|









|
|
|
Demonstrating low-impact
development BMPs in the Midwest
By Andrew J.
Sikich and Patrick D. Kelsey
The Morton Arboretum
is located in unincorporated DuPage County, IL, immediately adjacent
to the Village of Lisle. It has been located there since the 1920s
and has a long, proud history of preserving and enhancing the environment
and in educating the general public about trees, shrubs, and other
plantings. Traditionally, it was viewed as primarily a research
facility, with attendance mostly by those who already knew it well.
The only exception to this was significant attendance by the general
public during the fall color season.
In the 1990s, the arboretum
board of directors wished to increase visitation by the general
public in an effort to bring their message to more of the mainstream
populace. They underwent a large-scale planning process and developed
a 20-year master plan for the build-out of a new core area, with
additional gardens and visitor stations throughout the grounds (Figure
1). As a part of this master plan, a large new visitor center
was proposed. The new visitor center would be immediately adjacent
to several new gardens, including a maze garden and an extensive
childrens garden. These new gardens and the visitor center,
it was hoped, would bring a much larger year-round visitation to
the arboretum.
A new parking facility
would need to be constructed for the anticipated increase in visitors.
The lot needed to handle approximately 500 cars, or roughly three
times the capacity of the existing parking facility. This parking
lot posed a challenge, as the visitor center was located immediately
adjacent to Meadow Lake and the East Branch of the DuPage River.
The parking facility would be situated between these two bodies
of water. Meadow Lake was simultaneously undergoing a cleanup and
restoration project, partially funded by a grant from the Illinois
EPA (IEPA) Clean Lakes Program. The idea of constructing a 5-acre
asphalt parking lot next to Meadow Lake, and in the floodplain of
the East Branch of the DuPage River, did not seem to uphold the
goals of the Clean Lakes Program. Such a parking lot would produce
a significant concentration of pollutants, which would immediately
drain into Meadow Lake and subsequently the river. In addition,
the asphalt parking lot would heat the water, thereby degrading
the biodiversity and ecosystem in the downstream watercourses. Given
these factors, the arboretum decided that a green parking
lot would be the best solution to this problem.
To facilitate construction
of the lot, the arboretum applied for and received a 319 grant from
the IEPA, to be used for the construction of best management practices
(BMPs) within the parking facility. The grant was a 60%/40% matching
grant, for which the arboretum could receive up to approximately
$1.2 million for the design and construction of the parking lot.
The grant application was general in nature and listed several BMPs
that could potentially be incorporated into a parking lot. Thus,
upon receipt of the grant, the design team was charged with the
task of weighing the different BMPs and deciding which ones were
most appropriate for this project.
Selecting BMPs
Once the grant had been awarded, the arboretums design
team began the task of selecting the appropriate BMPs. The goals
were simple: reduction in overall stormwater runoff and improvement
in downstream water quality. The idea was to produce a parking lot
with the exact opposite effect of the standard asphalt parking lot,
which typically increases stormwater runoff and degrades downstream
water quality. For the design team to make educated decisions on
which BMPs would function the best on this particular site, they
needed to analyze many site conditions, such as soils, existing
drainage, floodplains, and wetlands. Once all the site parameters
were defined, a site plan could be put together that would produce
the desired amount of parking, with enough room left over for whatever
BMPs were selected.
Soils were analyzed through
the use of geotechnical borings, which were scattered throughout
the proposed area of the parking lot. In general, it appeared as
though the site was previously used for the distribution of overburden
from the excavation of Meadow Lake. Meadow Lake had been a borrow
site for the construction of Illinois Route 53, some 50 years earlier.
Apparently, soils that were not suitable for roadway embankment
had been cast aside in the general area of the proposed parking
lot. Most of the borings showed approximately 3 to 4 feet of unsuitable
material lying on top of in situ clayey sands and gravels. The design
team determined that once the overburden had been removed, the existing
clayey sands and gravels would be permeable enough to infiltrate
significant amounts of stormwater runoff.
An analysis of the groundwater
in this area had already been performed as a part of the Meadow
Lake project. The data generally showed a groundwater elevation
of approximately 665.0 feet (feet above mean sea level, NAD 27),
with significant fluctuations, which did not generally rise higher
than elevation 666.0 feet. The groundwater in this area is heavily
tied to the water surface elevation in the East Branch of the DuPage
River and generally flows in the same direction as the river, from
northeast to southwest.
The base flood elevation
(BFE) was plotted on the existing topographic survey. It was fairly
clear that the majority of the parking lot would need to be within
the floodplain of the East Branch of the DuPage River. This posed
a design challenge in that local ordinance requires no more than
12 inches of water over any parking lot surface during the 100-year
flood event. This set the minimum elevation for the parking surface
at 672.1 feet, exactly 1 foot below the BFE of 673.1 feet. Thus,
in order to minimize the amount of floodplain fill and minimize
the amount of compensatory storage required for the project, the
parking lot needed be installed at a relatively flat slope. In addition,
because of the 3 or 4 feet of existing unsuitable soil located in
the area of the proposed parking lot, a sizeable amount of structural
fill would be required to raise the lot to elevation 672.1 feet.
Once all of the existing
conditions were investigated and to the extent possible plotted
on the existing topography, the site planning process began. The
goal was to provide the maximum amount of parking within the space
provided, with maximum space left over for BMPs. The arboretum planning
staff developed a plan with long, linear medians separating each
parking bay from the next. These medians generally stretched from
southwest to northeast. The minimum median width was 9 feet from
back of curb to back of curb (B-B), with the maximum width being
approximately 15 to 20 feet. A 30-foot buffer was provided between
the parking lot and the edge of the proposed Meadow Lake. As expected,
about three-fourths of the parking lot would be within the BFE of
the East Branch of the DuPage River. Once the site plan had been
established, the design team analyzed several BMPs for use with
the project. These included but were not limited to permeable pavement,
bioswales, level spreaders, created wetlands, vegetated channels,
grass filter strips, and vortex-type oil traps.
Bioswales
The first BMPs selected were bioswales. The long, linear
medians and the permeable existing soils made them an obvious choice.
The bioswales function is to absorb stormwater and filter
it, using plants and permeable soils to trap heavy metals and other
pollutants prior to their entering the groundwater. The project
was tailor-made for bioswales. The 9-foot medians, being long and
linear, gave the team a great opportunity to drain the parking lot
into the medians. Because the parking lot needed to be built on
a minimum of 3 to 4 feet of fill, structural, permeable fill could
be used in lieu of clay to allow stormwater to run through the soil
and into the existing subgrade, thereby reducing total stormwater
runoff. The bottom of the unsuitable soil that needed to be removed
from this site was at approximately elevation 668.0 feet. This was
an important elevation because with the groundwater at roughly elevation
665.0 to 666.0 feet, the design would provide the minimum 2 feet
of separation required by the IEPA for groundwater protection. This
separation helps ensure that any impurities or contaminants are
filtered by the soil before runoff enters the groundwater.
Permeable Pavement
Once it was decided to include bioswales in the design
of the parking lot, a lengthy discussion, held over several weeks
time, was conducted regarding the benefits of permeable pavement.
During this time, all members of the design team pursued a quest
for information on the various types of permeable pavement and the
investigation of how these pavements would function given the requirements
of the arboretum. The arboretum staff desired a parking lot that
could be in use year-round. This, of course, meant that the pavement
surface would need to be durable and plowable. In addition, the
location of the bus parking area and visitor center truck dock required
that a significant portion of the parking lot be structurally designed
to withstand heavy truck and over-the-road bus loading. These factors
seemed to rule out products that were primarily substructure support
with grass or gravel placed on top, as they would not be plowable
and did not seem to have the structural integrity to withstand the
heavy vehicles. Thus, the design team focused on permeable concrete
paver units. Porous asphalt and concrete pavers were initially investigated,
but the majority of the research studied indicated that they tend
to clog within three to five years of installation and are quite
difficult to clean once they have become clogged. In addition, some
of the research indicated that in freezing climates, black ice could
form as droplets of water are retained at the surface of the pavement,
creating small, icy domes. This could create a situation that could
either become dangerous or require the arboretum to excessively
apply de-icing materials, which as a policy it tries to minimize.
Thus, based on the research investigated at the time, the product
of choice became the interlocking, permeable concrete paver.
Interlocking concrete
pavers are extremely durable and very high-strength. Their interlocking
nature gives them the ability to withstand heavy traffic loading,
and the high-strength concrete from which theyre made (8,000
to 11,000 psi) gives them durability and the ability to withstand
heavy point loading. The pavers themselves are L-shaped, with notches
in strategic locations that, when the pavers are pieced together,
form openings approximately 1 inch square. These openings are filled
with uniformly graded washed stone, which allows stormwater to flow
through the voids and into the base course and sub-base of the pavement.
Research indicates that this type of pavement acts as an excellent
filter to trap heavy metals and other pollutants from the initial
runoff in the majority of rainstorms. Coupled with the fact that
the project site had a highly permeable in situ sub-base, permeable
pavement seemed like an obvious choice.
It was determined early
in the design process that much of the pavement would need to be
heavy-duty and would be more expensive than typical parking lot
pavement, and the installation of the pavers would initially be
much more expensive than asphalt. The Arboretums 319 grant,
however, would cover 60% of the cost of the pavers and the entire
pavement section, because permeable pavement is a BMP. Asphalt pavement
is not a BMP and therefore would not necessarily be covered by the
grant. Nevertheless, the initial cost of the paver installation
was so significant that it had to be seriously considered in the
decision to select permeable pavement for use on this project.
The arboretum will own
and maintain its parking lot for many years into the future. Thus,
the life-cycle cost of permeable pavers versus asphalt was a significant
consideration in the decision to install the pavers. The sub-base
installation would be required in either case, due to the significant
depth of the existing unsuitable soil, so it was removed from the
life-cycle cost analysis. The pavement structure included in the
analysis was the wearing course and gravel base. Initial installation
cost for asphalt averaged about $17 per square yard for both heavy-duty
and light-duty pavements. The initial installation costs for the
permeable pavement system was approximately $42 per square yard,
or roughly two and a half times the cost of the asphalt system.
However, based on actual installations and research performed throughout
Europe and Australia, the lifespan of the concrete paver system
is expected to be at least 50 years. Thus, a 50-year life-cycle
cost analysis was performed.
Obviously, asphalt parking
lots do not last 50 years, especially in freeze/thaw climates. Frequent
crack filling and overlaying, and at least one reconstruction, will
be required within a 50-year span. Conversely, the maintenance required
on a permeable concrete paver system is minimal, limited generally
to restriping and the occasional cleaning of the aggregate within
the 1-inch holes. The latter need to performed only on a case-by-case
basis, depending on how the pavement is performing. In the case
of the arboretum, it was anticipated that this may need to be done
approximately every three years, and would probably cost around
$1,000 per application. The cost of restriping was considered the
same in both the asphalt and the paver system but was included in
the analysis, as it is a significant part of the minimal maintenance
required for the permeable pavement system.
After factoring in the
initial cost and anticipated maintenance, the total 50-year cost
(given in 2002 dollars) for asphalt was approximately $80 per square
yard, whereas the total 50-year cost for the permeable paver system
was $45 per square yard. Thus, because the arboretum will own the
parking lot and will need to maintain the parking lot for many years,
the paver system was a much better long-term choice. Based on this
analysis, it was decided to install the permeable paver system as
a BMP within this project.
Other BMPs
After the decision had been made to include both the bioswales
and the permeable pavement system, the remainder of the drainage
system could be further analyzed and additional BMPs selected. Because
the bioswales and the permeable pavement both function well as infiltration
systems, the fill that was used as a sub-base for the parking lot
should be permeable as well. Thus, the design for the entire sub-base
of the parking lot is a uniformly graded, washed, granular base.
This provides significant stormwater storage and the ability for
infiltration into the in situ soils. It was decided to use perforated
storm sewers along the length of each bioswale so that any stormwater
runoff entering the storm sewer system would still have an opportunity
to irrigate back into the sub-base and infiltrate the ground. To
assist in this process, a control structure would be installed at
the downstream end of the system to help restrict the flow of water
and allow it more time to infiltrate the ground. In the event that
this sub-base became overly saturated and needed to be drained,
the control structure would be designed to allow for easy access
and removal of the restriction so that the perforated storm sewers
would no longer irrigate the sub-base but help drain it. This would
help ensure that the arboretum would have not only an excellent
BMP in its pavement system but also a fully functional heavy-duty
pavement system with the ability to provide an extremely well-drained
base course when necessary.
The sewer system still
needed to be designed to meet the local ordinance requirements,
because at the time there were no credits given in runoff coefficients
for the installation of a permeable pavement. Thus, a relatively
large (30-inch-diameter) storm sewer drained the parking lot into
Meadow Lake. It was not desirable to install a typical flared end
section and lined riprap apron at the end of this system, as it
seemed in conflict with the green parking lot concept. Thus, a created
wetland/level spreading pool system was designed at the downstream
end of the storm sewer system. This system would provide a final
polishing pool and created wetlands to help filter out impurities,
and it would act as a level spreader to help eliminate point discharge
into the lake.
In addition to all of
the BMPs incorporated into the parking lot design, another storm
sewer system, which drained an adjacent traditional asphalt parking
lot and some other parts of the core area, also discharged into
Meadow Lake. With all of the BMPs designed as part of the main parking
lot, it did not seem appropriate to install a typical flared end
section at the end of this storm sewer system. Thus, a level spreader
system was designed to help dissipate energy and minimize erosion
at the downstream end of the system.
Design Details
Bioswales
A typical bioswale cross section was developed
using the 9-foot B-B median width. The concept of the bioswale is
to collect stormwater and allow it to infiltrate the constructed
soil, where it is either used by plantings or percolated through
the soil prior to overflowing into a storm sewer system. The desired
depth of ponding is no more than 0.5 foot. Therefore, the rims of
the catch basins along the storm sewer system are set at an elevation
0.5 foot above the bottom of the bioswale.
The initial concept was
to provide a concrete pavement edge, without a curb, to allow the
stormwater runoff to sheet flow into the bioswales, thereby minimizing
any concentrated flows and the resulting erosion. However, this
would require the installation of wheel stops at every parking stall
along the bioswales. Due to the large number of parking stalls and
the maintenance associated with wheel stops, this was not desirable
for the arboretum. Therefore, a barrier curb was incorporated into
the design. The challenge to the design team was to provide the
barrier curb but to minimize the amount of concentrated flow into
the bioswales. The final design incorporated 3-foot gaps in the
barrier curb, located along parking lot stripes to avoid the potential
for small vehicles or motorcycles to drive into the bioswales. These
gaps are spaced no more than three stalls (27 feet) on center. This
distance was a good compromise between having too many gaps, effectively
eliminating the curb, and having too long a distance for stormwater
to travel and concentrate. The curb line along the bioswales was
primarily level due to the floodplain restrictions, so the slope
required to direct stormwater along the gutter line to these gaps
was entirely provided within the curb structure itself. The top
of curb and the edge of pavement remain level, while the gutter
pitches from the middle of the solid curb section to each gap at
a slope of approximately 0.5%. Special grading details had to be
provided to ensure that the contractor would construct this correctly,
as this is not a standard curb installation.
Once stormwater enters
the bioswale, it collects in the bottom and ponds to a depth of
0.5 foot prior to overflowing into the storm sewer. The sideslopes
of the bioswale are graded at a 3:1 slope, from the edge of the
curb gaps down to the swale bottom, which is approximately 1 foot
below the edge of pavement. This allows for a 3-foot-wide flat bottom
down the center of each bioswale. A special soil mix was designed
for the bioswales to allow for an adequate growing medium and the
appropriate amount of infiltration.
The soil mantle was created
using a constructed sandy loam soil mix with approximately 5% coarse
organic matter content. Specific criteria for many soil properties
were prepared based on the site criteria, available soil mix components,
and mantle thickness. Several key chemical and physical characteristics
were necessary for the soil mantle to function as a chemical as
well as a physical filter. The organic matter needed to be uniform,
coarse, and fully mature. Organic matter maturity was tested using
a Solveta compost maturity test. The in situ pH of the final soil
product needed to be between 5.5 and 7.5. This was difficult to
achieve in northeastern Illinois, where the sands are typically
alkaline with a pH between 7.5 and 8.0. The amount of fine-particle
alkalinity was reduced by using washed, medium-grained sand that
had the fines removed. This was sufficient to create a sand pH in
the upper end of the acceptable range. The soil was mixed offsite
at a batch plant and backfilled with moderate compaction. Filter
fabric was not used to avoid two conditions: blinding, and the creation
of a perched water table. Minimal settling into the stone was observed.
The plantings designed
for the bioswales were specifically selected to handle both inundation
and drought conditions. This was a difficult challenge that took
many months of discussion by the design team. The ultimate design
also incorporated an irrigation system to allow the plants to be
watered in times of drought.
Lighting and storm sewers
also needed to be incorporated into the cross section. For obvious
reasons, it was not desirable for light-pole bases to conflict with
the storm sewer, so the storm sewer and catch basins were placed
on the opposite side of the bioswale from the light-pole bases.
This obviously impacted and directed the appropriate locations for
any trees within the bioswales, which needed to be located so as
not to conflict with surface drainage, storm sewers, or lighting.
All of this was accomplished within the 9-foot section allowed by
the plan. The final bioswale cross section is shown in Figure
2.
Permeable Pavement
Much forethought and discussion went into the design of
the permeable pavement cross section. As this type of pavement is
not yet commonly used in the midwestern United States and there
are no standards regarding permeable pavement and/or interlocking
concrete pavers in the Illinois Department of Transportation (IDOT)
Standard Specifications for Road and Bridge Construction (SSRBC),
the design team had to select sub-base, base, setting bed, and filler
aggregates for the pavement section. The aggregate under the pavement
needed to serve two purposes: Replace the unsuitable soils that
existed beneath the proposed parking lot section, and provide adequate
permeability to facilitate the infiltration of stormwater into the
in situ sub-grade. In order to meet the IEPA regulations with regard
to groundwater protection, a minimum 2 feet of separation between
the groundwater and the bottom of the excavation/fill was required.
Thus, using the conservative elevation of 666.0 for the groundwater
table, the bottom elevation for the excavation was set at 668.0.
In reviewing the soil boring data, this was determined to be adequate
to remove all of the existing, unsuitable soil. Thus, the parking
lot base elevation, or bottom of subgrade, was set at elevation
668.0.
 |
From the subgrade elevation
up to the bottom of the base course for the pavement, a uniformly
graded, crushed aggregate with no fines was desired. The coarse
aggregate #1 (CA1) designation in the SSRBC was selected. This material
is angular, crushed stone with no fines, ranging from approximately
1.5 to 3 inches. This material was used as fill from elevation 668.0
to the subgrade elevation immediately beneath the pavement base
course. Then, using the LockPave Pro software for the structural
design of interlocking concrete pavements, developed by Dr. Brian
Shackel, the design team proceeded to design the remainder of the
pavement section. Due to the strong interlocking nature of the pavers,
and the significant amount of aggregate sub-base being provided,
a minimal base course was needed. The material selected is SSRBC
designation CA7, which is basically a uniformly graded, crushed
aggregate approximately 0.75 inch, with no fines. The design team
anticipated that this material may be difficult to construct with
any level of accuracy because of its lack of fines. However, after
discussions with various contractors in the area, it was determined
that it would be possible to construct a thin layer of CA7 to an
acceptable level of accuracy. The minimum thickness that was desired
by most of the contractors consulted was 6 inches. A lift less than
6 inches in depth would be difficult to grade to the appropriate
elevation, but a lift of more than 6 inches might be difficult because
equipment tires might tend to sink. Thus, a 6-inch base course of
CA7 was selected for the pavement base course.
An experienced concrete
paver installer was consulted regarding the design of the setting
bed and pavers. The optimal setting bed was a 1.5-inch lift of three-eighths-inch
crushed aggregate with no fines, which most closely related to the
SSRBC CA16 designation. This material would also be suitable for
the filler material in the holes created by the pavers. However,
for aesthetic reasons, the arboretum staff desired a filler material
that more closely matched the paver color and chose a crushed granite,
mined in Wisconsin. The final cross section of the pavement is shown
in Figure 3.
There were no guidelines
in the local ordinances that would allow for a reduction in storm
sewer or stormwater detention sizing based on the use of the permeable
pavement system. However, the design team realized that there was
an extensive amount of stormwater storage located within the voids
of the aggregate material beneath the pavement section. Detention
storage for the entire project had already been provided in a separate
facility. Storm sewers were already being designed to handle runoff
in accordance with local ordinance requirements. However, because
the majority of the project was within the floodplain of the East
Branch of the DuPage River, floodplain compensatory storage was
needed. A separate facility was being designed in a downstream location
to handle compensatory storage for the majority of the core area
of projects. However, because of the extent of the parking lot project,
additional stormwater storage between the 10- and 100-year floodplain
elevations was needed. The storage provided within the voids of
the aggregate sub-base was calculated, using a conservative ratio
of 0.35. This provided a significant amount of the compensatory
storage needed beneath the pavement section. This storage could
be accessed several different ways via the perforated storm sewer,
the bioswales, or the pavement section itself. Therefore, the DuPage
County Department of Environmental Concerns was satisfied that this
storage would be accessed in a flood event greater than the 10-year
storm. Therefore, it was classified as compensatory storage within
the 10- to 100-year floodplain elevations, providing an enormous
secondary benefit to the project.
Perforated Sewers/Water
Level Control Structure
Perforated high-density polyethylene (HDPE) storm sewers
were selected for several reasons. They could be installed on a
slight radius to follow the bioswales, and they would infiltrate/exfiltrate
stormwater. A structure needed to be designed at the downstream
end of the system that would restrict the flow of water out of the
storm sewer system to allow it additional time to infiltrate into
the sub-base. Additionally, however, it needed to be easily maintained
and the restriction easily removable. This would ensure that, if
the sub-base were not draining quickly enough, it could be drained
more rapidly to maintain the pavement integrity. Thus, a water-level
control structure was designed utilizing a simple concrete baffle
with slots cast into it where 2- by 6-inch stop logs could be inserted.
The stop logs help restrict the flow of water but are not watertight,
allowing for the eventual draining of the system. If the system
needs to drained quickly, the structure is not very shallow and
the stop logs can be removed easily by hand. A detail of this structure
is shown in Figure 4.
 |
The storm sewers were
designed in the customary fashion to handle a 10-year storm event
at the pipe flowing full condition. It was not anticipated
that these storm sewers would actually need to function in this
manner, but again, local ordinance requirements dictated this design.
The storm sewers are pitched toward the water-level control structure
just as they would be in a standard design, allowing them to be
cleaned with traditional, readily available jetting equipment from
any downstream structure. Catch basins are located within the bioswales
to allow for the easy removal of sedimentation should any get trapped
in the system.
Created Wetland
and Level Spreading Pool
The downstream created wetland was provided for several
reasons. It acts as a final polishing pool or sediment trap, as
well as a very large level spreader, which helps reduce the erosive
effect of any significant flow. Wetland plants were selected for
both the upper level spreading pool and the lower created wetland
along the fringe of the newly constructed Meadow Lake. A cross section
of the created wetland/level spreading pool is shown in Figure
5. The level spreading pool is approximately 200 feet long,
which allows for significant energy dissipation of any flow entering
Meadow Lake at this location. The required plantings for this area
were incorporated into the Meadow Lake project to allow for a seamless
installation of plantings along the newly constructed shoreline.
Level Spreader
A level spreader was designed for the outlet of the traditional
storm sewer system, which drains an adjacent asphalt parking lot.
A 12-inch-diameter level spreader was designed to handle the more
frequent storm events. At a higher elevation, an overflow storm
sewer with a traditional flared end section was provided so that
if the capacity of the level spreader is exceeded, the storm sewer
system still drains adequately. The storm sewer was designed based
on a downstream tail water elevation slightly above the elevation
of the level spreader, to ensure that stormwater will not surcharge
any of the rim elevations in the upstream system. The level spreader
design consists of approximately 80 feet of slotted 12-inch HDPE
pipe. The slot is laid level from one end to the other, which allows
for a more uniform sheet flow and minimizes the potential of channelization
and erosion. Downstream of the level spreader, from the slotted
pipe to the waters edge, an apron of aggregate/soil mix (at
a 2:1 ratio) was provided and native plantings were incorporated
into the planting plan for the Meadow Lake construction in this
area. As a part of the Meadow Lake construction project, the shoreline
was additionally reinforced with turf-reinforcement mat (North American
Green C350). A cross section of the level spreader detail is shown
in Figure 6.
Construction
The construction effort for this project went very smoothly.
The combination of an excellent construction manager, a conscientious
contractor, and solid design plans provided a basis for very few
change orders and contractor requests for information. As with any
project that is not designed entirely using standard practices and
procedures, there were a few lessons learned.
This parking lot was
entirely constructed within the CA1 fill above the existing soils,
which forced the contractor to put careful thought into the scheduling
and sequence of construction. Storm sewers, for instance, were laid
on the existing subgrade in the open and covered with CA1 before
the installation of the remainder of the CA1 sub-base. Light pole
bases needed to be extended, making them a total depth of approximately
10 feet, so that 5 feet of the base was in the in situ soils prior
to the backfilling of the CA1 sub-base. This item was one of the
few change orders on the project.
One of the considerations
whenever constructing cast-in-place concrete curb and gutter is
the immediate backfilling of the curbs to prevent them from moving,
settling, or rolling backward. Because the curbs were constructed
far in advance of the bioswale soil mix being placed, there was
some concern that the curbs would roll backward upon the placement
of the pavers. The curbs were monitored closely, however, and the
contractor extended the CA1 sub-base an additional foot beyond the
back of curb to help prevent this from happening. Through careful
construction practices, no curb settled or rolled backward.
When the bioswale soil
mix was placed, the contractor had concern that the soil would migrate
into the CA1 sub-base. To prevent this, a layer of base course (CA7)
was added and the stone was compacted to lock the void space, thereby
producing the smallest voids possible. Soil was backfilled in lifts
so that the interface voids would fill with soil. This method has
been used successfully in other constructed soils and eliminates
the problems encountered with filter fabrics.
Finally, a discussion
was held after the installation of the pavement base course (CA7
layer). The general contractor was able to construct the base course
as designed to the tolerances required. This took some effort but
was achievable. The paver subcontractor had a somewhat difficult
time moving equipment around on the CA7 base course and requested
that the base course be thinner on the next project. However, through
conversations with both the general contractor and the paver subcontractor,
it was determined that the 6-inch lift was optimal, as the general
contractor confirmed the original decision that any lift thinner
than 6 inches would be difficult to construct to the required tolerances.
After more than a year
of using the parking facility, the arboretum is generally extremely
happy with it. Staff continually monitor the plantings that were
selected, and because the facility focuses on trees and plants,
they are able to monitor the progress of each species and can eventually
replace them if they feel these species are unsuitable for the bioswales.
Overall, however, the majority of the plantings originally selected
appear to be doing well. One practical issue that has been raised
occurs where two curb gaps are aligned on either side of a bioswale.
When this situation occurs close to the visitor center, it seems
that visitors use the opportunity to walk through the bioswale as
if the gaps were aligned for this purpose. Thus, on future projects,
it is desirable to make sure curb gaps are offset from one another.
This is not a major concern for the arboretum, as proper plantings
will likely deter visitors from walking through the bioswales in
these areas.
Research
Subsequent to the construction of the main parking lot, a joint
effort between the arboretum, Unilock of Chicago, and Christopher
Burke Engineering has been undertaken to research the effects of
this parking lot and the combination of the BMPs used. The research
has two main goals: first, to calculate the reduction in stormwater
runoff being realized by the downstream receiving system as a result
of each individual BMP, and second, to monitor the expected increase
in water quality.
 |
| Figure 7. Water Level Sensor in PVC Housing |
Several data-logging
transducers were installed at various locations around the parking
lot to monitor the flow of water from different portions of the
design. They were placed at curb inlets and in bioswales, and one
was placed in the immediately adjacent asphalt parking lot to provide
baseline measurements. The sensors have been calibrated, and take
readings every five minutes, which will produce tremendous amounts
of data but will help ensure that no storm event, no matter how
small, is missed. Figure 7 shows one of the sensor installations.
The sensor lies within the PVC housing and measures depth of flow.
This must be converted to a flow rate utilizing formula created
ahead of time.
Staff members from the
Morton Arboretum will read the sensors once or twice a month and
submit the data to Christopher Burke Engineering for analysis. Additionally,
arboretum staff members will collect runoff samples from both the
asphalt parking lot and the main parking lot as a basis for comparison.
Tests will be run on the stormwater to determine levels of various
pollutants, such as total suspended and dissolved solids, phosphorous,
zinc, copper, and cadmium. The anticipated result of this research
is a reduction in stormwater runoff and an increase in water quality
to the downstream receiving system. Research began in December 2004.
It is anticipated that a two-year study will be undertaken, with
final results being released in the early spring of 2007.
Summary
The Morton Arboretums main parking lot project was exemplary
from start to finish. The cooperative design process among the owner,
engineers, landscape architects, regulators, and contractors facilitated
an end product that is not only good for the environment but also
very functional for the arboretum. The EPA grant largely facilitated
this project and through its public outreach and education requirements
will help ensure the project is noted by the general public and,
ideally, used as a pilot project for others to model. It is our
hope that the successful implementation of the BMPs on this project
will help facilitate additional local research and increase the
confidence of local regulators and public officials to significantly
increase the use of such applications on a widespread basis.
References
Rollings, Ph.D., P.E., Raymond S., and Marian
P. Rollings, Ph.D., P.E., for Uni-Group USA. 1999. Design Considerations
for the Uni Eco-Stone Concrete Paver.
Shackel, Dr.
Brian. ©19982005 F. von Langsdorff Lic. Ltd. LockPave
Pro. Presented by Uni-Group USA.
Shackel, Dr.
Brian. 1990. Design and Construction of Interlocking Concrete Block
Pavements. London: Elsevier Applied Science.
Uni-Group USA.
2002. Uni Eco-Stone Guide and Research Summary.
Andrew J. Sikich,
P.E., is vice president and Patrick D. Kelsey, CPSSc/SC, is environmental
resources manager of Christopher B. Burke Engineering West Ltd.
in St. Charles, IL.
SW
November/December 2005
|