|
By
Arthur H. Benedict, Guy Oliver, Robert Franklin,
and Ron Devitt

Since 1995, Redmond,
WA, has been a leader in requiring high levels of treatment to reduce
turbidity levels in construction stormwater. Located in the Puget
Sound region of western Washington (Figure 1), the city has a strong
stormwater management program to ensure that local salmon spawning
streams and other environmentally sensitive water bodies are protected
from stormwater runoff. Management of stormwater from construction
activities has been, and remains, one of the cornerstones of the
city's program.
Puget Sound's wet season
typically is from October through April. Although precipitation
patterns vary, long-duration events (three to seven days) that can
generate large quantities of construction runoff are not uncommon.
Best management practices (BMPs) that prevent mobilization of sediment
during construction are often the most effective and least costly
site stormwater management measures. Where such measures are not
practical, however, some means of sediment control is required.
Once mobilized, coarse
sediments can be removed by sediment control BMPs, such as detention
ponds and sediment traps. Fine sediments and clay-size particles
cannot be readily controlled using these conventional measures,
however. Thus the City of Redmond, working with the Washington State
Department of Ecology, local contractors, site owners, and technology
suppliers over the last eight years, has provided guidance for applying
three innovative treatment technologies - polymer clarification,
electrocoagulation, and chitosan-enhanced sand filtration (CSF)
- to remove fine sediments and clay-size particulates from construction
runoff at locations within the city (EES Consulting Inc., 2001,
2003; Economic and Engineering Services Inc., 2003).
Regulatory Environment
Stormwater management
at construction sites is regulated under the Clean Water Act and
provisions of the Pollution Prevention Act of 1990. Washington Administrative
Code (WAC 173-201A) states that for receiving waters, such as lakes
and other high-quality waters, discharges must not raise turbidity
by more than 5 NTU (nephelometric turbidity units) over background
when the background turbidity is 50 NTU or less or increase turbidity
by more than 10% above background when background turbidity is greater
than 50 NTU. Many water bodies in the state are subject to these
stringent standards.
The
Department of Ecology implements the state regulations through a
statewide general permit for construction activities (general permit)
issued under the National Pollutant Discharge Elimination System
(NPDES). The City of Redmond developed a technical manual that defines
specific policies and procedures applicable to stormwater management
and erosion control (City of Redmond, 1999). A key feature of the
city's stormwater management and control program - identification
of the need to provide high-level treatment of construction runoff
- is triggered when an applicant submits a stormwater pollution
prevention plan and preliminary construction documents for review
under the general permit. For the construction sites described in
this article, provisions for stringent turbidity control requirements
were added to site permits under state-issued administrative orders.
The Department of Ecology formed an advisory committee to develop
a protocol by which new construction stormwater treatment technologies
can be approved for general statewide use. Approved technologies
are posted on a Web site, thus eliminating the need for such administrative
orders with these technologies.
Why Raise the Bar?
The technologies described
in this article - polymer clarification, electrocoagulation, and
CSF - are capable of reliably achieving turbidity levels in treated
construction stormwater equal to 10 NTU or less. What are the benefits
of achieving such high-quality treated stormwater?
As previously noted,
stringent standards for turbidity must be met for many state water
bodies. Thus the primary benefit of requiring high-level treatment
is achieving water-quality and habitat protection. Another benefit
is improved overall site stormwater management. Contractors involved
with the technologies described herein reported that planning for
stormwater treatment fostered better scheduling of construction
activities and better overall site stormwater management. Contractors
also noted that through this early planning, opportunities to optimize
use of conventional BMPs were identified. Therefore the awareness
of stormwater management personnel was enhanced and personnel training
needs were identified.
Implementation of high-level
construction stormwater treatment also provides an opportunity for
construction to occur during the wet season. Construction otherwise
might be curtailed during the wet season in environmentally sensitive
areas because of concerns over the capability of conventional BMPs
to provide the necessary protection. The innovative technologies
employ fail-safe design and operating features to prevent inadvertent
violations of discharge limitations. Hence they provide a barrier
to turbidity release, allowing for wet-season construction in the
city.
How Is Treatment Accomplished?
Successful application
of polymer clarification, electrocoagulation, and CSF was accomplished
through careful planning, design, and operation of the treatment
facilities to ensure that they were integrated into overall site
stormwater management. As illustrated in Figure 2, construction
stormwater treatment involved five basic steps: interception and
collection of onsite runoff, primary detention of the untreated
runoff, treatment to effect turbidity reduction, secondary detention
of treated stormwater, and monitoring and testing prior to release
to the receiving environment. In addition, all sites were required
to install and maintain appropriate conventional BMPs to prevent
or minimize erosion during construction.

Primary detention facilities
required at each site served two purposes. First, by accumulating
and temporarily storing stormwater until treatment was needed, treated
flows were attenuated, and treatment facility sizing could be optimized.
Second, they served as sediment control BMPs to remove coarse particulates
such that subsequent treatment facilities were not overloaded with
sediment. Stormwater released from the primary detention facilities
still contained fine sediment and stable, clay-size particulate
suspensions that needed further treatment to meet the stringent
state water-quality standards.
In some cases, the primary
detention facilities were sized as permanent facilities to meet
postconstruction criteria. In other cases, detention capacity was
provided only for the construction phase. In the latter situations,
the primary detention facilities were either modified for postconstruction
use or decommissioned once construction was complete. Both lined
and unlined primary detention facilities were used at the Redmond
sites.
Figures 3, 4, and 5 present
flow schematics illustrating the basic treatment steps involved
in each technology. Regardless of the technology, the quantity of
runoff that accumulated in the primary detention facility at each
site was routinely monitored, as were forecasts of expected weather
events. Treatment was initiated based on this information and site-specific
criteria. Thus, although treatment facilities were maintained on-site
at all times during the period when generation of sediment-laden
construction runoff was expected, active stormwater treatment during
this operating period was intermittent.
Polymer Clarification
Figure 3 illustrates
a typical polymer clarification system employing two lined treatment
cells that treat stormwater in batches. Batch treatment begins by
filling Cell No. 1 with stormwater from the primary detention facility
(Cell No. 2 is empty). As Cell No. 1 is filling, an appropriate
dose of synthetic polymer is metered into the cell. The polymer
causes fine sediment and clay-size particles to form large particles
called "flocs" that can be gravity settled. All polymer
clarification systems in Redmond used the synthetic polymer Catfloc
2953. This is the only polymer approved for such use in Washington.

When Cell No. 1 is full,
inflow to the cell and mixing of cell contents is stopped. A settling
period follows. During the settling step for Cell No. 1, Cell No.
2 is filled and dosed with polymer. Once the settling step in Cell
No. 1 is complete, testing for residual turbidity, pH, and acute
toxicity (bioassays) occurs (see the section on monitoring and testing).
If testing is satisfactory, the contents of Cell No. 1 are released
to the environment and the fill-treat-settle-test-release cycle
is repeated. If the tests are unsatisfactory, stormwater is re-treated.
For the polymer clarification systems used in Redmond, the treatment
cells themselves served as secondary detention facilities; hence
separate secondary detention facilities were not required (see Figure
2).
Electrocoagulation
Figure 4 illustrates
a typical electrocoagulation system for construction stormwater
treatment. Following a decision to treat, stormwater from the primary
detention facility is pumped at a continuous and preset rate to
the electrocoagulation cells where fine sediment and clay-size suspensions
are subjected to an electrical field. The electrical field generates
flocs that subsequently can be removed by gravity settling. At the
Redmond sites, facilities referred to as tube settlers were used
for this purpose. Granular media filtration followed to remove fine
floc particles. Filtered stormwater then was pumped to the secondary
detention facility for temporary storage, monitoring and testing
prior to release to the environment through 10-micron cartridge
filters.

Chitosan-Enhanced
Sand Filtration
Figure 5 illustrates
the CSF system. Chitosan is a biodegradable polymer produced from
the chitin in crab shells. In its liquid form, it treats stormwater
in a manner similar to the synthetic polymer Catfloc 2953; that
is, it treats stormwater by forming flocs from fine sediments and
clay-size suspensions that then can be separated from the liquid
stream. The liquid chitosan used at the Redmond construction site
was produced by Vanson Inc. and marketed under the trade name Storm
Klear Liqui-Floc by Natural Site Solutions LLC.

During active treatment,
stormwater that accumulated in the primary detention facility was
pumped at a continuous, preset rate to a mixing chamber where liquid
chitosan was metered and rapidly dispersed into the stormwater at
an appropriate dose rate. Flow from the mixing chamber then was
directed to sand filtration equipment where flocs were separated
from treated stormwater. One-micron cartridge filters followed the
sand filtration equipment. They acted as a protective barrier to
prevent noncompliant stormwater from being discharged to the receiving
environment. As with the other systems, monitoring and testing were
performed prior to release of treated stormwater from the secondary
detention facilities.
Monitoring and
Testing
Monitoring and testing
requirements were site-specific. At a minimum, however, the turbidity
and pH of both untreated and treated stormwater were measured prior
to each release of treated stormwater. Also, bioassays typically
were required on the first five batches of treated stormwater and
then on every 1020 batches. Acute toxicity tests involved 24-hour
static bioassays using Daphnia magna (water flea) and 96-hour
static bioassays using Onchorynchus mykiss (rainbow trout).
Site Characteristics
The described treatment
technologies have been used at 12 construction sites in Redmond.
Table 1 summarizes site characteristics. Nine sites employed polymer
clarification, two used electrocoagulation, and one used CSF. Site
drainage areas were between 5 and 65 ac., and average slopes varied
from essentially zero to about 10%. All sites except one were for
new commercial developments; that one was for a new public transit
facility.
The operating periods
reported in Table 1 (1.7520 months) reflect the length of time
that the treatment facility remained on-site, whether or not active
treatment occurred. In some cases, treatment facilities were on-site
during more than one wet season. The treatment rates reported represent
the total volume of stormwater treated by the system (expressed
as gallons of runoff treated per acre of drainage area) divided
by the operating period, expressed in months. Thus they represent
the average treated runoff rate for each site (after detention).
Allowable release rates
to the receiving environment varied from 60 to 884 gpm. Higher values
were allowed only under extreme circumstances. Allowable release
rates typically were between 60 and 200 gpm. Allowable release rate
was an important site and treatment criterion because the release
rate determined in large measure the size of the detention facilities
required relative to site area, expected rainfall-runoff relationships,
and similar site-specific factors.
Treatment Performance
Turbidity Reduction
Table 2 illustrates the
turbidity reduction capability of each stormwater treatment technology
based on experience in Redmond. All technologies were able to reduce
construction stormwater turbidity to median levels below 10 NTU,
with the electrocoagulation and CSF systems yielding values at or
below 5 NTU. The maximum treated stormwater turbidities reported
for both the electrocoagulation and CSF systems were below 10, whereas
maximum values for the polymer systems were generally higher.
Demonstrated performance
of the treatment systems covers a wide range of untreated stormwater
turbidity concentrations. Median values of untreated (presettled)
stormwater were between 117 and 14,000 NTU for the polymer systems,
whereas lower values were experienced with the electrocoagulation
and CSF systems. There are more sites, a larger quantity of stormwater
treated, and a longer experience record (six years) for the polymer
systems than for either of the other technologies. The electrocoagulation
performance record includes experience at two sites over a six-
to nine-month period, and the chitosan system represents performance
over two and a half months. It is expected that the high performance
demonstrated by the electrocoagulation and CSF systems would be
maintained even with a longer period of record.
Control of pH
NPDES permit conditions
for the Redmond sites required that the pH of stormwater discharged
to the receiving environments be maintained between 6.5 and 8.5,
with a target of matching receiving-water pH. Although rainfall
tends to be acidic (Minton, 2002), contact with site soils frequently
resulted in construction runoff at the Redmond locations that tended
to be neutral. The main exception to this generality was during
periods when concrete pours for foundations and similar structural
components were part of construction activities. During these periods,
the pH of construction runoff frequently reached values of 11.0
or more. Control of pH was maintained either through the addition
of a neutralizer or by carbon dioxide dispersion. With only a few
exceptions, the pH of treated stormwater was maintained at all times
at all sites for the entire eight-year period of record.
Bioassays
As previously stated,
bioassays were required as part of routine monitoring and testing
at all sites. None of the stormwater treated and discharged failed
the acute toxicity criteria.
Sediment Disposal
All of the treatment
technologies generate sediment that must be disposed. Quantities
were small and varied depending on site-specific factors; accumulated
sediment typically remained in the treatment systems to enhance
floc formation and was removed when treatment facilities were decommissioned.
Sediments were tested to document that they were nonhazardous and
disposed either on-site or at a local landfill.
Treatment Costs
The cost of construction
stormwater treatment is site-specific. Actual costs associated with
polymer clarification were not readily available from site owners
because of the sensitivity to release of this information. Based
on the information provided, however, polymer clarification costs
varied from 0.8 to 1.5% of project construction costs. These values
include costs associated with construction of the batch treatment
cells and for labor, chemicals, sediment disposal, and monitoring
and laboratory activities. They also include the costs of primary
detention facilities at those sites where temporary, construction-phase
installations were used. The costs of primary detention facilities
that were sized for postconstruction use are not included.
Table 3 shows a breakdown
of polymer system costs. The breakdown is based on information from
four sites and represents the general cost levels associated with
each cost category. The largest single cost is associated with construction
of the treatment cells (and primary detention facilities if developed
for temporary construction-phase use).

Monthly unit costs, expressed
as actual cost per 1,000 gal. of stormwater treated per month of
operation ($/1,000 gal./mo.), were developed for the electrocoagulation
and CSF systems. For the two electrocoagulation sites reported (Table
1), monthly unit costs were $5.83/1,000 gal./mo. and $8.00/1,000
gal./mo. Equipment lease costs accounted for 60-75% of the total
costs. The values reported here do not include primary detention,
secondary detention, or site mobilization/demobilization costs.
Monthly unit cost for
the CSF site was $10.22/1,000 gal./mo. Approximately 30% of the
total cost was for system setup (sand filter materials, pipe, materials,
metering pump installation, labor, and equipment). Monthly operating
cost (equipment rentals, power, chitosan, and monitoring) accounted
for the remaining 70% of the total cost.
The monthly unit costs
reported here should not be indiscriminately applied to other construction
sites. These unit costs are sensitive to site-specific factors,
such as the quantity of stormwater actually treated, the length
of time treatment facilities and operations are required at the
site, and the treatment capacity provided at the site. This is illustrated
in the cost-sensitivity analysis for electrocoagulation found in
Table 4.

The analysis was prepared
for a 10-ac. site operating over an eight-month period that generated
treated runoff rates (see Table 1) between 20,000 and 60,000
gal./ac./mo. The analysis shows that monthly unit cost will vary
- in this case from $4.08/1,000 gal./mo. to $8.25/1,000 gal./mo.
- in response to the volume of stormwater actually treated. A similar
analysis for the CSF system, which treated runoff at an actual rate
of 10,100 gal./ac./mo., shows that the monthly unit cost would be
$5.11/1,000 gal./mo. rather than the $10.22/1,000 gal./mo. actually
reported if the treated runoff rate had been 20,000 gal./ac./mo.
References
City of Redmond.
Stormwater Management and Erosion Control Technical Notebook,
Issue Number 3. Stormwater Engineering Services Division. April
1, 1999.
Economic and
Engineering Services Inc. City of Redmond, Field Experience with
Alternative Construction Stormwater Treatment Technologies.
December 2003.
EES Consulting
Inc. City of Redmond, Washington - Polymer Treatment, Review
of Field Experience, Phase 3. July 2001.
EES Consulting
Inc. City of Redmond, Electrocoagulation Treatment of Construction
Stormwater. February 2003.
Minton, G.R.
Stormwater Treatment. Resource Planning Associates, Seattle,
WA. 2002.
Arthur
H. Benedict, Ph.D., P.E., is an associate with Economic and Engineering
Services Inc. in Bellevue, WA. Guy Oliver is lead construction inspector
and Robert Franklin is one of the Development Services Division
managers in the City of Redmond Public Works Department. Ron Devitt
is a facilities manager for general stormwater permits at Washington
State Department of Ecology.
SW
May/June 2004
|