|


Many
Florida communities had to clear more post-storm debris
than typically collected in an entire year, but Mother
Natures wrath had just that and more in mind.
By
Jonathan Burgiel and Chuck McLendon
Prior to
the disastrous hurricane season of 2004 when four storms
(Charley, Frances, Ivan, and Jeanne) impacted the state,
many Florida communities knew about but discounted the
risks of a catastrophic storm hitting the statelet
alone their community. No major hurricane had hit Florida
since Andrew made landfall south of Miami some 13 years
earlier. In central Florida, it had been more than four
decades since Hurricane Donna had struck. Spared a direct
hit by prior recent storms, no one could have foreseen
the onslaught of hurricanes that would ravage the peninsula
in the ensuing months.
To date,
more than 53 million cubic yards of debris have been
cleared and nearly $4.4 billion in disaster recovery
assistance have been appropriated by the Federal Emergency
Management Agency (FEMA). Indeed, these storms have
had a lasting effect on the Sunshine State.
Table
from FEMA
In retrospect, there are many lessons that can
be gained from the 2004 hurricanes. Whether its
hurricanes, tornadoes, ice storms, mudslides, or forest
fires, all communities have unforeseen natural disaster
risks that can benefit from Floridas experience.
|
Table.
Florida's 2004 Hurricanes by the Numbers
(as of March 10, 2005)
|
- 53
million cubic yards of debris have been removed.
- $4.4
billion in FEMA diasaster aid have been rewarded.
- 15,600
temporary manufactured housing units have been
provided for displaced families.
- More
than 1.24 million victims have applied for federal
and state assistance.
- All
67 Florida counties have been affected.
|
Prepared
Versus Unprepared
It was evident from the response by communities
across the state that some had done effective upfront
preparation. These communities had workable disaster
recovery plans that could be easily mobilized. Understanding
that hurricanes are a known weather risk for Florida,
proactive communities like Lake County (near Orlando)
had update-to-date Disaster Response Plans and pre-positioned
disaster debris hauling contracts so they could hit
the ground running immediately after the storms.
Other communities
found that, when the storms hit, their disaster recovery
plans were insufficient. Some plans identified parks
as potential debris staging areas but did not take into
account situations such as traffic, and proximity to
schools and residential neighborhoods.
Many communities
also found another critical shortfall in the pre-event
planning process was poor multijurisdictional coordination.
Generally, coordination with the Florida Department
of Transportation (FDOT), which is responsible for all
state and federal highways across the state, was woefully
inadequate. In the Panhandles Escambia County
(which includes Pensacola), the FDOT had retained its
own disaster debris contractor. Keeping the countys
contractor on county roads and the FDOT contractor on
its assigned state/federal roads proved to be a huge
task. Debris contractors are paid by the cubic yard
collected, so debris equals money. When an FDOT contractor
was found to be either intentionally or unintentionally
collecting debris on a county road (or vice versa),
the situation became volatile in some cases.
Having multiple
contractors in the same area also proved to be challenging
from a customer service standpoint. Escambia County
received calls requesting debris collection service
from residents living on roads that the FDOT was responsible
for clearing.
In retrospect,
having a cooperative agreement with the FDOT, whereby
a single debris contactor is assigned to collect all
debris within a designated zone containing county, state,
and federal roads would have been preferable over the
use of multiple haulers. Paying close attention that
the proper loading location is recorded on each load
ticket also makes back-end accounting regarding who
pays (the county versus the FDOT versus the city) substantially
easier.
Escambia
County also found that a tremendous amount of coordination
needed to occur with the two incorporated cities in
the county as well as with the school board and regional
utility authority.
Add to this
special procedures and accounting for stump, hanging
limbs, and dangerous leaning tree removal; waterway
cleanup; initial 72-hour push; and private right-of-entry
release forms, and you have the making of a never-ending
maze of complexities that no one would have imagined
unless proper planning had taken place well in advance.
It was clear
that pre-event planning, like an insurance policy, paid
out multiple-fold for communities that were ready to
deal with the literal mountains of debris collected
over the ensuing months.
Making
the Grade
Many times, the benefits of communities being prepared
versus unprepared materializes during the critical time
period immediately following a natural disaster, whats
known as the push periodthe first
72 hours after the disaster when heavy equipment is
used to clear roadways for emergency vehicles. Literally,
at this point, a good plan can mean the difference between
life and death, and create a positive or negative public
image of how the local government performed while under
fire.
In Florida,
typically, solid waste management or public works/roads
departments took the lead on responding to debris removal
throughout the state. Those that received the highest
marks from their customers had the necessary equipment
and personnel ready to mobilize and get the debris cleared
while others were stumblingsometimes taking days
or up to a week to get a response team on the ground
and mobilized.
With the
significant volume of debris generated, debris hauling
crews and equipment were in short supply. In many cases,
makeshift plywood trailers were used to haul away debris.
Often, this patchwork of vehicles was ill-prepared to
handle the heavy limbs and debris generated by the storms.
Again, communities with a plan and pre-approved contracts
were the first to receive assistance from trained crews
and appropriate equipment.
Markets,
Markets, Markets
Once the debris was removed from the streets, the
next phase of the cleanup effort beganprocessing
and getting rid of the millions of cubic yards of mulch
and construction-and-demolition (C&D) debris. According
to the Florida Department of Environmental Protection
(DEP), the volume of debris resulting from the four
hurricanes would fill Florida State Universitys
Doak Campbell Stadium (an 80,000-seat football stadium)
in Tallahassee, to the brim more than 90 times.
 |
While under
normal circumstances materials generated as a result
of a storm may have some minimal value, the massive
oversupply of mulch and C&D debris crippled the
already shaky economics for recycling these material
streams. Stockpiling the processed mulch was generally
not an option due to the need to restore parks for spring
sports leagues as well as concerns about spontaneous
combustion of mulch piles. The pie chart provides an
aggregate summary of the mulch markets for five communities
representing approximately 20% of the states total
debris volume.
As shown,
the vast majority of mulch from these five case study
communities was either landfilled, utilized for daily
landfill cover, or used as fuel in domestic or foreign
biomass plants. Huge quantities of mulch were trucked
to major ports (including the Port of Mobile, AL, and
Port Canaveral, FL) where the feedstock was loaded onto
massive freighters. This material was ultimately used
as fuel for biomass plants in Italy. Domestic fuel markets
included the Okeelanta Cogeneration Plant, the Ridge
Generating Station, and the Telogia Power facilityall
in Florida.
Interestingly,
only a very small fraction of the debris generated in
these five communities was burned. Many communities
attempted trial burns using air curtain incinerators,
but most were ultimately shut down due to residents
complaints about smoke and embers. Approximately 4%
of the mulch was utilized for groundcover for nurseries
and for pathways at flea markets, such as the one at
the Central Florida Fairgrounds in Orlando. A company
that took some of the material from Lake County plans
to utilize the mulch in a compost product.
Reimbursement
Issues
Reimbursement from FEMA is an important and sometimes
long, drawn-out process that needs to be taken into
account both in pre-planning activities and throughout
the duration of the disaster recovery effort. As many
in Florida have found, this aspect of the project will
continue to be a focus of the recovery effort long after
the cleanup has been completed.
There are
many specific regulations and requirements that FEMA
has imposed in the last few years. If these rules and
regulations are not closely followed, communities may
not be reimbursed for the costs they have paid out to
their disaster debris contractors. One critical process
that FEMA requires is collection and disposal monitoring.
This process requires that trucks be certified prior
to initiating collection activities to determine their
volumetric capacity. Once certified, monitors are assigned
to follow collection vehicles and issue tickets testifying
that only storm-generated debris (as opposed to land
clearing debris, etc.) from a designated zone was collected.
Once at the debris staging area, visual estimates of
truck fullness are made by disposal monitors stationed
in towers prior to the truck unloading.
Until four
or five years ago, no formal monitoring of debris haulers
was required by FEMA. However, due to high levels of
fraud by a few unscrupulous debris hauling firms, FEMA
has since instituted the requirement for monitors to
follow and record all debris loads hauled. As part of
R.W. Becks role in the recovery effort, more than
500 staff members assisted in this monitoring and data
gathering effort in Florida. Knowing these types of
monitoring requirements and incorporating them into
a communitys disaster recovery plan can be invaluable
because this data often serves as a communitys
cornerstone for FEMA reimbursement.
Summary
In summary, while natural disasters pose unknown
risks, community managers in charge of disaster response
need to be proactive. Development of pre-event disaster
response plans and contracts was the best investment
that many Florida communities have ever made. Many others
that did not prepare in advance are now hurriedly preparing
requests for proposals for disaster preparedness assistance
and to select pre-positioned haulers for the future
storm seasons. The unknown risks wont change,
but plans for dealing with them definitely can.
Jonathan
Burgiel and Chuck McLendon are principals with R. W.
Beck, a national solid waste consulting and engineering
firm. They can be reached at jburgiel@rwbeck.com
and cmclendon@rwbeck.com
or 407-422-4911.
MSW
- September/October 2005
|