Sediment
clogs our nations waterways, costing us billions of dollars
in restoration and cleanup each year. Runoff from construction sites
is one source of sediment that can be easily addressed. Following
the basic design steps outlined here, a system can be developed
for controlling this runoff and preventing the sediments from travelling
off-site and into downstream water bodies.
By Jerald S. Fifield

The role of any structural
sediment control measure is to create conditions for sedimentation;
that is, to allow for the deposit of soil particles that are in
suspension. When transport mechanisms that carry soil particles,
such as water or wind, move at a slow rate, particles might settle
out of suspension.
The
Theory of Sediment Containment Systems
Sediment containment
systems are hydraulic controls that function by modifying the storm-runoff
hydrograph and slowing water velocities. Some of the more common
names for these structures are sediment basins, sediment ponds,
and sediment traps. The function of any sediment containment
system is to contain suspended particles found in runoff waters.
When
designed correctly, all sediment containment systems complete the
following:
1. provide containment
storage volume for incoming runoff waters,
2. create uniform flow
zones within the containment storage volume,
3. discharge water at
a controlled rate.
Retention Versus
Detention. When all runoff waters are captured, efficiency
of the containment system is 100%. However, the feasibility of retaining
all runoff waters from a construction site is nearly impossible.
Instead of trying to retain all runoff waters, a containment system
should provide sufficient volume for capturing suspended particles
and still be able to drain.
Calculating Minimum-Containment
Surface Areas. If a sediment containment system is to be
effective for capturing a design-size particle, it must allow for
the flow of water through the system and provide time for deposition
of suspended particles.
Defining
the Three Types of Sediment Containment Systems
Traditionally, when sediment
containment structures captured runoff from 1.2 to 2 ha (3 to 5
ac.) or less, a sediment trap was used. When the contributing area
to the structure exceeded these values, then a sediment basin or
pond was used.
The problem with
using a single value for the total contributing area is that it
does not take into account the type of soils from which runoff is
occurring. A suggested method that uses suspended design-size particle
criteria to distinguish which type of containment system to use
appears in Table 1.
 |
Type-1 Sediment
Containment System. A Type-1 sediment containment system
will require development of a structure to capture the maximum possible
number of medium silt and smaller suspended particles. Since these-size
particles have low settling velocities, large storage volumes, long
flow-path lengths, and controlled discharges will be required. Type-1
systems are designed to have the highest possible net efficiency
and are best represented by the traditional sediment basin and trap.
Type-2 Sediment
Containment Systems. The Type-2 sediment containment system
will capture suspended particles having faster settling velocities
than particles requiring Type-1 structures. Consequently, smaller
storage volumes and shorter flow-path lengths can be used. As with
a Type-1 structure, these sediment control systems will also have
controlled discharges. Whereas their net effectiveness for the inflow
of all suspended particles may be low, Type-2 systems will still
have a high apparent effectiveness.
Type-3 Sediment
Containment Systems. The least effective methods to control
suspended particles in runoff waters are represented by Type-3 sediment
containment systems. These are not necessarily design structures,
as found with Type-1 and Type-2 systems, but are often best management
practices (BMPs) found on construction sites. Examples include bale
and silt-fence barriers, inlet control structures, and drainage
ditch-check structures. Whenever significant runoff occurs, all
Type-3 systems have very low net and apparent effectiveness to control
suspended particles. When runoff is very low, however, the Type-3
sediment control systems can be effective in reducing suspended
particles as long as they are continuously maintained.
Minimum
Sediment Containment System Volumes
In order to calculate
a minimum containment system volume, it is necessary to decide upon
a minimum settling depth. Theory suggests that any depth will be
sufficient. Practicality dictates sufficient depth must exist to
ensure sufficient deposition zones.
Type-1 Sediment Containment
System Minimum Storage Volume
To compensate for actual
conditions, such as short-circuiting and dead areas, it has been
recommended (Goldman et al., 1986) that systems have a minimum settling
depth of 0.61 m (2 ft.). Field experience has demonstrated that
Goldmans suggestion for depth is functional for construction
sites. Therefore, the following criteria are suggested for providing
minimum runoff volumes (VOLRO) for sediment containment
systems (SAm = minimum water-surface area):

In order to reduce maintenance
on any sediment containment structure, additional depth should be
provided near inflow areas. This allows heavier particles to be
immediately trapped to allow more deposition space for design-size
particles within uniform flow zones.
An approximation of additional
sediment-storage volume (VOLSSV) can be found by overexcavating
the bottom of the containment system by 10%, or:

Combining the results
of Equation 1 and Equation 2 will provide the following minimum
sediment containment volume (VOLm) equation:

If a sediment containment
system is a rectangular solid shape having sides of 0.67 m (2.2
ft.), then Equation 3 will be fulfilled. Construction of a containment
system, however, will not necessarily create vertical sides. Therefore,
designers should strive to create a sediment containment system
volume having an average depth (Davg) that meets the
following criteria:

Environmental Protection
Agency Requirements. When
4 ha (10 ac.) or more are disturbed, EPA (1992) requires that a
storage volume of 252 m3/ha (3,600 ft.3/ac.)
be developed to capture runoff. This is equivalent to the first
25 mm (1 in.) of runoff per unit area from a storm event of 76 mm
(3 in.).
EPA selected 76 mm as
being representative of an average two-year, 24-hour storm event
for the nation. However, 76 mm of precipitation is not necessarily
representative as an average two-year, 24-hour storm event in the
Eastern United States. Review of similar maps for the Western United
States demonstrates the same conclusion.
Finally, Figure 1 illustrates
that only Type A (i.e., sandy) soils will produce 25 mm of runoff
in response to 76 mm of precipitation. All other soils will have
greater runoff values.
In 1998 EPA revised its
criteria. These criteria suggest that sufficient volume exists for
a sediment containment system to capture the first 25 mm of runoff
or to capture the runoff resulting from a two-year, 24-hour
storm event.
The 1998 ruling leaves
unanswered whether 25 mm of runoff is a maximum value to consider.
When runoff from more impervious soils (i.e., clays) is considered,
there may be large volumes generated that cannot be handled on a
construction site in a practical manner.
In order to address EPAs
requirements, it is recommended that Type-1 sediment containment
systems have a minimum volume by selecting the largest value
as calculated by either of the following methods:

Type-2 Sediment Containment
System Minimum Storage Volume
Development of a Type-2
sediment containment system has the advantage of selecting a design-size
particle that has a relatively fast settling velocity. Usually these
structures are smaller than a Type-1 system since they do not require
large storage volumes for runoff waters. Therefore, the volume calculated
by Equation 3 is sufficient for this containment system.
Type-3 Sediment Containment
System Minimum Storage Volume
Since these systems represent
the more "temporary" BMPs found on construction sites,
calculating design volumes is usually not necessary for most structures.
Thus, their net efficiency to control suspended design-size particles
is very low. The only time these structures will be effective is
when a small amount of runoff occurs from disturbed lands.
Summary of Type-1
and Type-2 Sediment Containment System Minimum Parameters
Table 2 provides a summary
of the equations used to calculate minimum structural parameters
for Type-1 and Type-2 sediment containment systems. These structures
provide the greatest potential for reducing the number of suspended
particles in runoff waters from construction sites.
Effective sediment containment
systems require the following:
1. understanding soil-particle
distribution of contributing upstream, disturbed lands;
2. identifying the design-size
particle;
3. providing sufficient
containment surface area, flow length, and volume for maximum net
effectiveness;
4. identifying and providing
a design discharge value;
5. developing a maintenance
plan to ensure that an average depth of at least 0.67 m (2.2 ft.)
is available at all times for the containment volume.
Designers must always
be cognizant of hydrologic constraints of sediment containment and
detention systems. What is provided in Table 2 is only a guideline
for determining minimum parameters needed to capture design-size
particles in runoff waters. Professional judgment on proper drainage
designs for developing areas must never be compromised. For example,
large contributory areas often require development of large, centralized
detention facilities. When this occurs, designers must verify that
the minimum parameters for a sediment containment system are part
of the centralized detention facility. In this manner, efficient
control of sediment in runoff waters will be realized.
References
Goldman, S.J.,
K. Jackson, and T.A. Bursztynsky. Erosion and Sediment Control
Handbook. McGraw-Hill, pp. 5.1-5.31. 1986.
US Environmental
Protection Agency. "Final NPDES General Permits for Storm Water
Discharges from Construction Activities." Notice, Federal
Register, Part II. US Government Printing Office, Washington,
DC. September 9, 1992.
US Environmental
Protection Agency. "Reissuance of NPDES General Permits for
Storm Water Discharges from Construction Activities." Notice,
Federal Register, Part II. US Government Printing
Office, Washington, DC. February 17, 1998.
Jerald S.
Fifield, Ph.D., CPESC, is president of HydroDynamics Inc. in Parker,
CO. This article is an excerpt from Designing for Effective Sediment
and Erosion Control on Construction Sites, which will be published
this spring by Forester Media .
|