual design, which was completed
on August 31, the contractor also obtained bids from
qualified drillers to construct landfill-gas
extraction wells; bids from qualified suppliers of landfill-gas flaring equipment;
and a bid from a local contractor to perform the balance
of construction.
These bids became the basis for the proposal of the final
design-build contract, which WES accepted on September
27, approximately two weeks behind the schedule contained
in the initial proposal and 2% below the bid. Work began
in early October, with a planned completion date of
December 14.
Drilling
Problems Lead to Delays
From the
beginning, the drilling subcontractor encountered difficulties.
Despite having drilled wells into this landfill previously,
the drilling proved more difficult and time-consuming
than anticipated. In addition, the subcontractor subcontracted
the drilling for the soil-gas extraction wells and the
monitoring wells; his first two lower-tier subcontractors
essentially failed to perform. Because of these repeated
failures, HDR took responsibility for locating a qualified
third lower-tier subcontractor to complete the work
in parallel with the second subcontractor.
The final wells were not completed until January 18,
approximately five weeks behind the original schedule.
In general, a delay in schedule almost always results
in a problem project, particularly a cost overrun. Through
active management of the overall project, the contractor
was able to avoid most if not all of these problems.
Furthermore, the flare station, provided by a subcontractor,
completed its final testing on December 14, as had been
scheduled, and WES signed an acceptance of the flare
station on December 18. By this date, approximately
60% of the landfill gas extraction wells were available
and on-line, providing the owner with continuous vacuum
on the landfill itself and essentially meeting the owner's
commitment to have a system running by mid-December.
Design-Build
Process Results in Cost-Savings
During early
February 2002, WES received a financial reconciliation
for the project involving a deductive change order of
almost $30,000. WES and HDR then agreed to conduct a
"lessons-learned" session following several months
of operation of the system.
Dick Sprague is with HDR Inc. in Denver, CO. David
Lutz is with HDR Inc. in Kansas City, MO.
MSW
- May/June 2004
|