|
A demonstration site
shows promise for BMPs in space-limited urban settings.
By Clay Emerson
and Robert Traver

In the spring of 2004,
an infiltration trench was built on the grounds of Villanova University
near Philadelphia, PA. Funded by the Pennsylvania Department of
Environmental Protections Growing Greener Program and the
EPAs Section 319 Nonpoint Source Pollution Management Program,
the trench is the most recent addition to Villanovas Stormwater
BMP Research and Demonstration Park. Other best management practices
(BMPs) include a stormwater wetland, a bioinfiltration traffic island,
and a porous concrete site (see the article Lessons in Porous
Concrete in this issue). All of the BMPs, including the infiltration
trench, are retrofits. Each site is instrumented and serves as a
research tool. The BMPs are currently under study through the EPAs
Section 319 National Monitoring Program.
 |
| Figure 1. Site before construction showing grading problems and consequent erosion |
Project Background
The construction of the infiltration trench began in the spring
of 2004, and monitoring was initiated in July. The BMP was constructed
in a small area between an academic building and a parking garage.
The area was considered unsightly by the university because of poor
grading (Figure 1).
The design for the infiltration
trench BMP included three main components. First, the sites
basic stormwater functions were to collect and infiltrate runoff
from the upper deck of the adjacent bi-level parking garage. Second,
the site was designed to provide sufficient research and demonstration
opportunities to study the BMPs hydrologic and water-quality
performance. Third, the infiltration trench was designed to improve
the sites aesthetic appeal and function for the university.
Initial Site Investigations
Originally the site was chosen because of its proximity to
the parking garage. The garage is used only by university staff
and does not receive any large truck or delivery traffic, so there
is little chance of a major hazardous spill. More investigation
was required, first to ensure that the general area was appropriate
for such a BMP and later to determine the specific location and
orientation of the trench. University plans were collected in an
effort to determine the various existing utilities and infrastructure
in the area. This was a particularly arduous task, because although
plans existed for both the garage and the academic building, there
were no plans specific to the common area between them. Onsite investigation
proved to be the only reliable method. The grassed area contained
three large electrical conduits, which were encased in concrete;
one single telephone line; two stormwater conduits; and an existing
stormwater inleta surprisingly dense network of utilities
for a grassed area only 45 feet wide. Ultimately it was the locations
of these utilities that determined the exact size, location, and
orientation of the trench.
During the early stages
of the design process, a site investigation and feasibility study
was performed. The results of this process showed that the site
was suitable for the installation of an infiltration trench. First
a test pit was dug to determine the depth to bedrock or water table
and to classify the local soil properties and their suitability
for stormwater infiltration. The depth to bedrock in the test pit
was approximately 6 feet. Several authors recommend that 4 feet
of soil are desirable between the bottom of an infiltration BMP
and bedrock. Therefore, the 6-foot depth to bedrock in the test
pit was a concern. Based on the location and elevation of a nearby
first-order stream, the depth to groundwater was estimated to be
about 15 feet. The test pit showed that there were 18 inches of
disturbed topsoil followed by an equally thick layer of undisturbed
and heavily weathered schist. The bottom 3 feet of the soil profile
were dominated by a light tan sand layer that appeared to have excellent
potential for infiltration. Soil samples were also taken from this
layer and later analyzed in a laboratory setting. The particle size
distribution of the soil sample classified the material as a loamy
sand according to the Soil Conservation Service Soil Texture Triangle.
An undisturbed 2-foot-deep step was left in the sand layer in which
to perform some basic infiltration tests.
A constant-head infiltrometer
was used in the test pit to estimate the soils infiltration
capacity. The apparatus consists of a 6-inch-diameter metal ring,
which is hammered into the soil to a depth of 3 inches. A long,
graduated water supply tube stands on top of the ring and maintains
a constant 6 inches of head on the soil surface. The flow rate is
then calculated directly using the graduations and a stopwatch.
The percolation test showed that the soil was able to absorb water
a rate of 8.1 inches per hour. The three-dimensional flow characteristics
associated with this type of infiltration test seem to be more appropriate
for the infiltration trench than they would be for some of the other
infiltration BMPs at Villanova. The trench is relatively small and
deep, and the near-vertical walls of the trench likely are responsible
for a large portion of the infiltration. Other infiltration BMPs
that have a larger and flatter soil-water interface seem to exhibit
infiltration rates closer to the soils hydraulic conductivity;
this is often much lower than a standard percolation test
would suggest.
 |
| Figure 2. Excavated trench showing monitoring wells and geotextile fabric liner |
After the initial site
investigations, the limiting factor appeared to be the somewhat
shallow depth to bedrock observed in the test pit. However, due
to the unexpected discovery of some of the utilities, it was decided
that the final location for the trench would be approximately 10
feet away from the test pit. This new location was directly downhill
along what was likely the original slope of the site. Therefore
it was hypothesized that the depth to the fractured bedrock would
be significantly larger. The final depth of the completed trench
is 6 feet. No bedrock was encountered by hand augering to an additional
4-foot depth within the base of the trench (10-foot total depth).
Although not directly
part of the infiltration trench project and funding, a retaining
wall was first constructed to alleviate the erosion of the steep
slope adjacent to the future location of the trench. The construction
of the wall was done prior to the excavation of the infiltration
trench to prevent potential compaction and the migration of sediment
into the newly constructed BMP.
Design and Construction
As previously stated, the first design objective of the infiltration
trench was its stormwater function. However, because of the projects
research and demonstration goals, there were many measures taken
that were specific to the sites monitoring and demonstration
purposes. These features include the installation of two monitoring
wells in the trench (Figure 2). Both wells contain a pair of groundwater
samplers, one at 2 feet and one at 4 feet beneath the bottom of
the trench in the undisturbed subsoil. One well houses a pressure
transducer, which enables the depth in the bed to be monitored.
Another monitoring-specific feature is the bench located against
the wall of the parking garage as shown in Figure 3. This bench
houses a small grit and trash separator, a baffle, and a V-notch
weir. The weir, in conjunction with a second pressure transducer,
allows for continuous inflow monitoring. The top of the bench is
locked and mounted on hinges for maintenance and demonstration purposes.
A tipping bucket rain gauge was also installed on the upper level
of the parking garage. All the instrumentation is wired to a datalogger
located in a secure area of the garage. Finally, information signage
has been installed at the site.
 |
| Figure 3. Completed infiltration trench with monitoring/pretreatment bench and picnic table. |
 |
| Figure 4. Original drainage configuration consisting of PVC drains and small concrete channels conveying runoff onto street. |
The third objective of
the design was to improve the sites aesthetic appearance and
functionality as a campus common area. Therefore, the infiltration
trench was overlain with EP Henry ECO Pavers, which provide a strong,
durable, and porous surface. Picnic tables were placed on the patio
created by the trench. The bench used to house the grit and trash
separator and the weir also provide additional seating for the students
and faculty that frequent the newly renovated common area.
Like the other BMPs in
the Stormwater BMP Research and Demonstration Park, the infiltration
trench was a retrofit. The garages existing stormwater system
consisted of PVC-piped gutters that were directly connected to the
street by small concrete channels as shown in Figure 4. Street inlets
in the area along with the overflow of the infiltration trench drain
to the stormwater wetland just downstream of the site. The original
PVC gutters were disconnected and rerouted to the infiltration trench.
There a crushed stone bed provides temporary storage while the runoff
is allowed to infiltrate the surrounding soil. The rerouted gutters
capture roughly a third of the parking garage runoff, resulting
in a 100% impervious drainage area of approximately 17,000 square
feet.
 |
| Figure 5. Porous paver surface of infiltration trench |
The trench is approximately
13 feet long, 10 feet wide at the top, and 6 feet deep. The trench
is filled with large clean-washed stone aggregate, approximately
3 to 6 inches in diameter. The crushed stone bed provides approximately
40% void space, which results in a total capacity of approximately
200 cubic feet of storage in the trench, or about 0.15 inch over
the drainage area. This relatively small capture depth was acceptable
because the contributing drainage area can be easily decreased if
it is determined to be too large by simply reconnecting the original
PVC gutters at the desired downspouts. To date, the drainage area
has not been decreased, and overflow generally does not occur until
approximately 0.5 inch of rainfall is observed. This is because
of the rapid infiltration rate observed in the observation wells
at the site. The stone bed is completely wrapped in a Class C geotextile
fabric. The fabric prevents the surrounding soil from migrating
into the stone bed and decreasing its effective storage. At the
top of the bed above the geotextile is a 2-inch layer of choker
stone overlain with ECO Pavers. Decorative 6- by 6-inch timbers
were used to outline the ECO Pavers. The pavers have nubs that evenly
space them and provide 17.4% open space according to the manufacturers
specification sheet. The ECO Pavers were donated to the project
by EP Henry. The open space between the pavers was filled with small
choker stone to complete the installation. See Figure 5.
A perforated four-way
PVC fitting at the top of the bed just beneath the pavers connects
to a 6-inch PVC overflow pipe, which carries flows in excess of
the beds storage capacity to a nearby existing storm drain.
However, the flow in the 6-inch overflow pipe is somewhat impaired
by the crushed stone in the bed. Therefore, in periods of intense
rainfall when the storage bed is full and the capacity of the overflow
pipe is exceeded, the ECO Pavers act as an additional overflow.
Excess runoff is allowed to flow up from between the pavers and
over 2 feet of grass and into the storm drain. This design feature
has worked perfectly and results in evenly distributed sheet flow
at fairly low velocity that has not caused any erosion of the small
grass strip between the trench and the inlet.
Conclusion and Recommendations
One lesson learned during the construction arose when the crushed
stone arrived at the site for installation. The stone was specified
to be clean washed. However, the stone clearly had not
been washed and contained fine sediment that could decrease the
life expectancy of the BMP. Fortunately, this was noticed before
placement of the stone. The dump truck was then driven to a contained
area where the bed was inclined and the stone was washed by a worker
using a hose. Although this process was time consuming, it was absolutely
imperative that the stone not contain significant amounts of fine-particle-size
sediment. This experience illustrates the importance of both clear
specifications and, most importantly, onsite supervision at similar
BMP construction sites. A comprehensive site investigation is very
important, especially if the project is a retrofit and there is
a possibility of encountering existing utilities. In all, very few
problems were encountered during the construction of the infiltration
trench. This demonstrates the importance of proper siting, a thorough
site investigation, and sound design.
The infiltration trench
is reducing erosive storm flows and nonpoint-source pollution to
the headwaters of Mill Creek. Additionally, the BMP is replenishing
local groundwater supplies and helping maintain baseflow in the
local first-order tributaries of Mill Creek. The long-term monitoring
being conducted at the site is providing detailed insight into the
performance of the BMP. This experience and performance data will
be used to better understand and implement similar stormwater BMPs
in the future. The extreme design limitations imposed by the relatively
small area with numerous utilities show that the infiltration trench
BMP is capable of being successfully retrofitted into some of the
tightest existing urban conditions. The trench, still only a year
old, has been the subject of numerous tours attended by students,
professors, regulators, watershed groups, and design engineers.
Acknowledgements
Funding for the project was provided through the Pennsylvania
Department of Environmental Protections Growing Greener Program
with continued support from the EPAs Section 319 Nonpoint
Source Pollution Management Program. This support does not imply
the endorsement of this project by the EPA or the Pennsylvania Department
of Environmental Protection. The design and construction of the
infiltration trench was overseen by the Villanova Facilities Management
Departments Executive Director Robert Morro. Special thanks
go to Project Manager Nick Grosso at Facilities Management, and
Erika Dean for her continued hard work and dedication to the project.
The authors also wish to thank EP Henry for donating the porous
pavers.
Robert Traver is a
professor in the Department of Civil and Environmental Engineering
at Villanova University and directs the Villanova Urban Stormwater
Partnership. Clay Emerson is a VUSP research associate.
SW
July/August 2005
|