By Anthony
J. DePasquale, Douglas Leatherman, and Randy Thomas
Molly Anns Brook,
a tributary of the Passaic River, flows through an urban area in
Paterson, Haledon, and Prospect Park, NJ. Inadequate channel capacity
led to repetitive flooding in neighborhoods along a 2.5-mi. stretch
of the brook. In the summer of 1999, the Philadelphia District US
Army Corps of Engineers designed and constructed a flood protection
project to alleviate the problem, incorporating a deeper and wider
channel to provide flood protection from a 50-year storm event.
Although erosion
protection is paramount when designing flood protection projects
in any environment, it becomes even more critical in urban settings
because of the proximity of structures, as was the case with Molly
Anns Brook: In several areas, structures comprised the banks.
In addition, features of the projects location, such as limited
right of way, undulating and outcropping bedrock, and high stream
velocities caused by stormwater runoff from surrounding developed
areas, imposed many constraints on design and construction.
Conventional solutions,
such as riprap, wire-mesh gabions, cabled concrete mats, and more
than 3,000 lin. ft. of precast concrete retaining walls, had been
used to protect the banks and contain the floods on adjacent areas
of the brook. For two especially difficult locations, however, the
corps chose less conventional geocell approaches to ease construction
and reduce costs. Although cellular confinement has been around
for almost 20 years - developed in the late 1970s as a cooperative
research effort between the corps and Presto Products Company of
Appleton, WIthe corps has rarely used geocells in flood protection
projects and had never used it for constructing earth-retention
walls along streambanks.
In one location
in Molly Anns Brook, design velocities approaching 20 ft./sec.
along 300 ft. of a sharp bend in the channel would traditionally
have required a 54-in.-thick layer of riprap. Seeking a more economical
alternative, the corps first considered using cabled concrete mats,
previously used on a separate phase of the project. The final design,
however, called for a single, 4-in. layer of Prestos perforated
Geoweb cellular confinement system (geocell) filled with low slump
concrete and underlain with a nonwoven geotextile, which was adequate
to protect the bend while still reducing labor, excavation, and
materials costs.
In the other location,
a geocell system was used to construct a 400-ft.-long gravity wall,
an alternative to a more expensive reinforced concrete retaining
wall. The corps used perforated, 8-in.-high geocell layers filled
with compacted soil or aggregate to construct the wall along the
right bank of the brook. Designed to withstand flash flooding and
high velocities during its 50-year design life, the wall ranges
from 9 to 14 ft. high and is protected from scour by a 4-in. concrete-filled
geocell along its base.
The corps estimates
the methods used saved $80,000 over more traditional solutions.
This article takes a close look at how geocell technology was incorporated
in the construction of the channel lining and gravity wall.
Channel Lining
In the channel bend,
polymeric tendons and 0.5-in.-diameter steel bars anchored the geocell
sections to the 1:2 channel sideslope. The factor of safety for
slope stability controlled the spacing of the anchor system. The
tendons were spaced every 19 in. or every third cell, running perpendicular
to the brook. Varying lengths of 0.5-in.-diameter rebar, spaced
between 8 and 48 in., anchored the tendons to the slope, depending
on the depth to bedrock. If rock was located within 1 ft. of the
final grade, rock anchors were specified.
Perforations were
required in the interior geocell walls for two reasons: to allow
the concrete within the 4-in. depth to adequately bond between the
cells and to increase the frictional resistance between the concrete
and the cell walls. The internal bond was established by using the
perforated cell walls and filling the cells with a reduced-size
aggregate in the concrete. The perforations also allowed a high
factor of safety against the dislodging of individual concrete-infilled
cells in the channel, which is exposed to freeze/thaw cycles and
high-velocity storm events.
Anticipating bedrock,
the corps determined that any outcropping would be left in place
and the geocell system would be formed around the outcrop. Weep
holes were placed on 8-ft. centers near the bottom of the slope
to alleviate pore water pressure and uplift.
Installing the
geocell system required a minimal crew of three. After laying the
geocell on the graded slopes from top to bottom and anchoring it,
the contractor used a bucket on a tracked backhoe to fill the geocells
with concrete. Although the original design called for a trowel
finish, the smooth surface caused some safety concerns - students
from a nearby high school who cut across the channel could potentially
slip on a smooth surface - and a rough-raked finish was used instead.
This change in the concrete finish had a negligible impact on the
channel capacity and allowed the contractor to complete the job
in significantly less time.
To allow equipment
access along the streambed, the entire cross-section was completed
in two phases. First the channel sideslopes were graded, followed
by the streambed and low flow channel sections. The ability to complete
the cross-section in phases and not be concerned with cold joints
was helpful. The flexibility of the geocell system was beneficial
in constructing the low flow channel; the material had to be flexible
enough to cover the 8-ft.-wide x 2-ft.-deep trapezoidal channel
and maintain the integrity of the cells. The cells also act as expansion
joints throughout and prevent future uncontrolled cracking. The
300 lin. ft. of channel lining was completed in less time than it
would have taken an equal length of 21-in.-thick riprap.
Geocell Gravity Wall
The optimal use of a
geocell wall was in an area where the elevation of rock surface
was known to vary greatly. Essentially, a gravity wall had to be
designed for the greatest anticipated height, then modified in the
field for varying heights depending on the elevation of the rock.
The design of the
wall was an iterative process between the corps and InterSol Engineering
Inc., consultants for Presto Products. The wall was designed as
a conventional gravity wall composed of 8-in.-deep geocell layers.
Geocell layers extended from the face into the bank a distance of
3 to 7.5 ft. Each layer of geocell was set back 2 in. from the face
of the underlying layer. The slope of the front face of the wall
was 1:4. The design called for filling the cells with the native
silty sand and gravel materials except for the outer five cells
of the first five geocell layers; these cells were filled with 0.75-in.
stone. The concern was that the exposure to constant flows could
cause loss of material in the wall. The final stream grade was established,
and the drawings reflected only the one visible rock outcrop along
the 400-ft. length.
The wall was designed
to accommodate several required pipe penetrations for local stormwater
outfalls. In addition, a foundation drain was included to collect
any groundwater flows from behind the wall.
Because the wall
would frequently be subject to high water velocities, scour along
the toe of the wall was a major concern. A 4-in.-thick layer of
geocell (the same as used in the channel lining), 8 ft. wide, was
included at the base of the wall and filled with concrete.
To improve the
appearance, a solid tan geocell material was used on the face of
the exterior walls. In addition, the 2-in. setback in each layer
provided space for the outer cells to be filled with topsoil and
planted with Virginia creeper, a hardy perennial vine. The open
front cells of each geocell section form horizontal terraces that
capture rainwater while controlling groundwater evaporation, creating
a natural environment for vegetation. Eventually, the entire wall
face will have a vegetated appearance.
Before excavation
to the final stream grades, the exact location and elevation of
the bedrock were unknown. Once the overburden was removed, the bedrock
was exposed under the footprint of the wall in four major areas.
Beginning at one end of the wall, layers of geocell were brought
up one level at a time. When outcrops protruded in the path of the
wall, the geocell was simply cut and the next layer started. As
the layers were constructed, the outcrops were eventually encapsulated
beneath additional layers of geocell. Outcrops that extended beyond
the face were incorporated in the final structure. Because of the
width of the channel in this area, impacts to channel capacity as
a result of the rock outcrops were acceptable.
Initially the design
called for filling the cells with native materials, but because
of the many large rocks in this material and the need to overfill
the cells for compaction, the geocell infill was changed to 0.75-in.
stone. Including stone infill alleviated the need for meticulous
compaction and removal of excess materials and rendered the drain
unnecessary. The effect of the free-draining stone, combined with
the perforated cells, allowed the entire wall to act as a drain.
Previous stability concerns regarding slow draining of the backfill
after a flood event were alleviated.
Inadvertent damage
to some of the exterior cells during construction demonstrated the
redundant nature of geocell wall construction. With the 8-in. horizontal
cell depth, a breach of an outer cell exposed the next cell completely
intact. Multiple cell breaches would be unlikely under even the
worst conditions.
Although the Molly
Anns Brook project required only 300 lin. ft. of concrete-filled
geocell channel lining and 400 lin. ft. of geocell gravity walls,
the project should be a springboard to future use of geocells in
flood protection and streambank erosion projects. The estimated
cost for design and construction of the geocell wall was less than
half that for an equal length of reinforced concrete retaining wall.
The channel lining was completed at about one-quarter of the cost
of a 54-in. riprap section of equal length.
Anthony J. DePasquale,
P.E., and Douglas Leatherman, P.E, are with the Philadelphia District
US Army Corps of Engineers in Cherry Hill, NJ. Randy Thomas, P.E.,
is with ACF Environmental in Richmond, VA.
|