By Janice Kaspersen
Stormwater runoff misdirected,
permits pulled, delays potentially costing a company hundreds of
thousands of dollars - and behind it all, one of the country’s most
rigorously protected bodies of water. These elements came together
in April 1999 during the construction of Bethesda Place II, a 12-story,
300,000-ft.2 Maryland office building.
 |
| The
concrete treatment vault was cast in place before construction
of the building could continue. |
The
building’s design originally called for the stormwater runoff from
the underground parking garage to flow into the sanitary sewer system,
as is the practice in the District of Columbia. About half the district
is served by a combined sewer system that accommodates both sanitary
flow and stormwater runoff. Just a few miles away in the city of
Bethesda, however, stormwater runoff must be directed into a separate
stormwater system. By the time the problem came to light, construction
of the garage was well under way.
The
project fell under the authority of theWashington Suburban Sanitary
Commission (WSSC), which has stringent stormwater requirements,
and Maryland’s Montgomery County Department of Permitting, which
halted the project when the drainage problem was discovered. Before
the general contractor for the garage portion of the project could
divert the parking garage runoff to the stormwater system, it had
to demonstrate to both authorities that the stormwater would be
adequately filtered.
Joe
Morrison, project manager for contractor John J. Kirlin Inc. of
Rockville, MD, estimates that delays would have cost the company
$150,000 per day. "It was ugly. We were stopped dead if we
didn’t give them an approved method of controlling or purifying
the stormwater."
Bethesda
lies within the Chesapeake Bay watershed. "We’re really sensitive
here because of the bay," Morrison acknowledges. The WSSC exercises
stringent control over its portion of the watershed, reflecting
efforts in recent years to clean up the bay. Chesapeake Bay is North
America’s largest estuary and the most biologically diverse, with
more than 3,600 species of plants, fish, and animals. Pollution
threatened many of these species during the 1970s, and in the 1980s
the bay became the first estuary in the United States to receive
intensive government-sponsored restoration. Besides parts of Maryland,
the 64,000-mi.2 watershed that drains into the bay encompasses
parts of Delaware, the District of Columbia, New York, Pennsylvania,
Virginia, and West Virginia.
The
Department of Permitting offered a suggestion for John J. Kirlin’s
problem, however: a device called the StormFilter for removing stormwater
pollutants. Manufactured by Stormwater Management of Portland, OR,
the StormFilter is a passive treatment system that uses chemical
- not mechanical - processes to reduce pollutants. Precast treatment
vaults of different sizes and configurations are available, but
Stormwater Management and John J. Kirlin chose a 6- x 12-ft. cast-in-place
unit for Bethesda Place II. Shipping a precast concrete vault from
the West Coast didn’t make much sense, Morrison points out, so Stormwater
Management provided build-in-place engineering drawings and communicated
the plan to WSSC. "We had the permit in three days," says
Morrison. "The whole turnkey installation was probably a seven-day
form-out, pour-out process."
The
vault contains cylindrical filter cartridges - in this case, four
- each capable treating peak flows of 15 gal./min. Once the StormFilter
is operating and stormwater flows into the vault, a float-actuated
priming system prevents it from flowing out again until the water
level rises high enough to purge air from the filter cartridges
and create a siphon in the cartridges’ central drainage tubes. As
the filters start to become plugged with debris, the siphon effect
increases, helping to maintain a high flow rate. Hoods prevent air
from entering the cartridges and breaking the siphon effect until
the water level has dropped.
Morrison
points out that another potential delay, if the drawings had not
been immediately available, was the placing of the underground piping
for the water exiting the vault. "We had to know where - what
elevation. You can’t put piping in unless you know where the end
is going to be. Once we got the drawings, we knew what elevation
we needed to run to."
The
rechargeable cartridges accept different filtering media, depending
on the pollutants expected at a particular site. Filter media, which
can be used in combination for maximum effect to target a variety
of pollutants, include a pleated fabric insert, perlite, zeolite,
and a patented leaf media made from processed deciduous leaves.
At Bethesda Place II, where oil, grease, and radiator coolants from
the parking garage were the main concern, perlite filters were used.
"We
used to just put concrete interceptors in with baffles," Morrison
points out. "This is a little bit more sophisticated."
|