|
An update on the Villanova
Urban Stormwater Partnerships demonstration site
By Robert Traver,
Andrea Welker, Michael Horst, Megan Vanacore, Andrea Braga, and
Leo Kob

This article provides
an update on the current status of the porous concrete surface for
the Villanova University Porous Concrete Best Management Practice.
Originally constructed in 2002, the original surface failed and
was replaced in 2003, providing valuable lessons learned as featured
in Stormwater magazine (Traver et al. July/August 2004, www.stormh20.com/sw_0407_villanova.html).
After a second winter, limited portions of the site failed a second
time and were replaced in October 2004, again providing valuable
lessons as to the use of this material. Street sweeping was performed
onsite and found to be a viable means of maintaining the porosity
of the concrete by removing fines and debris from the surface.
 |
| Figure
1. Villanova University porous concrete site. |
Project Overview
A porous concrete infiltration best management practice (BMP)
was constructed during the retrofit of an existing paved area in
the center of the campus of Villanova University in August 2002
(Figure 1). The contributing watershed area is approximately 50,000
square feet and is highly impervious, consisting of pedestrian walkways,
rooftops, and some grass areas. The rooftops and some adjacent paved
areas are directly connected to three separate rock storage beds
(4 feet deep) that are outlined by the porous concrete surface.
The rock beds are linked through piping systems to distribute the
runoff between beds and allow for overflow for major storm events.
The porous concrete surface is edged using decorative pavers with
the porous concrete outlining the site and standard concrete in
the center of the site.
Installation involved
demolishing the original site, extensive regrading, and construction
of the infiltration BMP (Traver et al. 2004). A strength additive
was used. The site was designed to capture and infiltrate the first
2 inches of runoff, thereby reducing downstream stormwater volumes,
streambank erosion, and nonpoint-source pollution. The project joins
the Villanova University Best Management Practice Demonstration
Park as both a research and a demonstration site (Traver 2002).
Funding for the project was provided through the Pennsylvania Non-Point
Source Pollution Section 319 Program, and the site has been designated
as an EPA National Monitoring site. Further information on this
and other projects can be found through the Villanova Urban Stormwater
Partnership Web site (www.villanova.edu/VUSP).
 |
| Figure
2. Demolished concrete on uppper bed. |
In October 2004, during
Villanova Universitys fall break, construction was performed
at the site to replace sections of the porous concrete that had
failed or were not functioning properly, approximately 40% of the
reconstructed surface (Figure 2). It was observed that the areas
of porous concrete that had failed were from the later parts of
each individual pour, and that the first portion of each pour was
in acceptable to good condition. It had also been observed during
the original reconstruction that the end of each pour was less malleable
and extremely hard to work. Because only the top layer of the porous
concrete had failed, it is speculated that impermeable layers were
formed at the end of the pours, allowing freeze/thaw to occur.
 |
| Figure
3. Sections of removed porous concrete. |
Demolition began onsite
on October 12, 2004, with the uppermost bed. Twelve sections of
porous concrete were removed from the site (Figure 3). The sections
to be replaced had been marked prior to demolition by Villanovas
Facilities Management Office. Each section was saw-cut and subsequently
jackhammered to break up the porous concrete. The large chunks that
were removed appeared to be in good condition other than at the
surface. The large pieces were removed by hand, and some of the
gravel was shoveled out. This process did produce some fines and
gravel, but the magnitude was not substantial enough to clog the
pores and prevent water from infiltrating the bed. The demolition
also ripped up the joints between the porous concrete and the standard
concrete, which were to be replaced during pouring. Demolition was
completed at the end of the first day.
Four test pads had been
poured on Villanovas campus prior to the reconstruction in
2003 and were reevaluated before this renovation. Two of these pads
were formed with the same proprietary additive used in the original
and the 2003 pour, and the remaining pads used the Florida
mix, a standard porous concrete mixture, with no proprietary
strength additive. Because all four pads had remained in good condition
and had maintained their porosity, it was decided that the strength
additive that had been used in the previous pours was not necessary.
 |
| Figure
4. Hand-troweling the porous concrete. |
Pouring began at 6 a.m.
on October 13 in the upper bed. The expansion joints had been replaced,
marking each separate porous concrete pad. Initially, the pour from
the first mixer appeared to be too gravelly and dry. The placement
was halted, and workers spread out what had already been poured.
The remaining concrete was mixed in the drum for an additional period
of time and the pour was resumed. This pour was a much better consistency,
and they began again and worked along in small sections. The mixture
was poured 1.5 inches above the surrounding surface, as opposed
to 0.5 inch higher as in the reconstruction in 2003, so that a roller
with higher compaction could be used. The higher compaction allowed
the workers to get the porous concrete flush to the standard concrete
already in place without the elevation difference that was noted
during the previous construction. A hand trowel was used after the
porous concrete was raked into place to ensure the pour was even
and filled all gaps (Figure 4). The concrete sections were then
quickly compacted with the roller, which was hosed down each time
before passing over the concrete to prevent the concrete from sticking
to the roller.
 |
| Figure
5. Rolling the porous concrete. |
 |
| Figure
6. Wet burlap covering. |
On the first section
poured, a hand tamper was used preceding the roller, presumably
to compact portions of the porous concrete at the edge to ensure
that it was flush with the standard concrete. However, the roller
itself seemed to be accomplishing this, so this practice was not
continued. In addition, on another section the contractor attempted
to have water continuously flowing from the roller, rather than
having it sprayed on the roller by hand, but this produced a smooth
(nonporous) surface because the porous concrete became too hydrated
and created an impervious section (Figure 5).
After compaction, each
section poured was covered with wet burlap strips (Figure 6). Because
this material is heavier than the plastic that had been used in
the previous construction, it remained in place over the concrete
throughout the recommended 48-hour period and allowed for better
hydration.
 |
| Figure
7. Nonpourous area at end of truck. |
 |
| Figure
8. Villanova University vacuum street cleaner. |
The second mixer at the
site had material of a similar consistency to that of the first
mixer, but at the end of the second mixer the remaining material
that flowed down the chute was extremely wet and gravely, leaving
water ponding on the surface of the pad (Figure 7). This section
was removed and repaved when construction resumed on October 16
at 6 a.m., following a two-day delay because of adverse weather
conditions. Paving was completed on the second day of pouring. It
was observed that the Florida mix was much easier to pour than the
previous mixture, and no problems with stiffening occurred during
the pours.
Once the porous concrete
had cured for approximately 48 hours, the burlap strips were removed.
The color of the new sections was fairly consistent and close to
that of the existing sections. It is believed that over time the
color will even out further. A few small sections where the different
compaction techniques were attempted do appear less pervious, but
overall the new sections appear to be in good shape, and their effectiveness
looks promising.
It is generally recommended
that porous concrete surfaces be vacuum-swept at least twice a year
to keep the concrete free of pore-clogging debris. Street sweeping
was performed on the Villanova site in August and December 2004
(Figure 8). This cleaning was very successful in removing the particles
that could potentially clog the porous concrete. The porous concrete
was visibly cleaner after the street cleaner passed over it, and
the removed debris could be seen in the truck.
Villanova Urban Stormwater
Partnership
The mission of the Villanova Urban Stormwater Partnership is
to advance the evolving comprehensive stormwater management field
and to foster the development of public and private partnerships
through research on innovative stormwater management BMPs, directed
studies, technology transfer, and education.
Acknowledgments
Funding for the project was through the Pennsylvania Non-Point
Source Pollution Section 319 Program. This support does not imply
endorsement of this project by the EPA or the Pennsylvania Department
of Environmental Protection. The design and construction was overseen
by Robert Morro and Leo Kob of Villanovas Facility Management
Office. The design firm for the infiltration portions of the project
was Cahill Associates from West Chester, PA. The site contractor
was N. Abbonizio Contractors.
References
Traver, Robert. 2002. Development of a BMP
research and demonstration park. 9th International Conference on
Urban Storm Drainage, Environmental and Water Research Institute,
ASCE.
Traver, Robert,
Andrea Welker, Clay Emerson, Michael Kwiatkowski, Tyler Ladd, and
Leo Kob. 2004. Villanova
Urban Stormwater Partnership: Porous concrete.
Robert Traver and
Andrea Welker are professors in the Department of Civil and Environmental
Engineering at Villanova University and direct the Villanova Urban
Stormwater Partnership (VUSP). Michael Horst is the VUSP research
associate, and Andrea Braga and Megan Vanacore are graduate assistants.
Leo Kob is with Villanovas Facility Management Office.
SW
July/August 2005
|